That the Late Representations Report be noted; 2. That the application be APPROVED for the reasons and based on the policies contained within the report, and be subject to a landscaping condition to include a 2m buffer and an informative recommending the use of deer fencing; 3. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided thar the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Roberts and seconded by Councillor Hoptroff)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
24th April 2025
Application SMD/2024/0067 No: Location The Tawny Hotel, Consall, ST9 0AG Proposal Installation of new 300kW solar photovoltaic array inclusive associated infrastructure (Total 887 PV modules) including additional screen planting to rear of site. Applicant Consall Hall Estate Ltd Agent CTD Architects Parish/ward Consall Date registered 7th February 2024 If you have a question about this report please contact: [name removed] tel: 01538 395400 or e-mail [email protected]
REFERRAL
The application has been called in by Councillor Worthington.
1. SUMMARY OF RECOMMENDATION
Approve subject to conditions
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The site is in the open countryside a short distance to the east of Consall village and which comprises part of a field immediately to the north and west of the Tawny Hotel spa resort/estate, formerly Consall Hall. To the east is the main car park for the Tawny Hotel. To the south, is a row of wedding accommodation “pods” which run parallel to the north boundary of the Tawny Hotel estate. The rest of the field lies to the west of the site. There is another field to the north and further to the north is a dwelling on the south side of Consall Lane, called “Priory”, about 130m to the north of the site boundary. To the other side of Consall Lane is Old Hall Farm/Consall Old Hall. The access to the site is via one of the entrances to the Tawny Hotel off Consall Lane to the north-east and which leads to the car park. The field site is rectangular and has maximum dimensions of 100 x 40 metres (roughly 0.4 hectares although the forms state 0.48 ha presumably as the actual red line application site also includes the access and part of the Tawny Hotel grounds). The site is not in the ownership of the applicant but within the ownership of Consall Old Hall. The site is in the Green Belt. The site is also in the Churnet Valley. 3. DESCRIPTION OF THE PROPOSAL
3.1This is a full planning application to cover the site with rows of ground-mounted solar/PV panels for the use of Tawny Hotel. A hedge would be continued along the north boundary of the site to provide some screening. There would be 30 arrays (rows) of panels crossing the site on an east-west axis. The array structures supporting the panels would have a height of 2.0 metres.
3.2The application site also includes the access driveway up to the public highway and part of the car park, presumably as these areas will be required for the construction vehicles.
3.3There would also be battery storage. The submitted Planning Statement explains that this facility will enable any unused electricity generated by the solar array to be stored for periods when the array is less productive thereby optimising the efficiency of the solar array. This would be placed inside a metal container within the existing Tawny Hotel service yard to the other side of an existing close boarded fence marking the south edge of the car park. The container would have a footprint of 12.3 x 2.4 meters and a height of 2.6 metres. The cables and ducting from the batteries would be linked to the solar arrays field site via an underground trench. Three inverters would be placed on the boundary between the field and the car park.
3.4The Planning Statement states the solar array development will produce in the order of 256.96 MWh of renewable electricity to serve the existing wedding venue and hotel on the site. It states the following:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.