CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hillingdon
Central & South Planning Committee, Thursday 18 June 2009 at 2.30pm

Brunel University, Kingston Lane, Hillingdon - 532/APP/2009/566

Approved Planning 1 paper

Central & South Planning Committee approved this item on Thursday 18 June 2009. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

Resolved – 1. That details in compliance with conditions 12 'Landscape Maintenance', 13 'Screening of plant', 23 'Details of waste storage facilities', 25 'Details of access to building entrances', 26 'Details of car parking provision for wheelchair disabled people', 30 'External lighting scheme', 32 'Scheme for protecting the proposed building from noise' and 62 'External lighting' of outline planning permission 532/APP/2002/2237 dated 19/04/2004 as they relate to Phase 1 of development within Zone A10 be approved. 2. That the reserved matters of siting , design, external appearance and landscaping of a new Eastern Gateway Building (Zone A10 (Phase 1) in compliance with condition 3 of outline planning permission ref: 532/APP/2002/2237 dated 19/04/2004 be approved, subject to the conditions and informatives set out in the officer’s report and the condition on the addendum sheet amended as follows:- That the café facility and external seating area identified on the plans hereby approved shall be permitted to operate within the hours of 0700 hrs and 2200 hrs seven days a week, unless otherwise approved in writing by the Local Planning Authority. Reason To safeguard residential amenity in accordance with Policy OE1 of the Unitary Development Plan Saved Policies September 2007.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to Central & South Planning Committee

Report of the Corporate Director of Planning & Community Services

Address BRUNEL UNIVERSITY KINGSTON LANE HILLINGDON

Development: RESERVED MATTERS (DETAILS OF SITING, DESIGN, EXTERNAL APPEARANCE AND LANDSCAPING) OF A NEW EASTERN GATEWAY BUILDING (ZONE A 10 (PHASE 1) - GATEWAY), TOGETHER WITH DETAILS OF LANDSCAPING, LANDSCAPE MAINTENANCE, SCREENING OF PLANT, WASTE STORAGE FACILITIES, ACCESS TO BUILDING ENTRANCES, CAR PARKING PROVISION FOR WHEELCHAIR DISABLED PEOPLE, EXTERNAL LIGHTING, SCHEME FOR PROTECTING THE PROPOSED BUILDING FROM NOISE AND EXTERNAL LIGHTING, IN COMPLIANCE WITH CONDITIONS 3, 12, 13, 23, 25, 26, 30, 32 AND 62 (AS THEY RELATE TO ZONE A10 (PHASE 1)) OF OUTLINE PLANNING PERMISSION REF: 532/APP/2002/2237 DATED 19/04/2004 'MASTER PLAN PROPOSALS' LBH Ref Nos: 532/APP/2009/566

Drawing Nos: S2111/51-04 rev F (GA Zone 4) S2111/52-01 rev F (Levels and Surface Water Draining Masterplan) 07071/P-101 rev A (Site Location Plan) 07071/P-102 rev A (Existing Site Plan) 07071/P-105 rev A (Existing Context Sections) 07071/P-106 rev A (Existing Site Sections) 07071/P-110 rev A (Basement Floor Plan) 07071/P-111 rev A (Ground Floor Plan) 07071/P-112 rev A (First Floor Plan) 07071/P-113 rev A (Second Floor Plan) 07071/P-114 rev A (Third Floor Plan) 07071/P-115 rev A (Fourth Floor Plan) 07071/P-116 rev A (Roof Plan) 07071/P-120 rev A (Proposed Context Sections) 07071/P-121 rev A (Proposed East and West Elevations) 07071/P-122 rev A (Proposed North and South Elevations) 07071/P-123 rev A (Typical Proposed Elevation: 1. Wrap, 2. Audtorium) 07071/P-124 rev A (Proposed Entrance Elevation) 07071/P-125 rev A (Proposed Atrium Elevations) 07071/P-130 rev A Proposed Sections A-A & B- B) S2111/51-01 rev G (External Works Masterplan) S2111/51-02 rev F (External Works GA Zone 2) S2111/51-03 rev F (GA Zone 3) S2111/52-02 rev D (External Works GA Zone 2 - Levels and Surface Water Drainage) S2111/52-03 rev D (External Works GA Zone 3 - Levels and Surface Water Drainage) S2111/52-04 rev D (External Works GA Zone 4 Levels and Surface Water Drainage ) S2111/53-06 rev B (Gabion Retaining Wall Zone 2) S2111/53-08 rev B (Relocated Vehicle Control Barrier) S2111/53-09 rev C (External Sections)

Central & South Planning Committee - 18th June 2009 PART 1 - MEMBERS, PUBLIC & PRESS S2111/55-01 rev B (Planting Masterplan) S2111/55-02 rev C (Tree Retenion and Removal Plan) Deaign and Access Statement Version 02 and appendices A - G (Issue Date 06-03-2009)

Date Plans Received: 20/03/2009 Date(s) of Amendment(s): Date Application Valid: 20/03/2009

1. SUMMARY The application seeks reserved matters approval for the appearance, landscaping, layout and scale of a new Gateway Building at the Eastern Entrance to Brunel University. The proposed building would have a gross external floorspace of 7,664 sq.m providing space for a new auditorium, academic and reception space.

The principle of a building in this location has been established under the outline master plan for Brunel University and the current proposal is considered to fully comply with the terms and conditions of this consent.

The design of the building and surrounding landscaping has been addressed in the context of the surrounding street scene, the retention of a 25m landscape buffer and the recently constructed Mary Seacole Building. It is considered the building would form part of a strong gateway pair of buildings at the Eastern Entrance to the campus, appropriate in terms of the surrounding character of the area and street scene.

It is not considered that the proposal would have any detrimental impacts on nearby residents or the closest of the student accommodation.

The proposal demonstrates the incorporation of sustainability measures through its design and is considered to exceed the sustainability requirements set out within the London Plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brunel University, Kingston Lane, Hillingdon: 532/APP/2009/566Report 362 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JH
Councillor John HensleyChair, present
JC
Councillor Judith CooperVice-Chair, present
MB
Councillor Michael BullCommittee Member, present
PB
Councillor Paul ButtivantCommittee Member, present
JD
Councillor Janet DuncanCommittee Member, present
PJ
Councillor Patricia JacksonCommittee Member, apologies, sent representative
CM
Councillor Carol Melvin BSc (Hons)Reserve, present as substitute
JO
Councillor John OswellCommittee Member, present

On this subject at Hillingdon

Search all
  1. Brunel University, Kingston Lane, Hillingdon - 532/APP/2009/566This decision
  2. Heinz Wolff Building, Brunel University - 532/APP/2021/330Approved
  3. Brunel University Playing Fields - 532/APP/2020/1978Approved
  4. Quad North Building, Brunel University, Kingston Lane - 532/APP/2020/1852Approved
  5. Quad North Building, Brunel University, Kingston Lane, Hillingdon - 532/APP/2020/590Approved
  6. Gaskell Building, Brunel University - 532/APP/2019/3271Approved

More from Hillingdon Central & South Planning Committee

All decisions
MeetingDecisionOutcome
4 May 2021 To sign and receive the minutes of the previous meeting dated 7 April 2021That the minutes of the meeting dated 7 April 2021 be approved as an accurate record subject to an amendment to indic... Approved Open
4 May 2021 2 De Salis Road, Hillingdon - 38071/APP/2020/36391) That the application be refused; and 2) That delegated authority be granted to the Head of Planning to explore the... Refused Open
4 May 2021 43 Sweetcroft Lane, Hillingdon - 17412/APP/2021/5991) That the application be refused; and 2) That delegated authority be granted to the Head of Planning, in consultati... Refused Open
4 May 2021 Heinz Wolff Building, Brunel University - 532/APP/2021/330That the application be approved. That the application be approved. Approved Open
4 May 2021 Harmondsworth Landfill Site, Harmondsworth Lane - 43155/APP/2020/4267That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on... Approved Open