Second Quarter Finance Performance and Procurement Report

Noted Executive 4 papers

AI summaryHigh Peak Borough Council's Executive has noted the second quarter 2025/26 finance, procurement and performance position, with a forecast General Fund underspend of £666,960 against budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExecutive noted the quarterly report
MoneyForecast underspend £666,960General Fund forecast underspend against budget
What happens nextNot stated
Who it affectsCouncil-wide finances and servicesCouncil taxpayers, tenants, suppliers and staff

What was decided

The Executive noted the Second Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C, as set out at 3.3 of the covering report. Report 2.1

Why

The report sets out the council's performance and forecast financial position after considering service activity through the second quarter of the year. Report 3.1

Detailed analysis is provided in three appendices covering finance, procurement and performance, with the position summarised at 3.3 of the covering report. Report 3.2, 3.3

The money

  • £666,960 General Fund provisional outturn forecast as underspend against budget Report P5
  • £219,900 Efficiencies identified so far in the year, exceeding the annual target Report P5
  • £1,046,378 Housing Revenue Account forecast deficit for 2025/26 Report P5
  • £4.886million General Fund Capital Programme forecast underspend compared to budget Report P5
  • £25.3million Cash investments held at the end of the second quarter Report P5
  • £73.3 million External borrowing at the end of the second quarter Report P5
  • £256,820 Forecast overspend on net interest cost Report P5
  • £430,123 Sundry debt over 60 days old at 30 September 2025 Report P5

Implications

  • Financial: There are substantial financial considerations contained throughout the report. Report P8
  • Risk: Several risks to the financial position are identified and explained in the financial report at Appendix A. Report P8
  • Climate: Environmental and sustainability implications are discussed throughout the body of the report, including deployment of the climate change reserve within the Communities service. Report P8
  • Other: Biodiversity net gain expenditure and funding is included in the relevant service area forecast outturn. Report P8
  • Equalities: The report has been prepared in accordance with the Council's Equality and Diversity policies. Report P8

Who and where

  • Council taxpayers, with collection at 55.22% against 55.36% the previous year Report P5
  • Business ratepayers, with collection at 57.93% against 58.55% the previous year Report P5
  • Housing Revenue Account tenants, through the HRA budget and £12.72million capital programme Report P5
  • Suppliers and contractors, through 59 completed procurement activities and a forward plan of 90 for 2025/26 Report P5

Timeline

  • 1 April to 30 June 2025: Procurement performance measurement period, which recorded 96% Report P5
  • 30th September 2025: Date of revenue collection figures for council tax, business rates and sundry debt Report P5
  • 2025-12-04: Executive meeting at which the quarterly report was noted

Plain English for the jargon

  • General Fund: The main revenue account for the council's day to day spending on services.
  • Housing Revenue Account (HRA): A ringfenced account covering income and spending on council housing.
  • Provisional outturn: An early forecast of the year end financial position based on activity to date.
  • Sundry debt: Smaller amounts owed to the council by individuals or organisations for various services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/36

Resolved

That the Second Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised at 3.3 of the covering report be noted.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive

Recommendation

2.1It is recommended that the Executive discuss and note the Second Quarter 2025/26 Finance, Procurement and Performance position detailed in Appendices A, B and C and summarised at 3.3 of this covering report.

Executive summary

3.1This report summarises the Council’s performance and forecast financial position after considering service activity throughout the second quarter of the year.

3.2Detailed analysis is provided in Appendix A (Finance), Appendix B (Procurement) & Appendix C (Performance).

3.3The position can be summarised as follows:

Subject Headline Reference Finance The Finance headlines at the second update are: Appendix A Subject Headline Reference Performance against Budget • The General Fund provisional outturn for 2025/26 is forecast as a £666,960 underspend against budget Efficiency Programme • £219,900 in efficiencies have been identified so far in the year, which exceeds the target set for the year. Housing Revenue Account • The Housing Revenue Account is forecast to be in deficit by £1,046,378 which is £23,722 less than anticipated in the revised budget Capital Programme • The General Fund Capital Programme budget for 2025/26 as revised is £17.36million. The provisional outturn forecasts a £4.886million underspend compared to budget • The HRA Programme for 2025/26 is revised at £12.72million. The provisional outturn is £12.22 million which is a forecast underspend of £0.51million compared to budget Treasury Management • Cash investments held at the end of the second quarter totalled £25.3million and external borrowing was £73.3 million • A £256,820 overspend on net interest cost is forecast Revenue Collection as at 30th September 2025: • Council Tax 55.22 % (55.36% previous year) • Business Rates 57.93% (58.55% previous year) • Sundry debt over 60 days old £430,123, 170 invoices (£77,387 previous year, 135 invoices) Procurement The Procurement headlines for the second quarter are: Appendix B • 59 procurement activities were completed • The Procurement forward plan includes 90 procurement activities for completion/start in 2025/26 (including HPBC and or Joint (SM/HP) activity) • Procurement performance during the period 1 April to 30 June 2025 was 96% Performance The Performance headlines for the second quarter are: Appendix C • 66% of the key performance indicators were on track to be met, with 58% performing better than in the previous year • The Council closed 133 complaints and received 166 comments, 69 MP comments and 23 compliments in the year

4. How this report links to Corporate Priorities 4.1 The successful delivery of all corporate priorities is dependent upon the effective management of performance and financial resources, which is the subject of this report.

Alternative options

5.1Detailed analysis is contained within the appendices.

6. Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/36Appendix A 246 KB Download
PDF
/36Appendix B 357 KB Download
PDF
/36Appendix C 1.2 MB Download
PDF
Second Quarter Finance Performance and Procurement ReportReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
AM
Councillor Anthony McKeownChair, present
DG
Councillor Damien GreenhalghVice-Chair, apologies
AB
Councillor Alan BarrowCommittee Member, present
GC
Councillor Godfrey ClaffCommittee Member, present
FS
Councillor Fiona SlomanCommittee Member, present
JT
Councillor Jean ToddCommittee Member, present
AS
Andrew StokesOfficer, expected
SH
Sally HamptonOfficer, expected
MT
Mark TrilloOfficer, expected
LV
Linden VernonOfficer, expected
MD
Member Diary HPBCOfficer, expected
MO
Martin OwenOfficer, expected

All 19 on the meeting page

On this subject at High Peak

Search all
  1. Second Quarter Finance Performance and Procurement ReportThis decision
  2. Second Quarter Finance, Procurement & Performance ReportsDecided
  3. Second quarter Finance, Performance and Procurement ReportNoted
  4. Second Quarter - Finance, Procurement & PerformanceNoted
  5. Second Quarter - Finance, Procurement & Performance ReportNoted
  6. Second Quarter - Finance, Procurement & Performance ReportNoted

More from High Peak The Executive

All decisions
MeetingDecisionOutcome
27 Aug 2026 To resolve that the public and press be excluded from the meeting for the following items because there may be disclosure to them of exempt information as defined in Part 1 of Schedule 12A of the Local Government Act 1972.That the public and press be excluded from the meeting for the following items because there may be disclosure to the... Decided Open
6 Aug 2026 To approve the minutes of the previous meetingThat the minutes of the meeting held on 11 June 2026 be approved as a correct record. Approved Open
6 Aug 2026 Forward PlanThat, subject to the above, the be noted. Noted Open
6 Aug 2026 Fourth Quarter Finance, Performance and Procurement UpdateThat the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A, B and C and... Noted Open
6 Aug 2026 Anti-social Behaviour, Hate and Neighbourhood Management PoliciesThat the Anti-Social Behaviour Policy, Hate Policy and Neighbourhood Management Policy, be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies