Resolved
That the report be received.
AI summaryMoorlands Partnership Board noted progress on heritage restoration projects, with church roof, clock and funerary monument work in progress and a £50,000 budget for 2025-2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the report be received.
2.1That the update report is noted.
3.1This report deals with progress to date on those projects awaiting commencement, on site, or completed since the last meeting of the Moorlands Partnership Board.
3.2This report is for information only but does offer Members an opportunity to comment on progress. The report will be presented with an accompanying power point presentation which displays images of each project.
4. How this report links to Corporate Priorities
4.1This report concerns publicly funding the restoration and repair of historic properties or places that are either listed or an identified heritage asset. This in turn, is related to the Council’s corporate aims 3:
• Help create a strong economy by supporting further regeneration of towns and villages.
5.1There are no alternative options as this is an update report on progress only. 6. Project updates and progress
2021/2022 OFFERS:
Christ Church, Biddulph Moor – Roof repairs A funding application to the Heritage Lottery Fund has now been successful. The applicant is just waiting for a confirmation start date from the contractor.
2024/2025 OFFERS:
St Giles The Abbot Cheadle – Church clock repairs Waiting for works to commence.
2025/2026 OFFERS:
St Lawrence Churchyard Biddulph – Funerary Monument repairs (7) Works to the 7 funerary monuments are underway but works are progressing slowly due to poor weather.
Cenotaph Biddulph – railings repairs Grant Funding Agreement signed and applicant can now start works on this project.
St Edwards - Cupola repairs It is hoped that an existing hatch to the Cupola can be opened to allow access for the repair of the wooden and lead cupola and negate the need for working at height specialist equipment. This will result in a reduced cost to the works.
ANTICIPATED APPLICATIONS:
Stafford Arms – Window replacement
8 Sheep Market Leek – façade repairs
7. Implications
7.1Community Safety – No implications at this stage.
7.2Workforce – The Moorlands Partnership Scheme is administered by an officer within the Regeneration Team with assistance when required from the Council’s Conservation Officer.
7.3Equality and Diversity/ Equality Impact Assessment - No implications at this stage.
7.4Financial considerations - There are allocations within the capital programme for the Moorlands Partnership grant scheme. The projects outlined in this report have been met from approved budgets from previous years. The budget for this year 2025-2026 is £50,000. 7.5 Legal - Local authorities are empowered to give grants towards improvements in conservation areas under Section 57 of the Planning (Listed Buildings and Conservation Areas) Act 1990.
7.6Climate Change – No Implications at this stage.
7.7Consultation – Grant offers are made in consultation with and approved by the Moorlands Partnership Board. Where required, projects that require planning permission and listed building consent are subject to the normally statutory consultations.
Andrew Stokes Chief Executive
Web Links and Location Contact details Background Papers Joanne Brooks Regeneration Officer: [email removed]. uk
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Summary of ProjectsReport | 75 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
| 17 Nov 2025 | Summary of Projects.That the report be received. 2. That the Regeneration Officer be requested to consider the allocation of heritage pla... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.