Resolved – That no objection has been raised subject to the consultations and informatives set out in the officer’s report and the Addendum Sheet and the following additional conditions: SUDS – WORDING TO BE PROVIDED Reason - WORDING TO BE PROVIDED Graywater drainage - WORDING TO BE PROVIDED Reason - WORDING TO BE PROVIDED
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Central & South Planning Committee, 24 pages
Report of the Head of Planning & Enforcement
Address P5 CAR PARK SEALAND ROAD HEATHROW AIRPORT
Development: Erection of an Energy Centre comprising two buildings (Energy Centre Building and Operations Building) and associated infrastructure (Consultation under Schedule 2, Part 18 of the Town and Country Planning (General Permitted Development) Order 1995).
LBH Ref Nos: 66849/APP/2010/479
Drawing Nos: 19757-00-GA-200-000011 2.0 (Ground Floor Layout) 19757-00-GA-200-000012 3.0 (Site & Location Plans) 19757-10-GA-200-000006 2.0 (First Floor Layout) 19757-20-GA-200-000005 2.0 (Roof Layout) 19757-XX-SE-200-000012 3.0 (Energy Centre Elevations) 19845-XX-SE-200-000002 3.0 (Operations Building External Elevations) 19757-XX-SE-200-000013 2.0 (Building Sections) 19757-00-GA-200-000013 2.0 (Landscape Plan) Schematic - Heat Links Plan Unnumbered GCI images Design and Access Statement dated December 2009 Supporting letter from Heathrow Airport Limited dated 26/02/10 Noise Assessment Report dated November 2009 Air Quality Assessment dated December 2009 Sustainability Statement dated November 2009
Date Plans Received: 02/03/2010 Date(s) of Amendment(s): Date Application Valid: 02/03/2010 1. SUMMARY BAA has submitted this proposal for consultation under Part 18 of the Town and Country Planning (General Permitted Development) Order 1995 (GPDO). It proposes the erection of an energy centre and associated infrastructure to serve the new proposed Terminal 2A (T2A) (formerly referred to as Heathrow East Terminal), Terminal 2B (T2B) (formerly referred to as the Midfield Pier), the Central Terminal Area (CTA) and Terminal 5 (T5), at the P5 Car Park at Heathrow Airport.
The outline planning permission for T2A, granted in July 2007 (ref: 62360/APP/2006/2942), included the provision of an energy centre, to serve the new terminal, in this location. An Environmental Impact Assessment accompanied that application, and a detailed design for the energy centre was subsequently approved in December 2008.
Since that time, and in compliance with the requirements of the S106 agreement, which formed part of the planning approval for T2A, BAA have developed a more strategic plan for the provision of energy across Heathrow. The aim of this is to provide increased flexibility of operation and to achieve wider CO2 reductions. Accordingly, the development goals for the airport have now changed such that the energy centre is required to not only serve T2A and T2B, but also the other terminals and buildings within the CTA. This has resulted in the need for significant changes to the functioning and scale of the proposed energy centre. As a result, details of the revised scheme can no
Central & South Planning Committee - 25th May 2010 PART 1 - MEMBERS, PUBLIC & PRESS longer be progressed under the original T2A planning consent and need to be progressed via a new application/consultation.
A Screening Opinion in respect of the new proposed energy centre was issued to the Council earlier this year, and it was subsequently confirmed that an Environmental Impact Assessment would not be required. Accordingly, the applicant has chosen to progress the proposal under Part 18 of the GPDO.
It is not considered that the proposal would have any significant adverse impacts in terms of visual or residential amenity and it would have significant benefits in terms of reducing emissions across the airport and meeting the goals set out in the Heathrow Wide Energy Strategy. The proposal complies with relevant UDP and London Plan policies and, accordingly, it is recommended that no objections be raised. 2. RECOMMENDATION No objection subject to the following consultations and informatives:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.