AI summaryHigh Peak Borough Council's Portfolio Holder has approved £70,990 from Climate Change Reserves to fund biodiversity, decarbonisation, EV charger and related projects running from 2025/26 to 2027/28.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSpend from Climate Change Reserves to projects in Appendix A
Money£70,990 approved, from £74,994 remaining balanceOf a £196,452 reserve, with £4,004 held back
What happens nextNot stated
Who it affectsNot stated

What was decided

The Portfolio Holder approved the proposed budget allocation of £70,990 from the Climate Change Reserves to the projects listed in Appendix A of the report. Report 2.1, 3.4

Six project areas will be funded, covering biodiversity in parks and green spaces, Air Aware, ecological surveys, sustainable events guidance, decarbonisation of council assets, and EV charger maintenance. Report 3.5, P7

The remaining £4,004 balance is to be held and managed by the Communities and Climate Change service to cover inferred or emerging project costs through to 2028. Report 3.7

Why

The Joint Climate and Nature Steering Group formally approved the updated Climate Change and Nature Delivery Plan on 20 October 2025, and the council needs funds to deliver its actions. Report 3.1, 7.4, 7.6

The funding supports Aim 4 of the Corporate Plan 2023-27: to protect and improve the environment and respond to the climate emergency declared by the council in 2019. Report 4.1, 7.1

It also helps meet the council's Plan for Nature, adopted in October 2023, and the Nature Recovery Declaration adopted in May 2024, including the statutory duty to conserve and enhance biodiversity. Report 7.2, 6.7, P24

What happens next

Officers in the Communities and Climate Change service will manage the reserve and coordinate delivery with partners and other council services, using existing workforce capacity. Report 6.2, P16

The Joint Climate and Nature Steering Group will meet about six times a year to oversee delivery, and a six-month and an annual report will be produced on progress. Report 8.3, 8.5

Any spend given to parties outside the council must be covered by an enforceable agreement in line with procurement rules to ensure funds are used as intended. Report 6.5, P20

The money

  • £196,452 Current balance of Climate Change Reserves for Staffordshire Moorlands, covering 2026/27 to 2027/28 Report 3.2, P18
  • £74,994 Remaining reserve after committed spend approved by delegated decision on 28 November 2025 Report 3.3
  • £70,990 Proposed allocation from remaining reserve for projects in Appendix A, covering 2025/26 to 2027/28 Report 3.4, 3.5, 3.6
  • £4,004 Residual balance to be held by Communities and Climate Change service for inferred or emerging costs through to 2028 Report 3.7

Options considered

  • Chosen: Approve £70,990 allocation from Climate Change Reserves to deliver Delivery Plan actions. Funds needed to carry out the actions in the updated Climate Change and Nature Delivery Plan Report 2.1, 3.4, 3.6
  • Rejected: Do not approve the proposed allocation. Would mean a number of actions in the Climate Change and Nature Delivery Plan are not delivered Report 5.1, P13

Implications

  • Financial: The earmarked Climate Change Reserve stands at £196,452, of which £70,990 is now allocated and £4,004 is held back for emerging costs. Report P18, 3.2, 3.4, 3.7
  • Legal: Spending has broad legal powers as it is incidental to a core council function, but external payments must be backed by an enforceable agreement under procurement rules. Report 6.5, P20
  • Equalities: No equality and diversity or equality impact assessment issues identified. Report 6.3
  • Climate: The budget supports the council's climate and sustainability commitments, decarbonisation of assets, EV charger upkeep, and the Plan for Nature and statutory biodiversity duty. Report 6.6, 6.7, P22, P24, 7.2
  • Staffing: Delivery will be coordinated by the existing Communities and Climate Change service workforce, with support from partners and other services. Report 6.2, P16
  • Other: The council will track progress through the new Joint Climate and Nature Steering Group, recognising the local government reorganisation context and aiming for a strong legacy. Report 8.3, 8.4, P38

Who and where

  • High Peak Borough Council's Communities and Climate Change service, which will manage the reserve and coordinate delivery Report 3.7, 6.2, P16
  • Joint Climate and Nature Steering Group, which will oversee delivery Report 3.1, 8.3
  • Partners and other council services supporting delivery of climate and nature projects Report 6.2, 7.7
  • Residents and community groups benefiting from biodiversity, air quality and decarbonisation projects in the borough Report 3.5, P7, 7.1

Timeline

  • 2019: Council declared a climate emergency and pledged to work towards carbon neutrality by 2030 Report 7.1
  • 2021: Climate change action plans approved and adopted Report 7.1
  • October 2023: Council adopted its Plan for Nature Report 7.2
  • May 2024: Council adopted a Nature Recovery Declaration Report 7.2
  • 20 October 2025: Joint Climate and Nature Steering Group approved the updated Climate Change and Nature Delivery Plan Report 3.1
  • 28 November 2025: Committed spend for agreed projects was approved via delegated decision report Report 3.3
  • 2025/26 to 2027/28: Delivery period for projects to be funded by the proposed £70,990 allocation Report 3.4, 3.5
  • Through to 2028: Period over which the remaining £4,004 may be used to cover inferred or emerging project costs Report 3.7

Plain English for the jargon

  • Climate Change Reserves: Earmarked funds set aside by the council to tackle climate change and mitigate its impact on council services
  • Climate and Nature Delivery Plan: Updated plan adopted in October 2025 setting out the council's climate and nature objectives, aims and actions
  • Joint Climate and Nature Steering Group: New group meeting about six times a year to oversee, manage, monitor and review delivery of the council's climate and nature plans
  • Plan for Nature: Council document adopted in October 2023 reviewing the state of nature locally and recommending where nature recovery efforts should be prioritised
  • Nature Recovery Declaration: Declaration adopted in May 2024 formally recognising the nature crisis and committing to work with partners on nature recovery
  • Biodiversity Net Gain: Legislation requiring development to leave biodiversity in a better state than before, listed among related strategies in the report
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item1

Resolved

DECISION: The Portfolio Holder approved the proposed budget allocation to the projects identified in Appendix A of the report. A RECORD OF ANY CONFLICT OF INTEREST DECLARED: None A NOTE OF ANY DISPENSATION, IF GRANTED: None
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Cabinet Delegated Decisions

Recommendation

2.1That the Portfolio Holder approves the proposed budget allocation to the projects identified in Appendix A.

Executive summary

3.1The newly formed Joint Climate and Nature Steering Group formally approved the updated Climate Change and Nature Delivery Plan including associated actions on 20 October 2025.

3.2The Climate Change Reserves for Staffordshire Moorlands currently stands at £196,452, to cover the financial years 2026/27 - 2027/28.

3.3The committed spend for agreed projects was formally approved via delegated decision report on 28 November 2025 leaving the remaining balance of the Climate Change Reserves at £74,994.

3.4To deliver on the actions detailed in the Climate Change and Nature Delivery Plan, it is proposed that £70,990 is allocated from the remaining balance of the Climate Change Reserves for delivery of a variety of projects and activities covering 2025/26 – 2027/28 to support the delivery of the Councils climate and nature objectives.

3.5The proposed spend includes allocation of spend for the following projects:

• Biodiversity initiatives in parks and green spaces • Air Aware • Ecological surveys • Sustainable events guidance • Decarbonisation of Council Assets • EV charger maintenance

3.6The full details of the proposed allocation can be found in Appendix A.

3.7It is proposed that the remaining balance of £4,004, following approval of the proposed allocation of £70,990, should be assigned and managed by the Communities and Climate Change service in line with Climate and Nature Delivery Plan aims. This balance should be used to cover any inferred costs or emerging project costs that arise between now and 2028, particularly as new initiatives and projects are implemented.

4. How this report links to Corporate Priorities

4.1This report relates to all Corporate Priorities, but in particular Aim 4 of the Corporate Plan for 2023-27 seeks to “Protect and improve the Environment including responding to the climate emergency” which directly relates to the implementation of the Climate Change and Nature Delivery Plan.

Alternative options

5.1To not approve the proposed allocation of the Climate Change Reserves budget and therefore not deliver on a number of the actions set out in the Climate Change and Nature Delivery Plan.

6. Implications

6.1Community safety, including safeguarding and prevention of terrorism None.

6.2Workforce

Officers within the Communities and Climate Change service will manage this reserve going forward and therefore delivery will be co-ordinated by the existing workforce and undertaken with support from partners and other services as relevant.

6.3Equality and Diversity/Equality Impact Assessment None. 6.4 Financial Considerations

At the time of writing, the Council carries an earmarked reserve set aside for the purposes of tackling climate change and mitigating the climate change impact of Council services. This reserve currently stands at £196,452, with proposals for spend set out within this report.

6.5Legal

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SM Proposed Spend 2025-2028 (1)Appendix A 69 KB Download
PDF
Climate Change ReservesReport 121 KB DownloadRead as text

At this meeting

Whole meeting
1Climate Change ReservesThis decision

On this subject at High Peak

Search all
  1. Climate Change ReservesThis decision
  2. Climate Change and Nature Delivery Plan Update - Performance Report October 25 to April 26Noted
  3. Climate Change ReservesApproved
  4. Climate Change ReservesApproved
  5. To confirm the appointment of Officers to the Joint Climate Change & Nature Steering Group as follows: Executive Director (Community Services) and Principal Climate Change OfficerDecided
  6. To confirm the appointment of Officers to the Joint Climate Change & Nature Steering Group as follows: Executive Director (Community Services) and Principal Climate Change OfficerDecided

More from High Peak Cabinet Delegated Decisions

All decisions
MeetingDecisionOutcome
6 Aug 2026 Leisure Facilities Capital ImprovementDECISION: That the Portfolio Holder for Leisure and Tourism approved the use of capital funds that had been included ... Approved Open
5 Aug 2026 Application to register Greenspace at Vicarage Road, Tean as an Asset of Community ValueDECISION: That the Portfolio Holder recommend to list the parcel of land/greenspace around Vicarage Road, Tean, Staff... Decided Open
28 Jul 2026 Alliance MyActive Wellbeing LimitedDECISION: 1) The appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd, be appr... Approved Open
21 Jul 2026 Proposed Dog Fouling Public Spaces Protection Order (PSPO)DECISION: 1) That commencement of statutory consultation on a proposed Dog Fouling Public Spaces Protection Order, be... Approved Open
10 Jul 2026 Application to register Royal Oak Hotel, 68 High Street, Cheadle, Stoke-on-Trent, ST10 1AN as an Asset of Community ValueDECISION: 1) That the listing of the Royal Oak Hotel, 68 High Street, Cheadle, Stoke-on-Trent, ST10 1ANbe approved; 2... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies