That the Late Representations Report be noted; 2. That the application be APPROVED for the reasons and based on the policies contained within the report; 3. That the Discharge of conditions concerning drainage be bought to this Committee for consideration; 4. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided thar the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Hoptroff and seconded by Councillor Johnson) (Having declared an interest Councillor Pointon withdrew from the meeting. Councillor Flunder also withdrew from the meeting. Neither were present during the consideration of and voting on the application.)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Proposal Application for Non-Material Amendment relating to SMD/2022/0444 Applicant Ameresco Ltd Agent Paul Butler Associates Parish/ward Cheddleton Date registered 1/11/24 If you have a question about this report please contact: Jane Curley [email protected].
REFERRAL
The application is referred to Committee because it has proved to be locally controversial
1. SUMMARY OF RECOMMENDATION
Grant the Section 96A application
2. DESCRIPTION OF THE SITE
2.1The site is currently agricultural fields bound in the main by hedgerows.
3. DESCRIPTION OF THE PROPOSAL
3.1This site has planning permission for a Flexible Energy Facility granted on 22nd December 2022 under reference SMD/2022/0444. Development has not yet commenced albeit the Council is currently considering a number of Discharge of condition applications
3.2This application is submitted under Section 96A and seeks a number of non material changes to the application. The applicant summarises the changes as follows:- a) Re-organisation of batteries, switchgear and transformers to meet operating requirements and allow for a maintenance track. b) Very small enlargement of facility to cater for the layout changes, includes revised buffer mitigation to the facility. c) Retaining wall detail added to plan. d) External DNO building not required and removed. e) Security fence detail confirmed to plan. 3.3 The application explains the technical reason the changes are needed, summarised as follows:- a) No space allowance on the planning drawing for MV/LV & Interface cable routes. b) No space allowance on the planning drawing for access roads for construction & operations and maintenance on completion. c) No space allowance on the planning drawing for drainage infrastructure. d) BESS Equipment used on planning drawing is physically smaller than the actual equipment to be installed (i.e. actual Battery units are 1.3m longer per unit). e) GIS substation actual dimensions are larger than detailed on the planning drawings - 46 * 29m actual against 39 * 18m original. f) Planning layout drawings show 2 satellite substations installed, there are actually 6 satellite substations required. g) Number of sets of BESS units shown on planning drawing is less than actually to be installed - 49 sets v 54 sets. h) Perimeter security fence not shown/allowed for on planning drawings. i) No space allowance on the planning drawings for the stores & welfare containers.
Amended plans
3.4During the processing of the application, updated plans were received to address comments raised by the Councils Landscape Consultant. These are discussed in the Officer comment section below
3.5The applicant also provided a document entitled Question Responses which provides the applicant’s response to comments raised in the letters of representation. Whilst many of these are not relevant to the consideration of this NMA application, the document provides some useful information including on the fire safety measures to be adopted
Final Plans considered
00 Cellarhead D 114 Rev K (Sheet 1 of 2) Site Layout plan Sheet 1 of 2
00 Cellarhead D 114 Rev F Bund Cross Sections AA and BB( Sheet 2 of 2)
00 Cellarhead D 115 Rev H Site cross sections plan AA- GG (Sheet 1 of 3)
00 Cellarhead D 115 D Cross sections AA, BB and CC (Sheet 2 of 3)
00 Cellarhead D 115 E Cross sections DD, EE FF and GG (Sheet 3 of 3)
00 Cellarhead D 116 C Elevation plan A, B C and D (Sheet 1 of 2)
00 Cellarhead D 116 C Site Elevations (Sheet 2 of 2)
00 Cellarhead D 118 A Site access road plan and sections AA, BB and CC
00 Cellarhead D 119 Perimeter bund retaining wall plan and sections
00 Cellarhead D 307 E Sub station location and Cross section plan AA BB and CC Sheet 1 of 4
00 Cellarhead D 307 D Substation plan (Sheet 2 of 4)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.