London Borough of Ealing, (Southall Gas Works) Hayes By Pass, Hayes
DecidedPlanning1 paper
Central & South Planning Committee decided this item on Tuesday 15 September 2009. Below is the council's own wording, with the papers it was decided on.
Resolved That the London Borough of Ealing be advised that the London Borough of Hillingdon has considered the application and raised strong objection to the scheme on the following grounds: 1. The applicant has failed to demonstrate that the road network can accommodate the levels of traffic that would be generated by the development, nor has it been demonstrated that there would not be a significant worsening of conditions on the highway network within the London Borough of Hillingdon. In particular objection is raised to: · The impact ... view the full minutes text for item 84.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
1.1The majority of this 44.7Ha site is located in the London Borough of Ealing, immediately to the east of the Grand Union canal. The proposed redevelopment of the former Southall Gas Works offers significant regenerative benefits (including remediation of contaminated land and provision of a considerable amount of housing).
1.2As this report relates to the request from the London Borough of Ealing for observations and comments in relation to the planning application it has received, the issue for consideration by the Central and South Planning Committee is the impact of the proposed development on the London Borough of Hillingdon (rather than the determination of the application itself).
1.3This is a substantial scheme with the potential to cause significant adverse impacts on the London Borough of Hillingdon. The application in its current form does not propose to adequately mitigate impacts, as such the proposal would: • Cause harm to the highways network; • Result in the loss of ecologically significant wildlife habitat; and • Result in future residents of the scheme intensively using land and facilities within the London Borough of Hillingdon (land and facilities which do not have the spare capacity necessary to cope with additional loading which would be resultant from this scheme); • Cause harm to the setting of the Green Belt and Grand Union Canal.
1.4Additionally, supporting documentation accompanying the scheme fails to demonstrate that the scheme would not result in potentially adverse economic impacts on existing centres and their shopping areas. Concern is also raised
Central & South Planning Committee – 15 September 2009 PART I – MEMBERS, PUBLIC AND PRESS in relation to the monitoring and management of contaminated material during remediation works (including the transportation of contaminated materials through the London Borough of Hillingdon).
1.5It is considered that the impact of the proposed development on land within the London Borough of Hillingdon has not been adequately addressed by the Applicant.
Recommendation
That the London Borough of Ealing be informed that the London Borough of Hillingdon raises strong objection to the proposed scheme on the following grounds:
1. The applicant has failed to demonstrate that the road network can accommodate the levels of traffic that would be generated by the development, nor has it been demonstrated that there would not be a significant worsening of conditions on the highway network within the London Borough of Hillingdon. In particular objection is raised to: • The impact of the development on the Bilton Way, which would result in a queue from the Pump Lane / Bilton Way roundabout to the Hayes bypass slip road; • The lack of any assessment of impacts arising from the development on Pump Lane / Coldharbour Lane roundabout; • Three bus routes are proposed through Pump Lane (which has a width restriction). No details of measures to prevent HGV’s using the bus route to gain access to Coldharbour Lane are proposed; Lack of a turning head at the proposed dead end with the A312.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.