Revised Local Plan Timetable (Local Development Scheme) 2026

Noted Executive 2 papers

AI summaryStaffordshire Moorlands Cabinet has approved a revised Local Development Scheme, setting a Local Plan timetable with adoption aimed for Quarter 2 - 2028. The plan is a partial review of the 2020 Local Plan.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSets Local Plan timetable to 2028 adoption
MoneyNot stated
What happens nextSend LDS to MHCLGOfficers authorised to notify Ministry of Housing
Who it affectsAll wards outside Peak ParkPlan covers non-Peak District area

What was decided

Cabinet noted the content of the revised Local Development Scheme so that it shall take effect following the call-in period. Report P9

Officers were authorised to send a copy of the revised Local Development Scheme to the Ministry of Housing, Communities and Local Government. Report P9

The agreed scheme must be made publicly available along with any amendments, and progress reported in the annual Authority Monitoring Report. Report 3.5

Why

Local planning authorities must prepare and keep up to date a Local Development Scheme, setting out the timetable and scope of local development documents. Report P10

The Local Plan Steering Group resolved to attempt a partial review of the 2020 Local Plan, including selected strategic policies and sites, before local government reorganisation. Report P10

Reforms to plan making under the Levelling-up and Regeneration Act 2023 are underway, so the timetable reflects the current planning system pending new regulations. Report P10, P23

What happens next

Draft Local Plan (Regulation 18) consultation is scheduled for Quarter 1 - 2026, followed by Regulation 19 publication in Quarter 4 - 2026. Report P11, P24

Submission of the Local Plan is targeted for Quarter 4 - 2026, with the Examination in Quarter 3 - 2027 and adoption in Quarter 2 - 2028. Report P11, P24, 7.11

Further engagement with neighbouring planning bodies on Local Plan timing will be undertaken once the Local Development Scheme is agreed. Report 7.11

Options considered

  • Chosen: Publish an updated Local Development Scheme with proposed timescales. The Council must publish an updated LDS to meet Government requirements, and the timescales are considered the most expedient possible given regulations, the Statement of Community Involvement and available resources. Report P14

Implications

  • Legal: Section 15 of the Planning and Compulsory Purchase Act 2004 requires local planning authorities to publish and maintain a Local Development Scheme, set out the timetable, and resolve the date the scheme is to have effect.
  • Staffing: Documents within the Local Development Scheme will be prepared by Development Services staff, with additional consultant support for parts of the Local Plan evidence base when necessary.
  • Risk: The Staffordshire Moorlands Local Plan and Developer Contributions Supplementary Planning Document are listed on the Council's Risk Register.
  • Equalities: An Equalities Impact Assessment accompanies the report; no direct implications identified. Report 6.3
  • Climate: No direct climate change implications arise from the Local Development Scheme itself; documents listed within it will be considered separately.
  • Financial: Budget requirements for documents in the Local Development Scheme are as per the Medium-Term Financial Plan.
  • Other: No consultation is required on the Local Development Scheme itself; consultations on documents listed within it will be considered separately.

Who and where

  • All wards outside of the Peak District National Park Report P6
  • Communities seeking to track plan-making progress Report P22
  • Developers and site promoters with interests in strategic sites Report P10
  • Neighbouring planning authorities, who will be engaged on Local Plan timing Report 7.11
  • Parish and town bodies preparing Neighbourhood Development Plans, whose timetables are not set out in the Local Development Scheme Report 7.11

Timeline

  • 2020: Staffordshire Moorlands Local Plan adopted
  • 2025: Last Local Development Scheme agreed
  • Quarter 1 - 2026: Draft Local Plan (Regulation 18) consultation Report P11, P24
  • Quarter 4 - 2026: Proposed Submission Consultation (Regulation 19) Report P11, P24
  • Quarter 4 - 2026: Submission of Local Plan to Secretary of State Report P11, P24
  • Quarter 3 - 2027: Examination in Public Report P11, P24
  • Quarter 2 - 2028: Adoption of the Local Plan Report P11, P24

Plain English for the jargon

  • Local Development Scheme (LDS): A document that sets out the timetable, scope and status of local development documents, including the Local Plan, as required by the Planning and Compulsory Purchase Act 2004.
  • Regulation 18: Stage under the Town and Country Planning (Local Planning) (England) Regulations 2012 covering preparation of a local plan and initial engagement with consultees.
  • Regulation 19: Stage under the 2012 Regulations at which the Council publishes the plan it considers sound for formal six-week representations.
  • Examination in Public: Independent consideration of the submitted plan and representations by a planning inspector, who may recommend modifications before adoption.
  • NPPF: National Planning Policy Framework, the Government's planning policy document; the 12th edition was published in December 2024.
  • Statement of Community Involvement (SCI): The Council's published document setting out how it will consult the community on planning policy documents.
  • Strategic Environmental Assessment (SEA): A statutory process for assessing the environmental effects of plans, required as part of plan preparation.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

DECISION: 1. That the content of the revised Local Development Scheme be noted so that it shall take effect following the call-in period. 2. That officers be authorised to send a copy of the revised Local Development Scheme to the Ministry of Housing, Communities and Local Government.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet

STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL

Cabinet

10 February 2026

Revised Local Plan Timetable (Local TITLE: Development Scheme 2026 Incorporating Local Plan Timetable PORTFOLIO HOLDER: Councillor Price - Deputy Leader & Portfolio Holder for Regeneration and Planning

CONTACT OFFICER: Alasdair Cross– Principal Officer (Planning Policy), Scott Moran - Planning Officer

WARDS INVOLVED: All wards outside of the Peak District National Park

Appendices Attached: Appendices Attached – Appendix A - Local Development Scheme 2026 Incorporating Local Plan timetable

1. Reason for the Report 1.1. To consider and agree a revised Local Development Scheme that establishes the timetable for the Staffordshire Moorlands Local Plan and other planning policy documents.

2. Recommendations 2.1. That the Cabinet notes the content of the revised Local Development Scheme so that it shall take effect following the call-in period. 2.2. That the Cabinet authorises officers to send a copy of the revised Local Development Scheme to the Ministry of Housing, Communities and Local Government.

3. Executive Summary 3.1. Local planning authorities must prepare and keep up to date a Local Development Scheme to set out details of local development documents, including the timetable for their preparation, their status and scope. The primary document is the Local Plan. 3.2. Reforms to the local plan making system, through the Levelling-up and Regeneration Act 2023, are underway and the upcoming Local Government reorganisation as such the Staffordshire Moorlands Local Plan timetable set out in this document reflects the current planning system. The Local Plan Steering Group have resolved to attempt to produce a partial review of the 2020 Local Plan involving an update of selected strategic policies including consideration of ‘strategic sites’, before Government migrates fully to ‘new style’ local plans and within the time remaining to the Council before Local Government Reorganisation. 3.3. The attached draft Local Development Scheme includes an up-to-date timetable for production of the Staffordshire Moorlands Local Plan. Public consultation is scheduled during 2026, with a view to publishing the plan for formal representations under Regulation 19 in the Quarter 4 - 2026. Following the satisfactory outcome of the plan at an Examination in Public, the plan is expected to be adopted in 2028. 3.4. The proposed timetable is as follows:

STAGE DATE Draft Local Plan (Reg 18) Quarter 1 - 2026 Proposed Submission Consultation (Reg 19) Quarter 4 - 2026 Submission of Local Plan Quarter 4 - 2026 Examination Quarter 3 - 2027 Adoption Quarter 2 - 2028

3.5Once agreed, the scheme must be made publicly available, and a copy sent to the Ministry of Housing, Communities and Local Government by email. The LDS should be kept under review to ensure that it remains up to date.

4. How this report links to Corporate Priorities 4.1. The Local Plan and other Supplementary Planning Documents link directly to four aims of the corporate plan.

5. Alternative Options 5.1. The Council must publish an updated Local Development Scheme to meet Government requirements. The timescales proposed for the Local Plan are considered to be the most expedient possible having regard to the requirements in the regulations and the Council’s Statement of Community Involvement and the level of resource available to support plan making.

6. Implications

6.1Community Safety - (Crime and Disorder Act 1998) None direct. 6.2 Workforce Preparation of documents within the Local Development Scheme will be undertaken by staff within Development Services with additional support from appointed consultants when necessary for elements of the Local Plan evidence base in particular.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 137 KB Download
PDF
Revised Local Plan Timetable (Local Development Scheme) 2026Report 95 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
MG
Councillor Mike GledhillChair, present
DP
Councillor Darren PriceVice-Chair, present
CA
Councillor Charlotte AtkinsCommittee Member, present
BC
Councillor Bill CawleyCommittee Member, present
DP
Councillor Dave ProudloveCommittee Member, present
MS
Councillor Matt SwindlehurstCommittee Member, present
CW
Councillor Chris WoodCommittee Member, present
NY
Councillor Nigel YatesCommittee Member, present
MD
Member Diary SMDCOfficer, expected
AS
Andrew StokesOfficer, expected
MO
Martin OwenOfficer, expected
AE
Anna EastgateOfficer, expected

All 15 on the meeting page

On this subject at High Peak

Search all
  1. Revised Local Plan Timetable (Local Development Scheme) 2026This decision
  2. Revised Local Plan Timetable (Local Development Scheme) 2026Noted
  3. Revised Working Age Local Council Tax Reduction SchemeApproved
  4. Revised Working Age Local Council Tax Reduction SchemeApproved
  5. New NPPF (Implications for town/parishes) and Revised Local PlanDecided
  6. Revised Local Development SchemeNoted

More from High Peak Cabinet

All decisions
MeetingDecisionOutcome
11 Aug 2026 Forward PlanDECISION: That the be approved for publication. Approved Open
11 Aug 2026 Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. Approved Open
11 Aug 2026 Fourth Quarter - Finance, Procurement & Performance ReportsDECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A... Noted Open
11 Aug 2026 Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... Approved Open