Resolved – That the application be approved, subject to the conditions and informatives set out in the officer’s report and an additional condition and informative as follows:- All car parking on the site shall be related to the vehicular workshop and MOT centre uses only. REASON To accord with the terms of the application in the interests of the character and openness of the Green Belt and amenity of the area in accordance with Policies OL4 and OE1 of the Hillingdon Unitary Development Plan Saved Policies (September 2007). The parking on site shall be in strict accordance with the layout shown on Drw . No. NOV/08/12A received 30/06/09 and no additional parking shall take place elsewhere on site. REASON To accord with the terms of the application in the interests of the character and openness of the Green Belt and amenity of the area in accordance with Policies OL4 and OE1 of the Hillingdon Unitary Development Plan Saved Policies (September 2007). Add informative: You are advised that no other uses other than those specified by this permission should be carried out on site.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Corporate Director of Planning & Community Services
Address FORMER HARLINGTON SERVICE STATION (SOUTH) HIGH STREET HARLINGTON Development: Use of site to include a MOT centre, erection of 2m high palisade fencing and alterations to parking layout (Part Retrospective Application).
LBH Ref Nos: 22/APP/2008/3462
Drawing Nos: NOV/08/12A - Revised Jun 09 (Block Plan) 1:1250 Location Plan NOV/08/12 (Floor Plan and Elevations) Design and Access Statement Letter dated 29th June 2009
Date Plans Received: 15/12/2008 Date(s) of Amendment(s): 15/12/2008 Date Application Valid: 14/01/2009 14/01/2009 30/06/2009 DEFERRED ON 21st April 2009 FOR FURTHER INFORMATION .
Members may recall that this application was deferred from the Central and South Committee meeting of the 21st April 2009 in order to allow further information to be submitted concerning the approved use of the site and a plan showing the extent of works being proposed, together with other uses operating from the site.
A letter dated 29th June 2009, together with a revised drawing, No. NOV/08/12A have been received. The letter states that the existing canopy at the side of the building will be removed. Car sales on site will also cease once permission has been secured for MOT use. The plans show parking spaces along the frontage of the site and on the eastern side boundary together with three disabled person spaces adjacent to the building. The plans also show a small fenced off compound for tyre storage to the rear of the building, with 2m high green painted palisade fencing. The existing palisade fencing is also shown to be green painted with low level planting of evergreen shrubs behind.
With the cessation of car sales and the removal of the canopy that is being used for car washing, the only uses on site would be the existing vehicular workshop with the proposed MOT use. 1. SUMMARY The existing garage use on the site is an established use within the Green Belt. The application would involve the use of part of the existing vehicle workshop to provide an MOT testing area, and it is not considered to result in a material alteration to the current use on the site by way of visual amenity, noise or disturbance and is therefore considered acceptable. No objections are raised to the palisade fencing.
The application is therefore recommended for approval. 2. RECOMMENDATION APPROVAL subject to the following:
Central & South Planning Committee - 21st July 2009 PART 1 - MEMBERS, PUBLIC & PRESS 1 T8 Time Limit - full planning application 3 years The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990. 2 OM1 Development in accordance with Approved Plans The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the development accords with the terms of the application in order to safeguard the character of the surrounding area and the openness of the Green Belt, in accordance with policies BE13 and OL4 of the adopted Hillingdon Unitary Development Plan, Saved Policies (September 2007).
3 HLC5 Industrial and Commercial Development The premises shall not be used except between 0800 hours and 1800 hours Mondays to Fridays, between 0800 hours and 1600 hours on Saturdays and at no time on Sundays and Bank Holidays.
REASON To safeguard the residential amenity of the occupiers of adjoining and nearby properties in accordance with Policy OE3 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.