High Peak Borough Council
Cabinet, Tuesday 28 November 2023 at 1.00pm

UKSPF Delivery and Procurement Update

Decided Executive 1 paper

Cabinet decided this item on Tuesday 28 November 2023. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

DECISION: That delegated authority be granted to Executive Director (Place) in consultation with the Leader to make the contract award decisions for contracts which exceed the Council’s Procurement Procedure Rules thresholds for requiring a delegated decision for award of contracts.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet

Recommendation

2.1It is recommended that delegated authority is granted to Executive Director (Place) in consultation with the Leader to make the contract award decisions for contracts which exceed the Council’s Procurement Procedure Rules thresholds for requiring a delegated decision for award of contracts.

Executive summary

3.1Staffordshire Moorlands District Council has been awarded £3,428,937 under the Shared Prosperity Fund (SPF). Approval to the allocation of SPF to projects submitted to the Department for Levelling Up, Housing and Communities (DLUHC) was given in January 2023 with the final deadline for all spending to be achieved being March 31 st 2025. To date approximately 18% of the total allocation has been committed to projects that have now been created and against which SPF grant is now being spent.

3.2In order to ensure full expenditure of the SPF grant a number of projects will need to be procured by the end of February 2024. These are listed below at table 1 of this report. The time required to complete procurement and obtain approval under normal procedures for award as set out in the Councils Procurement Procedures Rules for values exceeding £186,000 (i.e. Delegated Cabinet Decision) would not permit enough time for contract approvals in in consideration of sufficient time to ensure that all SPF grant can be spent by the deadline. 3.3 It is considered and recommended that authorising delegated approval to make the award of contracts to the Executive Director (Place) in consultation with the Leader will speed up the procurement and contract award end to end process enabling grant expenditure to be maximised.

4.0How this report links to Corporate Priorities

4.1The report links to the following Corporate Plan priorities:

Aim 1: Help create a safer and healthier environment for our communities to live & work. Projects included in the SPF programme of projects will introduce energy efficiency measures to reduce the cost of living for some households and support the development and delivery of the arts and culture strategy.

Aim 3: Help create a strong economy by supporting further regeneration of towns and villages. Projects included in the SPF programme of projects will stimulate economic growth, create new tourism opportunities, contribute to the increased viability of town centres and support the development/improvement of commercial workspace.

Aim 4: Protect and improve the environment. Projects included within the programme of SPF projects will lead to reduced CO2 emissions, lead to the improvement of open spaces, support Active Travel and support the development of ‘green’ skills and business practices.

Alternative options

5.1The alternative option is the continuation of normal procurement and approval procedures by way of an Individual Executive Decision or Executive Report for each individual contract. This is likely to result in delays in contract award and consequently underspend of SPF grant.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998)

None

6.2Workforce

None

6.3Equality and Diversity/Equality Impact Assessment

The UKSPF funding supports communities to thrive. A number of the funding interventions will support the Districts’ most deprived communities and contribute to social mobility through skills and training.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UKSPF Delivery and Procurement UpdateReport 358 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
MG
Councillor Mike GledhillChair, present
DP
Councillor Darren PriceVice-Chair, present
CA
Councillor Charlotte AtkinsCommittee Member, present
BC
Councillor Bill CawleyCommittee Member, present
DP
Councillor Dave ProudloveCommittee Member, present
MS
Councillor Matt SwindlehurstCommittee Member, present
CW
Councillor Chris WoodCommittee Member, present
NY
Councillor Nigel YatesCommittee Member, present
MD
Member Diary SMDCOfficer, expected
AS
Andrew StokesOfficer, expected
NR
Neil RodgersOfficer, expected
MO
Martin OwenOfficer, expected

All 16 on the meeting page

On this subject at High Peak

Search all
  1. UKSPF Delivery and Procurement UpdateThis decision
  2. UKSPF Project Delivery UpdateDecided
  3. UKSPF Delivery and Procurement UpdateDecided

More from High Peak Cabinet

All decisions
MeetingDecisionOutcome
11 Aug 2026 Forward PlanDECISION: That the be approved for publication. Approved Open
11 Aug 2026 Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. Approved Open
11 Aug 2026 Fourth Quarter - Finance, Procurement & Performance ReportsDECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A... Noted Open
11 Aug 2026 Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... Approved Open
11 Aug 2026 Adoption of Market Guidance (Development Management)DECISION: That the Guidance attached at Appendix 1 of the report be approved for use by the Council’s Development Man... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies