CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
High Peak Borough Council
Audit & Accounts Committee, Friday 5 June 2026 at 10.00am

Audit Committee Update - Grant Thornton. (TOR: External Audit 2)

Decided Finance 1 paper

AI summaryHigh Peak Borough Council's Audit and Accounts Committee received an update from its external auditor, Grant Thornton, on progress with the 2025/26 accounts audit and a set of sector developments.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee noted Grant Thornton's progress and sector update
Money£157,131 audit feeScale fee for the 2025/26 audit, set by PSAA
What happens next20 November 2026Audit Findings Report and Auditor's Annual Report due
Who it affectsCouncil and residentsExternal audit of 2025/26 financial statements

What was decided

The Committee resolved to receive the Grant Thornton audit progress and sector update report.

Why

Grant Thornton provided the report so the Committee could monitor delivery of external audit responsibilities and consider emerging sector issues. Report P7, P8, P12

The Committee is asked to note progress on the 2025/26 financial statements audit and the value for money planning, which has identified no significant weakness risks so far. Report P12

What happens next

The final accounts audit will run from 29 June 2026, with all work scheduled to complete by 30 November 2026 and reports tabled at the 20 November 2026 Committee meeting. Report P12, P14, P15

The Housing Benefit Subsidy certification deliverable is planned but its date is still to be confirmed. Report P18

Sector updates flag upcoming matters for the Committee to track, including the Crisis and Resilience Fund from 1 April 2026 and the new Local Outcomes Framework published on 9 February 2026. Report P37, P50

The money

  • £157,131 PSAA scale fee for the 2025/26 Council audit Report P12

Implications

  • Financial: Audit fee of £157,131 for 2025/26 reflects increased auditor workload and a shortage of audit firms willing to take on the work. Report P12
  • Legal: An external audit opinion on the 2025/26 financial statements will be issued at the 20 November 2026 Committee meeting. Report P14, P15
  • Risk: Grant Thornton notes that workforce shortages, recruitment challenges and rising complexity limit capacity to deliver transformation at the required pace in local government finance. Report P22
  • Other: The Committee is asked to consider how the Council handles new 2025/26 CIPFA Code changes on non-investment asset valuations and indexation. Report P25, P26

Who and where

  • The Council's finance team, which has responded promptly to auditor queries Report P12
  • Audit and Accounts Committee members, who receive the update and may wish to consider the sector issues raised Report P7, P8
  • Council taxpayers and residents, who rely on the audited accounts for assurance over public spending Report P57

Timeline

  • 23 February 2026: Interim audit work commenced Report P12
  • 5 June 2026: Audit Plan presented to the Committee for approval Report P12, P14
  • 29 June 2026: Final accounts audit begins Report P12
  • 20 November 2026: Audit Findings Report, Auditor's Report and Auditor's Annual Report due to Committee Report P14, P15
  • 30 November 2026: Target date for completion of all audit work Report P12

Plain English for the jargon

  • PSAA: Public Sector Audit Appointments, the body that sets scale fees and appoints auditors to principal local authorities
  • CIPFA Code: The Code of Practice on Local Authority Accounting in the United Kingdom, issued by the Chartered Institute of Public Finance and Accountancy
  • s151 officer: The local authority chief finance officer designated under section 151 of the Local Government Act 1972
  • Backstop: Statutory deadlines introduced to clear the backlog in local audit opinions, with disclaimed opinions used where work was incomplete
  • Crisis and Resilience Fund (CRF): New government fund from 1 April 2026, replacing the Household Support Fund, providing £1 billion a year in England until March 2029 to help low-income families with financial shocks
  • Value for Money: The auditor's work under the Code to assess whether the Council has proper arrangements for securing economy, efficiency and effectiveness
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item94

Resolved

That the update be received.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Audit & Accounts Committee

Staffordshire Moorlands District Council

Audit progress report and sector updates

May 2026 Commercial in Confidence

Agenda

1 Audit progress report 03 2 Introduction 04 3 Progress as at May 2026 05 4 Audit deliverables 06 5 Sector updates 08 6 Audit Committee Resources 19

© 2026 Grant Thornton UK LLP Audit Progress & Sector Updates | 2 Audit Progress Report Commercial in Confidence

Introduction

Richard Anderson This paper provides the Audit and Accounts Committee with a report on progress in delivering our Engagement Lead responsibilities as your external auditors. T: +44(0)121 812 7658 E: [email removed] The paper also includes a series of sector updates in respect of emerging issues which the Committee may wish to consider.

Members of the Audit and Accounts Committee can find further useful material on our website, where we Lisa Morrey have a section dedicated to our work in the public sector. Here you can download copies of our publications: Manager Local government | Grant Thornton T: +44(0)121 232 5302 E: [email removed] If you would like further information on any items in this briefing or would like to register with Grant Thornton to receive regular email updates on issues that are of interest to you, please contact either your Engagement Lead or Engagement Manager.

Nokukhanya P Mkhize Assistant Manager T: +44(0)121 812 7683 E: [email removed]

© 2026 Grant Thornton UK LLP Audit Progress & Sector Updates | 4 Commercial in Confidence

Progress as at March 2026 Financial Statements Audit Value for Money Our 2025/25 audit planning and risk assessment is now complete and our Audit Our value for money planning work is now complete and has not identified any Plan has been agreed with management and will be presented to the Audit and risks of significant weakness and no additional risk-based procedures are Accounts Committee on 5 June 2026 for approval. specified at this stage. We will undertake sufficient work to document our Our interim audit work commenced on 23 February as planned and we made understanding of your arrangements as required by the Code and follow up the good progress on areas of early testing for months April to November 2026 in the improvement recommendations made in prior years as noted in out audit plan. following areas:- Audit Fees • Fees and charges PSAA publish their scale fees: Auditor appointments and scale fees 2023/24 - • Operating expenditure 2027/28 – PSAA . For Staffordshire Moorlands District Council these fees are £157,131 for the Council audit for the year ending 2026. These fees are derived • Starters and leavers from the procurement exercise carried out by PSAA in 2022. They reflect both • Housing benefit payments the increased work auditors must now undertake as well as the scarcity of audit firms willing to do this work. • Grant income • Council tax and non-domestic rates reliefs Events The finance team have responded promptly to our queries and work has We held a webinar for members of Audit Committees on 10th February 2026, to progressed as expected. There are no issues to draw to your attention at this discuss best next steps to take “After the Backstop”. A recording for the webinar stage. can be found here: After the Backstop | Grant Thornton In addition we have written to the Council’s external valuation experts, the We also held two Local Government Accounts webinars for preparers of Pension Fund Auditor and made requests for external confirmations from accounts on 5th and 11th February 2026, where we discussed a range of topics banks, lenders and borrowers to support our work on revaluations, pensions, for preparing the 2025/26 statements of account. cash and cash equivalents, investments and borrowings. The final accounts audit will take place from 29 June and it is our intention that all audit work will be complete by 30 November 2026 and reported to the Audit and Accounts committee on 20 November 2026. © 2026 Grant Thornton UK LLP Audit Progress & Sector Updates | 5 Commercial in Confidence

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Committee Update: Grant Thornton. (TOR: External Audit 2)Report 718 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 26 attended
MS
Councillor Matthew SpoonerChair, present
CE
Councillor Charlotte EdwardsVice-Chair, present
JC
Councillor Jo CoxCommittee Member, apologies
KF
Councillor Keith FlunderCommittee Member, apologies
AH
Councillor Andrew HartCommittee Member, absent
DP
Councillor Dave ProudloveCommittee Member, apologies
CS
Councillor Charlie SmithCommittee Member, apologies
MW
Councillor Michael WorthingtonCommittee Member, absent
NY
Councillor Nigel YatesCommittee Member, present
JB
John BerrisfordAdvisory Member, present
MD
Member Diary SMDCOfficer, expected
EB
Emily BennettsOfficer, expected

All 26 on the meeting page

On this subject at High Peak

Search all
  1. Audit Committee Update - Grant Thornton. (TOR: External Audit 2)This decision
  2. External Audit Plan - Grant Thornton. (TOR: External Audit 4)Decided
  3. Audit Committee Update - Grant ThorntonDecided
  4. Audit Findings Report (Grant Thornton) (TOR: External Audit 2)Noted
  5. Auditor's Annual Report (Grant Thornton) (TOR: External Audit 2)Decided
  6. Audit Progress and Sector Update Report - Grant Thornton (TOR: External Audit 2)Decided

More from High Peak Audit & Accounts Committee

All decisions
MeetingDecisionOutcome
5 Jun 2026 Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... Approved Open
5 Jun 2026 External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. Decided Open
5 Jun 2026 Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. Decided Open
5 Jun 2026 Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. Approved Open
5 Jun 2026 Internal Annual Strategy and Annual Audit Plan (TOR: Internal Audit 3)That the Council’s Internal Audit Strategy 2026-2028 and Internal Audit Plan for 2026/27 be approved. Approved Open