23rd October 2023
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATES REPORT
HPK/2023/0286 – Land at Forge Works, Chinley
Chinley, Buxworth and Brownside Parish Council:
No comments.
Chapel Parish Council:
At our Planning Committee yesterday, it was unanimously resolved, re this application, to support the Planning Officer's written report to HPBC's Planning Committee.
Agent:
The following correspondence has been circulated to all Members of the Development Control Committee on the 9 th November 2023, which is summarised as follows:
Outline of planning history in relation to the Forge Works site, Compliance with Local Plan (LP) Policies S1 ‘Sustainable Development Principles’ through the provision of homes in sustainable locations making effective and efficient use of land whilst acknowledging Policy S1 also requires the provision of a range of economic development in sustainable locations, Consider LP E1 ‘New Employment Development’ is not directly relevant as the proposal is not seeking an employment use and references the extant permission for a live / work at the application site, LP Policy S6 ‘Central Sub-area Strategy’ is further considered irrelevant to the proposal given the site is not in an existing employment use whilst noting the policy also refers to supporting the development of new housing on sustainable sites within the built up area boundary, The reason for refusal primarily relates to LP Policy E4 ‘Change of Use of Existing Business Land and Premises’, however, state that the site is not in existing employment use and the extant planning permission for a live work unit is no longer required whereby the site is not allocated for employment use and therefore alternative proposals should be considered against the Development Plan, Highlights that the NPPF defines Use Class B1 as a ‘main town centre use’ falling within new Use Class E and therefore any planning application would require the applicant to meet with the sequential test stating that the Council would consider such uses appropriate in this location, Or, if the existing consent was built out, there would be nothing to prevent the building from being used by an alternative uses within Class E, Previous studies have identified the site location to be constrained for employment use, including its remote location away from centres of population, transport infrastructure issues and it being an out of centre site, As well, the introduction of an alternative employment use on the site to Use class B1 would have a greater potential to have an adverse impact on the residential amenity to the occupiers of the nearby dwellings due to the operating hours and vehicle movements to and from the site, The High Peak Housing and Economic Lands Needs Assessment (HELNA) undertaken in 2022 does not list the Forge Works site as available employment sites within the Borough and therefore consider LP Policy E4 is irrelevant given it does not form an ‘existing business or industrial land or premises’, Even if LP Policy E4 is considered to apply to the site, then the location is constrained (to comply with E4), and therefore there are other material considerations which indicate that planning permission should be granted for residential development, Indicative drawings have been submitted, showing one option of how the site could be developed to show how the maximum number of 9 units could be achieved on the site under the PIP regulations, and, The design, location and size of any proposed residential development falls to be considered under Stage 2 of the PIP process.
Case Officer:
Environmental Impact Screening (EIA):
The application does not fall within either Schedule 1 or 2 development thresholds.
Permission in Principle (PIPs):
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 420 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.