First Quarter Finance Procurement and Performance Report

Noted Executive 4 papers

The Executive noted this item on Thursday 5 October 2023. Below is the council's own wording, with the papers it was decided on.

Item24/19

Resolved

That the First Quarter 2023/24 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of the covering report be noted. 2. That the 2022/23 CFO Review of reserves as set out in item 12 of Appendix A of the report be approved. 3. That the approach to be taken for the governance and oversight of the efficiency programme be agreed.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive

Recommendations

2.1It is recommended that the Executive:

 Note the First Quarter 2023/24 financial, procurement and performance position detailed in Appendices A, B and C and summarised at 3.3 of this covering report.  Approve the 2022/23 CFO Review of reserves as set out in item 12 of Appendix A.  Approve the write-offs set out in Appendix D.  Consider and agree the approach to be taken for the governance and oversight of the efficiency programme. 3. Executive Summary

3.1This report summarises the Council’s performance and financial position after considering service activity up to the end of the First Quarter (i.e. 30th June 2023).

3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) & Appendix C (Performance).

3.3The position can be summarised as follows: Subject Headline Reference Finance The Finance headlines for the First Quarter are: Appendix A

Performance against Budget

 At the First Quarter stage the General Fund outturn for 2023/24 is projected to be £414,670 overspent.

Efficiency Programme

 No savings are programmed to be delivered in 2023/24 in line with the MTFP although a programme with five themes is being developed for the final three years of the MTFP to deliver £550k of net savings.

Housing Revenue Account

 The Housing Revenue Account is predicted to be in deficit (against budget) by £111,290 at the Quarter One stage.

Capital Programme

 The General Fund Capital Programme budget for 2023/24 as revised is £13.1 million. The projected outturn is currently forecast to be £367,050 underspent at the Quarter One stage.  The HRA Programme for 2023/24 as revised is £9.72 million. The projected outturn is forecast to be £9.62 million an overspend of £0.1 million compared to budget.

Treasury Management

 Cash investments held at 30 June 2023 totalled £17.4 million.  Council borrowing at 30 June 2023 totalled £63.777 million.  The Council’s net interest costs are forecast to be £214,400 under budget on the general fund and £56,360 over budget on the HRA.

Revenue Collection

 28.41% of Council Tax was collected by 30 June 2023, compared to 28.34% for the same period last year.  29.62% of Business Rates was collected by 30 June 2023 compared with 31.15% for the same period last year.  At the end of Quarter One the value of sundry debt over 60 days old was £91,232 which compares to £145,240 at 30 June 2022.

Procurement The Procurement headlines for the First Quarter are: Appendix B

 6 procurement activities were completed  The Procurement forward plan includes 49 procurement activities for completion/start in 2023/24 (either HPBC only or joint)  At the 30 June 2023, 74% of procurement activity undertaken was on the forward plan. Performance The Performance headlines for the First Quarter are: Appendix C  71% of the key performance indicators on track, with 70% performing better than at this point in the previous year.  The Council closed 23 complaints, and received 115 comments and 12 compliments in the First Quarter.

4. How this Report Links to Corporate Priorities

4.1The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/19Appendix A 871 KB Download
PDF
/19Appendix B 280 KB Download
PDF
/19Appendix C 1.7 MB Download
PDF
First Quarter Finance Procurement and Performance ReportReport 492 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 16 attended
AM
Councillor Anthony McKeownChair, present
DG
Councillor Damien GreenhalghVice-Chair, apologies
AB
Councillor Alan BarrowCommittee Member, present
GC
Councillor Godfrey ClaffCommittee Member, apologies
FS
Councillor Fiona SlomanCommittee Member, present
JT
Councillor Jean ToddCommittee Member, present
RB
Councillor Rob BakerCommittee Member, apologies
MT
Councillor Matt TaylorCommittee Member, present
AS
Andrew StokesOfficer, expected
NR
Neil RodgersOfficer, expected
SH
Sally HamptonOfficer, expected
MT
Mark TrilloOfficer, expected

All 16 on the meeting page

On this subject at High Peak

Search all
  1. First Quarter Finance Procurement and Performance ReportThis decision
  2. First Quarter Financial, Procurement and Performance Review 2025/26Noted
  3. First Quarter Finance, Performance and Procurement ReportNoted
  4. First Quarter Finance, Performance and Procurement ReportNoted
  5. First Quarter Finance, Performance and Procurement ReportNoted
  6. First Quarter Finance, Procurement and Performance ReportNoted

More from High Peak The Executive

All decisions
MeetingDecisionOutcome
27 Aug 2026 To resolve that the public and press be excluded from the meeting for the following items because there may be disclosure to them of exempt information as defined in Part 1 of Schedule 12A of the Local Government Act 1972.That the public and press be excluded from the meeting for the following items because there may be disclosure to the... Decided Open
6 Aug 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 11 June 2026 be approved as a correct record. Approved Open
6 Aug 2026 Forward PlanThat, subject to the above, the be noted. Noted Open
6 Aug 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
6 Aug 2026 Anti-social Behaviour, Hate and Neighbourhood Management PoliciesThat the Anti-Social Behaviour Policy, Hate Policy and Neighbourhood Management Policy, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies