Revised Local Plan Timetable (Local Development Scheme) 2026
NotedExecutive2 papers
AI summaryHigh Peak's planning executive councillor has approved a revised Local Development Scheme setting the timetable for the borough's new Local Plan, with draft consultation in early 2026 and adoption targeted for early 2028.
Written from the decision and the officer reportPDF Pro
OutcomeNotedRevised Local Development Scheme, to take effect after call-in
MoneyNot specifiedCosts covered in Medium Term Financial Plan
What happens nextDraft Local Plan consultationRegulation 18 stage in Quarter 1 2026
Who it affectsWhole borough areaAll wards outside the Peak District National Park
What was decided
The executive councillor noted the content of the proposed Local Development Scheme and approved it, so it takes effect after the call-in period. Report P7
The scheme sets an up-to-date timetable for the High Peak Local Plan under the current planning system, rather than the reforms being introduced through the Levelling-up and Regeneration Act 2023. Report P8, P12
Officers must send the approved scheme to the Ministry of Housing, Communities and Local Government and publish it publicly. Report 3.5, P12
Why
The Council is required by the Planning and Compulsory Purchase Act 2004 to publish and keep up to date a Local Development Scheme that sets out timetables for local development documents. Report P8, P12
The proposed timescales are considered the most expedient possible given regulatory requirements, the Statement of Community Involvement, and available resources. Report P8
The circumstances in Annex 1 of the NPPF that would let High Peak continue under the old plan-making system do not apply, so the plan must be prepared under the new NPPF with the higher standard method housing need figure. Report P8, P12
What happens next
Once the call-in period ends, officers will publish the Local Development Scheme and send a copy to the Ministry of Housing, Communities and Local Government by email. Report 3.5, P12
The Draft Local Plan (Regulation 18) will be published for consultation in Quarter 1 2026, followed by the Proposed Submission Consultation and submission to the Secretary of State in Quarter 4 2026. Report P8, P13
Progress against the timetable must be reported in the Council's annual Authority Monitoring Report. Report P12
Options considered
Chosen: Approve the revised Local Development Scheme with the proposed timetable. Required to meet Government requirements; timescales judged the most expedient possible Report P8
Implications
Legal: Under section 15 of the Planning and Compulsory Purchase Act 2004 the Council must publish and maintain an LDS, resolve that it has effect from a specified date, and report progress against it. Report P8
Staffing: Documents will be prepared by the Development Services section, with additional support from appointed consultants for elements of the Local Plan evidence base. Report P8
Financial: Provision for the costs of the Local Development Scheme is included in the Medium Term Financial Plan and revenue budget; no new figures are given. Report P8
Risk: The High Peak Local Plan features on the Council's Risk Register to identify and manage risks. Report P8
Equalities: No direct implications from the timetable; the Local Plan itself will have its own Equality Impact Assessment. Report P8
Climate: No direct implications from the LDS; climate change and biodiversity implications of the Local Plan will be considered separately. Report P8
Who and where
Residents, businesses and developers across all High Peak wards outside the Peak District National Park Report P4
Neighbourhood planning groups, whose plans are listed in the LDS but timetabled outside it Report 7.8
Timeline
January to March 2023: Early Engagement completed Report P8, P13
Quarter 1 2026: Draft Local Plan (Regulation 18) consultation Report P8, P13
Quarter 4 2026: Submission of Local Plan to Secretary of State (Regulation 22) Report P8, P13
Quarter 2 2027: Examination in Public Report P8, P13
Quarter 1 2028: Adoption of Local Plan (Regulation 26) Report P8, P13
Plain English for the jargon
LDS (Local Development Scheme): A statutory timetable setting out which local development documents a council will produce and when.
NPPF: National Planning Policy Framework, the Government's planning policy guidance for England.
Regulation 18: Stage of local plan preparation requiring early engagement with consultees on what the plan should contain.
Regulation 19: Publication stage where the council publishes the plan it considers sound for a six-week formal representation period.
Statement of Community Involvement (SCI): Document setting out how the council will consult the public on planning policy documents.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/20
Resolved
That the the content of the proposed Local Development Scheme be noted; and 2. That the Local Development Scheme be approved so that it shall take effect following the call-in period. ANY DECLARATION OF INTEREST None A NOTE OF ANY DISPENSATION GRANTED None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
HIGH PEAK BOROUGH COUNCIL
Individual Executive Decision
24 February 2026
TITLE: Revised Local Plan Timetable (Local Development Scheme) 2026 EXECUTIVE COUNCILLOR: Councillor Claff - Executive Councillor for Community Safety and Planning CONTACT OFFICER: Alasdair Cross - Principal Officer (Planning Policy), Scott Moran - Planning Policy Officer WARDS INVOLVED: All areas outside of the Peak District National Park
Appendices Attached – Appendix A - Draft High Peak Local Development Scheme 2026
1. Reason for the Report 1.1. To consider and agree a revised Local Development Scheme that establishes the timetable for the High Peak Local Plan and other planning policy documents.
2. Recommendation 2.1. That the Executive Councillor notes the content of the proposed Local Development Scheme. 2.2. That the Executive Councillor approves the Local Development Scheme so that it shall take effect following the call-in period.
3. Executive Summary 3.1. Local planning authorities must prepare and keep up to date a Local Development Scheme to set out details of local development documents, including the timetable for their preparation, their status and scope. The primary document is the Local Plan. 3.2. The attached draft LDS includes an up-to-date timetable for production of the High Peak Local Plan. Reforms to the local plan making system, through the Levelling-up and Regeneration Act 2023 are underway, and upcoming Local Reorganisation as such the High Peak Local Plan timetable set out in the LDS reflects the current planning system. 3.3. Annex 1 of the NPPF details circumstances by which Local Planning Authorities can continue their plan making under the old system (i.e. previous version of the NPPF and old standard method calculation). These circumstances do not apply in the case of the High Peak Local Plan so this will need to be prepared under the new NPPF including the new, higher, standard method minimum Local Housing Need figure. 3.4. The proposed timetable is as follows: STAGE DATE Early Engagement Completed January – March 2023 Draft Local Plan (Reg 18) Quarter 1 - 2026 Proposed Submission Consultation Quarter 4 - 2026 Submission of Local Plan Quarter 4 - 2026 Examination Quarter 2 - 2027 Adoption Quarter 1 - 2028
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.