Resolved
· That the minutes of the previous meeting held on 28 November 2024 be amended to reflect that Councillor Jebb is the Parish Councillor for Endon in the items listed under “Declarations of Interest”. · That the minutes be approved.
Moorlands Partnership Board approved this item on Tuesday 25 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
· That the minutes of the previous meeting held on 28 November 2024 be amended to reflect that Councillor Jebb is the Parish Councillor for Endon in the items listed under “Declarations of Interest”. · That the minutes be approved.
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL MOORLANDS PARTNERSHIP BOARD DECISIONS THURSDAY, 28 NOVEMBER 2024 PRESENT: Councillor C Jebb (Chair)
Councillors B Birch, B Emery, E Fallows, K Flunder, M Johnson, L Malyon, D Price, S Sillitoe, L Swindlehurst, V Wheeldon and N Yates
APOLOGIES: Councillors A Hart and P Upton
20 TO APPROVE THE MINUTES FROM THE PREVIOUS MEETING.
RESOLVED: That the minutes of the previous meeting held on 16 July 2024 be amended to reflect that Councillor Flunder is the County Councillor for the area in the two items listed under “Declarations of Interest”. That the minutes be approved.
21 DISCLOSURE OF INTERESTS:
Agenda No. Member Declaring Nature of Interest Interest 4 & 5 - Stockton Brook Councillor Sillitoe “Pecuniary” – Director Pumping Station of community interest group that use this site. Withdrew during the consideration and voting of the application. 4 & 5 - Endon Station, Councillor Jebb “Other” – District Endon Village Hall, The Councillor. The Vice Plough, White Bridge Chair oversaw and Stockton Brook proceedings of these Pumping Station. applications. Councillor Sillitoe "Other” – Parish Councillor Councillor Flunder “Other” – District and County Councillor 4 & 5 – The Trough, Councillor Flunder “Other” – County Christ Church, St Councillor James Court Clock Councillor Yates “Other” – County Tower and Miners Councillor Lamps. 4 & 5 – Garage Councillor Malyon “Other” – District Refurbishment and Councillor Belmont Road 4 & 5 – Den Engel Councillor Price “Other” – knows owner
22 SUMMARY OF PROJECTS Moorlands Partnership Board - 28 November 2024
The board received a report which provided an update and reviewed progress on the grants already approved (in previous years) under the Moorlands Partnership Board.
This report dealt with progress to date on those projects, awaiting commencement, on site or, completed since the last meeting of the Moorlands Partnership Board.
This report was for information only but offered Members an opportunity to comment on progress. The report was presented with an accompanying power point presentation which displayed images of each project.
Members discussed the process for chasing applications which were coming toward their grant expiration date and when funding should be withdrawn.
Members discussed the curtilage of a listed building, delay in replacing windows at Endon Station, planning constraints for Leonard Street, the restoration of Endon Village Hall, progress of The Plough application and the slow deterioration of the canal bridge.
Members suggested the Chairman be invited to visit the Miners Lamp project.
RESOLVED: That the update report be noted. That the recommendation to reallocate the underspend on the Foxlowe conservatory roof to the Foxlowe outhouse roof be approved.
23 FINANCIAL SUMMARY AND PROPOSED GRANT AWARDS
The report sought Member’s approval to allocate grant funding from the Moorlands Partnership Board (MPB) in 2024/25. The budget for this year is £60,000.
Members discussed signposting other grants and the heritage value of some applications.
RESOLVED: 1. That the financial summary in 3.2 be noted.
2. That a maximum grant of £8,000 towards the cost of eligible works totalling £21,264.61 (VAT excl.) towards the repair of the original cast iron windows at the Alton Castle be approved. The work will be subject to the standard grant scheme conditions and the following technical conditions: The works to be carried out in accordance with the Architects specification.
3. That a 75% grant of £5,925 towards the cost of eligible works totalling £7,900 (VAT excluded) towards the renewal of the flat roof to the Well building at the former Stockton Brook Pumping Station be approved. The work will be subject to the standard grant scheme conditions.
4. That a 75% grant of £4,736 (excl. VAT) towards the cost of eligible works totalling £6,315 (excl. VAT) towards the roof repair of the porch at
2 Moorlands Partnership Board - 28 November 2024
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
To Approve the Minutes from the Previous Meeting.Minutes | 211 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.