Resolved
That the update sheet be noted.
Development Control Committee noted this item on Monday 20 May 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update sheet be noted.
20th May 2024
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATES REPORT
HPK/2022/0474 – Land at Charlestown Works, Glossop
Applicant:
Affordable Housing We disagree that insufficient information was provided in regard to the level of affordable housing provision required. We have accepted that a number of affordable housing units are required, and had previously offered 20% of the development, a total of 5 Units. The viability study does quantify that 7 Units, 30% of the development is justified and therefore are happy to condition this within a S106 Agreement, in order to satisfy Policy H9.
We have also agreed to all sums stated within the Summary of Recommendation and again we are happy to condition this within any S106 Agreement.
Housing Types A schedule of accommodation confirms that the proposed dwellings are both accessible and adaptable’ to standard in Part M4(2) of Building Regulations / NDSS space standards. We disagree that the proposal doesn’t provide a range of housing types.
As noted within the summary of recommendation there are a lack of 1 Bedroom Apartments, and therefore for us to create a number of 3 Bedroom Apartments, would reduce the number of smaller 2-bedroom properties on each floor. The ideology of some of the smaller 2-bedroom properties was that nine of the apartments could be used as one bedroom apartment plus a home style office.
The schedule of accommodation has been updated to make this more transparent. We could in principle reduce the number of 2 Bedroom properties to just 1 Bedroom, however this reduces the market for people wanting to either homework or study. We have taken advice from a housing provider who is interested in both blocks; however, 3 and 4 Bed Apartments were not suitable, for their target audience.
Price point was taken into consideration in incorporating a 3 Bedroom Flat, which would have Resulted in a pricing point marketed at a higher price than the majority of 3 Bedroom Homes within the local area. The average housing types being chimney pots and therefore a 3-or 4-Bedroom Flat would not be aimed at the right demographic.
We have accommodated for either elderly or disabled residents on the ground floor, with access to a number of disabled parking.
We have updated our floor plan drawings Block 1, Reference 2022/027/PEAB1/D, & Block 2, Reference 022/027/PAB2/C, to reflect these changes. Design We do not agree that the proposed development does not provide for a sense high quality design. The design is both in keeping with the previous application, and in keeping with other neighbouring flat conversions within the local area. The only addition to this, is the residents garden incorporated within the roof of the development. During the planning process, it was noted a discussion had been raised from one of the flat owners in the converted building adjacent. In conjunction with comments raised from the council, in that we could/should remove a number of side elevation habitable windows. Revised Plans removing identified, side windows to the lounge and bedrooms were adjusted to make the scheme compliant in respect of any overlooking or privacy issues.
Highways We have adjusted the site-plan drawings, drawing reference 023/021/PSP/E, to satisfy the Highways Officers objection. To date there has been no discussion that the design to the external design was inappropriate, and at no time was it offered for a discussion with a Uban Design Manager or equivalent.
Environment Agency:
Awaited.
Case Officer:
Clearly, the applicant’s submitted Financial Viability Appraisal (FVA) only relates to the office (formerly B1) of the application site and therefore is not a site wide appraisal of the former Charlestown Works consent. Accordingly, the applicant would need to provide an FVA in relation to the entire approved scheme with evidence regarding sales information to date and construction costs expended to establish the affordable housing needs of the proposed development.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 206 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.