CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Corporate Select Committee, Monday 17 November 2025 at 6.00pm

Second quarter Finance, Performance and Procurement Report

Noted Committee 4 papers

AI summaryHigh Peak Borough Council Corporate Select Committee noted the second quarter 2025/26 finance, procurement and performance position, showing a forecast General Fund underspend of £666,960 and an HRA deficit of £1,046,378.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarterly finance, procurement and performance report
Money£666,960 forecast General Fund underspendHRA forecast deficit of £1,046,378
What happens nextNo new action requiredCommittee asked only to note the position
Who it affectsCouncil-wide services and budgetsAll residents and council tax/business rate payers

What was decided

The committee noted the Second Quarter 2025/26 Finance, Procurement and Performance position as set out in Appendices A, B and C. Report 2.1

Why

The report summarises the council's performance and forecast financial position after service activity throughout the second quarter of the year. Report 3.1

Successful delivery of all corporate priorities depends on effective management of performance and financial resources, which this report covers. Report P6

What happens next

Detailed finance, procurement and performance analysis is contained in Appendices A, B and C for the committee's consideration. Report 5.1, 3.2

The money

  • £666,960 Forecast General Fund underspend for 2025/26 Report P5
  • £219,900 Efficiencies identified so far in the year, exceeding the annual target Report P5
  • £1,046,378 Forecast Housing Revenue Account deficit, £23,722 less than the revised budget Report P5
  • £17.36million Revised General Fund Capital Programme budget for 2025/26 Report P5
  • £4.886million Forecast General Fund Capital Programme underspend against budget Report P5
  • £12.72million Revised HRA Capital Programme budget for 2025/26 Report P5
  • £12.22million Forecast HRA Capital Programme outturn, an underspend of £0.51million Report P5
  • £25.3million Cash investments held at the end of the second quarter Report P5
  • £73.3million External borrowing at the end of the second quarter Report P5
  • £256,820 Forecast overspend on net interest cost Report P5
  • £430,123 Sundry debt over 60 days old across 170 invoices Report P5

Options considered

  • Chosen: Note the Second Quarter 2025/26 Finance, Procurement and Performance position. Recommended in the covering report as the standard quarterly review process Report 2.1

Implications

  • Financial: There are substantial financial considerations contained throughout the report. Report P8
  • Risk: Several risks to the financial position are identified and explained in the finance report at Appendix A. Report P8
  • Equalities: The report has been prepared in accordance with the Council's Equality and Diversity policies. Report P8
  • Climate: Environmental and sustainability implications are discussed, including deployment of the climate change reserve within the Communities service. Report P8
  • Other: Biodiversity net gain expenditure and funding is included in the relevant service area forecast outturn. Report P8

Who and where

  • Council tax payers (55.22% collection as at 30 September 2025, compared with 55.36% the previous year) Report P5
  • Business rates payers (57.93% collection as at 30 September 2025, compared with 58.55% the previous year) Report P5
  • Creditors owed money by the council through sundry debt (170 invoices over 60 days old totalling £430,123) Report P5
  • Residents who raise complaints, comments, MP enquiries and compliments with the council Report P5

Timeline

  • 1 April to 30 June 2025: Procurement performance reported at 96% for the period Report P5
  • As at 30 September 2025: Council tax and business rates collection rates recorded, along with cash investments of £25.3million and external borrowing of £73.3million Report P5
  • 2025/26: Forecast outturn covers the full financial year for the General Fund, HRA and capital programmes Report P5

Plain English for the jargon

  • General Fund: The council's main revenue account for non-housing services, funded mainly by council tax, business rates and government grants.
  • Housing Revenue Account (HRA): A ring-fenced account that records income and spending related to the council's own housing stock.
  • Provisional outturn: An early forecast of the year-end financial position, before the accounts are closed.
  • Treasury Management: Management of the council's cash investments, borrowing and related interest costs.
  • Sundry debt: Smaller amounts owed to the council by individuals or organisations for non-tax charges, such as service fees.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/37

Resolved

That the Second Quarter 2025/26 Finance, Procurement and Performance positions detailed in Appendices A, B and C and summarised at paragraph 3.3 of the covering report, be noted .
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Corporate Select Committee

Recommendation

2.1It is recommended that the Corporate Select Committee discuss and note the Second Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised at 3.3 of this covering report.

Executive summary

3.1This report summarises the Council’s performance and forecast financial position after considering service activity throughout the second quarter of the year.

3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) & Appendix C (Performance).

3.3The position can be summarised as follows:

Subject Headline Reference Subject Headline Reference Finance The Finance headlines at the second update are: Appendix A Performance against Budget • The General Fund provisional outturn for 2025/26 is forecast as a £666,960 underspend against budget Efficiency Programme • £219,900 in efficiencies have been identified so far in the year, which exceeds the target set for the year. Housing Revenue Account • The Housing Revenue Account is forecast to be in deficit by £1,046,378 which is £23,722 less than anticipated in the revised budget Capital Programme • The General Fund Capital Programme budget for 2025/26 as revised is £17.36million. The provisional outturn forecasts a £4.886million underspend compared to budget • The HRA Programme for 2025/26 is revised at £12.72million. The provisional outturn is £12.22 million which is a forecast underspend of £0.51million compared to budget Treasury Management • Cash investments held at the end of the second quarter totalled £25.3million and external borrowing was £73.3 million • A £256,820 overspend on net interest cost is forecast Revenue Collection as at 30th September 2025: • Council Tax 55.22 % (55.36% previous year) • Business Rates 57.93% (58.55% previous year) • Sundry debt over 60 days old £430,123, 170 invoices (£77,387 previous year, 135 invoices) Procurement The Procurement headlines for the second quarter are: Appendix B • 59 procurement activities were completed • The Procurement forward plan includes 90 procurement activities for completion/start in 2025/26 (including HPBC and or Joint (SM/HP) activity) • Procurement performance during the period 1 April to 30 June 2025 was 96% Performance The Performance headlines for the second quarter are: Appendix C • 66% of the key performance indicators were on track to be met, with 58% performing better than in the previous year • The Council closed 133 complaints and received 166 comments, 69 MP comments and 23 compliments in the year

4. How this report links to Corporate Priorities 4.1 The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report.

Alternative options

5.1Detailed analysis is contained within the appendices.

6. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(Finance) for Second quarter Finance, Performance and Procurement Report /37Appendix A 246 KB Download
PDF
(Procurement) for Second quarter Finance, Performance and Procurement Report /37Appendix B 357 KB Download
PDF
(Performance) for Second quarter Finance, Performance and Procurement Report /37Appendix C 1.2 MB Download
PDF
Second quarter Finance, Performance and Procurement ReportReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 24 attended
CP
Councillor Chris PayneChair, present
LG
Councillor Linda GroobyVice-Chair, present
PB
Councillor Pauline BellCommittee Member, present
NC
Councillor Neville ClarkeCommittee Member, present
JC
Councillor Joanna CollinsCommittee Member, present
OC
Councillor Ollie CrossCommittee Member, absent
RM
Councillor Robert McKeownCommittee Member, present
RQ
Councillor Rachael QuinnCommittee Member, present
PR
Councillor Pam ReddyCommittee Member, present
ES
Councillor Edward SiddallCommittee Member, present
KS
Councillor Kath SizelandCommittee Member, present
JT
Councillor Jo TaylorCommittee Member, present

All 24 on the meeting page

On this subject at High Peak

Search all
  1. Second quarter Finance, Performance and Procurement ReportThis decision
  2. Second Quarter Finance, Procurement & Performance ReportsDecided
  3. Second Quarter Finance Performance and Procurement ReportNoted
  4. Second Quarter - Finance, Procurement & PerformanceNoted
  5. Second Quarter - Finance, Procurement & Performance ReportNoted
  6. Second Quarter - Finance, Procurement & Performance ReportNoted

More from High Peak Corporate Select Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 8 June 2026 be approved as a correct record. Approved Open
20 Jul 2026 Select Committee Work ProgrammeThat, subject to the above, the Select Committee Work Programme, be noted. Noted Open
20 Jul 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
20 Jul 2026 Performance Framework 2026/27That the proposed set of performance indicators and targets, and contextual indicators as set out in Appendix A be no... Noted Open
20 Jul 2026 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the following item of business as there may be disclosu... Decided Open