CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Audit & Accounts Committee, Friday 5 June 2026 at 10.00am

External Audit Plan - Grant Thornton. (TOR: External Audit 4)

Decided Finance 1 paper

AI summaryHigh Peak's Audit & Accounts Committee received Grant Thornton's external audit plan covering Staffordshire Moorlands District Council for the year ending 31 March 2026, with a proposed fee of £157,131.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee noted the plan, no approval sought
Money£157,131 proposed feeDown from £163,192 in 2024/25
What happens nextFinal audit visit July to early November 2026. Sign off at committee on 20/11/2026
Who it affectsStaffordshire Moorlands District Council auditPlan also references High Peak shared operations and joint journals

What was decided

The committee received the Grant Thornton external audit plan update for the year ending 31 March 2026. Report P1, P2

The plan covers the statutory audit of Staffordshire Moorlands District Council, including the three significant risks identified by the auditor. Report P1, P15, P18, P26, P31

The auditor's risk assessment found no significant weaknesses in value for money arrangements, with prior year improvement recommendations to be followed up. Report P15, P78, P82, P83

Why

Statutory audit requirements under the Code of Audit Practice 2024, with new earlier backstop deadlines for publishing audited accounts from 2025/26 onwards. Report P8, P11, P73

The auditor identified three significant risks: management override of controls, valuation of land, buildings and investment property, and valuation of the gross pension liability (£68.24 million at 31 March 2025). Report P15, P18, P26, P31

Six of thirteen prior year recommendations remain in progress or not addressed, including heritage assets revaluation, IT administrator access, and depreciation policy. Report P46, P47, P49, P51, P54

What happens next

Interim audit work takes place from March to early April 2026, with early sample testing from July 2026 to meet the internal deadline of 30 November 2026. Report P8, P15, P70, P89, P90

Final audit visit runs from July to early November 2026, with the Audit and Accounts Committee sign off scheduled for 20/11/2026 and a backstop publication date of 31 January 2027. Report P8, P89, P90

The auditor asks the Authority to arrange a November 2026 committee meeting, ensure resources for interim work, and notify promptly of any issues or delays. Report P8

The money

  • £157,131 Proposed audit fee for Staffordshire Moorlands District Council for 2025/26 (Exc. VAT) Report P99, P102, P116
  • £163,192 Previous year (2024/25) scale fee and actual fee charged Report P99, P102
  • £98,750 Total non-audit services fees (Housing Benefits certification, CFO Insights, Place Analytics) Report P115, P116
  • £40,000 Housing Benefits 24/25 assurance service fee Report P111
  • £40,500 Housing Benefits 25/26 assurance service fee Report P111
  • £8,250 CFO Insights subscription fee Report P114
  • £10,000 Place Analytics fee Report P115
  • £1,040k Planning materiality (approximately 2.5% of gross operating costs) Report P15, P42
  • £780k Performance materiality (75% of overall materiality) Report P42
  • £52k Clearly trivial threshold for reporting uncorrected misstatements Report P15, P42
  • £19,000 Specific materiality for senior officer disclosure notes Report P42
  • £68.24 million LGPS gross pension liability at 31 March 2025 Report P31

Options considered

  • Chosen: Receive the Grant Thornton external audit plan update. Standard committee practice to note the external auditor's plan; no alternative options were presented in the papers. Report P1

Implications

  • Financial: Audit fee reduced from £163,192 to £157,131; material misstatement risk areas include pension liability valuation and property valuations. Report P15, P26, P31, P99
  • Legal: The plan sets out how the auditor will meet statutory responsibilities under the Code of Audit Practice 2024, including the Accounts and Audit (Amendment) Regulations 2024 backstop regime. Report P8, P11, P73
  • Risk: Six of thirteen prior year recommendations are not yet fully addressed, including IT administrator access, payroll reporting, depreciation policy, and heritage asset revaluation. Report P46, P47, P49, P51, P54
  • Staffing: The auditor asks the Authority to ensure sufficient resources are available to support interim audit work and notify promptly of any issues or delays. Report P8
  • Other: Non-audit services from Grant Thornton total £98,750, with safeguards in place to address self-interest and self-review threats to independence. Report P111, P114, P115, P116

Who and where

  • Staffordshire Moorlands District Council (primary subject of the audit plan) Report P1, P11
  • High Peak Borough Council (referenced through shared finance system, inter-authority journals, and joint operations with Alliance Environmental Services, Alliance Norse Limited, and Alliance Leisure Limited) Report P11, P57, P63
  • Council taxpayers and residents (users of the financial statements) Report P37, P43
  • Members of the Audit and Accounts Committee at both councils Report P8, P11, P75

Timeline

  • 23 March 2026: Audit plan date of issue Report P2
  • 31 March 2026: Financial year end Report P89, P90
  • March / April 2026: Interim audit visit period Report P70, P89, P90
  • 30 June 2026: Formal deadline for the Authority to publish draft accounts Report P8
  • August / September 2026: Anticipated availability of Nicholson Institute insurance valuation following re-opening Report P47
  • July, October 2026: Final audit visit and fieldwork period Report P89, P90
  • October 2026: Audit and Accounts Committee close out Report P89
  • November 2026: Internal deadline of 30 November 2026 (dry run for future years); audit completion target Report P8, P89, P90
  • 20 November 2026: Audit and Accounts Committee sign off Report P89
  • 31 January 2027: Backstop statutory deadline for publishing audited financial statements for year ended 31 March 2026 Report P8

Plain English for the jargon

  • Backstop: Statutory deadline by which local authority audited financial statements must be published, introduced under the Accounts and Audit (Amendment) Regulations 2024.
  • VFM: Value for Money, the auditor's assessment of whether proper arrangements are in place for economy, efficiency and effectiveness.
  • LGPS: Local Government Pension Scheme.
  • IAS 19: International Accounting Standard for employee benefits, governing pension liability accounting.
  • IFRS 16: International Financial Reporting Standard for leases, requiring recognition of lease assets and liabilities.
  • CIPFA: Chartered Institute of Public Finance and Accountancy, publisher of the accounting code for local authorities.
  • PSAA: Public Sector Audit Appointments, the body responsible for appointing external auditors to local authorities.
  • NAO: National Audit Office, issuer of the Code of Audit Practice.
  • MHCLG: Ministry of Housing, Communities and Local Government.
  • ISA (UK): International Standards on Auditing (UK), the auditing standards applicable in the United Kingdom.
  • ITGC: IT General Controls, controls over IT systems relevant to financial reporting.
  • AAR: Auditor's Annual Report, the auditor's vehicle for reporting on value for money arrangements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item93

Resolved

That the update be received.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Audit & Accounts Committee

The Audit Plan for Staffordshire Moorlands District Council Year ending 31 March 2026

Date of issue 23 March 2026

The Audit Plan 1 Commercial in Confidence

Contents

Section Page The Backstop 03 Introduction and headlines 04 Risks identified and Other matters 06 Our approach to materiality 12 Progress against prior year recommendations 14 IT audit strategy 22 Interim audit work 23 Value for money arrangements 24 Logistics, our team and communications 28 Fees and related matters 30 Independence considerations 32 Communication of audit matters with those charged with governance 35 Financial reporting changes 37

The Audit Plan | 2 © 2026 Grant Thornton UK LLP Commercial in Confidence

The Backstop

The Future of the Backstop Local Audit Recovery MHCLG have asked us as a firm to report by 31 July On 30 September 2024, the Accounts and Audit In our audit report for the year ended 31 March 2026, on a case by case basis, our assessment of (Amendment) Regulations 2024 came into force. 2025, we issued an unqualified opinion and as a local authorities’ ability to both maintain and where This legislation introduced a series of backstop result no rebuilding of assurance is required. necessary rebuild assurance. Having a clear, agreed dates for local authority audits. These Regulations project plan to complete our work on both the Our Work financial statements and the VfM by the end of require audited financial statements to be published In order to meet future statutory deadlines, for by a specific date. The upcoming backstop dates November 2026 is a key part of this assurance. 2025/26 we will be working towards an internal are as follows: deadline of 30 November 2026, as a dry run for Our ask of the Authority • for years ended 31 March 2026 by 31 January future years. Whilst we recognise that the formal • Arrange an Audit and Accounts Committee 2027 deadline for you as a local authority to publish your meeting for November 2026. • for years ended 31 March 2027 by 30 November draft accounts is 30 June 2026, we feel an important first step towards achieving closure by the • Ensure sufficient resources are available to 2027; and support all interim audit work. end of November is to complete early testing • for years ended 31 March 2028 by 30 November wherever possible. With this in mind, we look to • Notify us promptly of any issues or delays so that 2028. undertake more significant early testing during our we can plan accordingly. The Regulations are supported by the National Audit interim audit visit. We will also look to complete Office’s (NAO) Code of Audit Practice 2024. The initial sample testing from July. backstop dates were introduced to clear the backlog We will engage early with your finance team to of historic financial statements and support the clearly set out our expectations and what is needed reset of local audit. Where audit work is not to make a success of these plans, and we ask that complete, this will give rise to a disclaimer of you work with us to achieve this. opinion. This means the auditor has not been able to form an opinion on the financial statements.

The Audit Plan | 3 © 2026 Grant Thornton UK LLP Commercial in Confidence

Introduction and headlines

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Audit Plan: Grant Thornton. (TOR: External Audit 4)Report 987 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 26 attended
MS
Councillor Matthew SpoonerChair, present
CE
Councillor Charlotte EdwardsVice-Chair, present
JC
Councillor Jo CoxCommittee Member, apologies
KF
Councillor Keith FlunderCommittee Member, apologies
AH
Councillor Andrew HartCommittee Member, absent
DP
Councillor Dave ProudloveCommittee Member, apologies
CS
Councillor Charlie SmithCommittee Member, apologies
MW
Councillor Michael WorthingtonCommittee Member, absent
NY
Councillor Nigel YatesCommittee Member, present
JB
John BerrisfordAdvisory Member, present
MD
Member Diary SMDCOfficer, expected
EB
Emily BennettsOfficer, expected

All 26 on the meeting page

On this subject at High Peak

Search all
  1. External Audit Plan - Grant Thornton. (TOR: External Audit 4)This decision
  2. Audit Committee Update - Grant Thornton. (TOR: External Audit 2)Decided
  3. High Peak Borough Council Audit Plan 2025 - 2026 (External Audit)Noted
  4. Audit Progress and Sector Update Report (External Audit)Noted
  5. Audit Findings Report - External AuditApproved
  6. Interim Auditors' Annual Report for the year ended 31 March 2025 - External AuditNoted

More from High Peak Audit & Accounts Committee

All decisions
MeetingDecisionOutcome
5 Jun 2026 Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... Approved Open
5 Jun 2026 Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. Decided Open
5 Jun 2026 Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. Decided Open
5 Jun 2026 Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. Approved Open
5 Jun 2026 Internal Annual Strategy and Annual Audit Plan (TOR: Internal Audit 3)That the Council’s Internal Audit Strategy 2026-2028 and Internal Audit Plan for 2026/27 be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies