Resolved
Resolved – That the application be Approved , subject to the conditions and informatives set out in the officer’s report and addendum sheet circulated at the meeting.
Central & South Planning Committee approved this item on Tuesday 8 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the application be Approved , subject to the conditions and informatives set out in the officer’s report and addendum sheet circulated at the meeting.
Report of the Head of Planning & Enforcement
Address DATA CENTRE BUILDING (ANTONIN ARTAUD), BRUNEL UNIVERSITY KINGSTON LANE HILLINGDON
Development: Installation of Supply Generator and associated fuel tank.
LBH Ref Nos: 532/APP/2010/509
Drawing Nos: 60102068-DC-PA-E001 Rev B (Data Centre Location Plan) 60102068-DC-PA-E004 Rev A (Antonin Artaud Elevations) Design and Access Statement 60102068-DC-PA-E002 (Proposed Generator Location Plan) 60102068-DC-PA-E003 (Proposed Generator Floor Plans) E-mail from Turner & Townsend Project Management received 25/05/2010 at 15:12
Date Plans Received: 08/03/2010 Date(s) of Amendment(s): 08/03/2010 Date Application Valid: 19/03/2010 1. SUMMARY The application seeks the installation of an emergency supply generator, contained within an acoustic enclosure, and emergency fuel tank in the south eastern corner of the existing service yard to the south of the Antonin Artaud Building, which contains the University's Arts Centre and Data Centre. The proposed generator is to supply emergency power to the Data Centre.
The structure represents inappropriate development within the Green Belt, however the principle of the proposed generator within Site 2 of Brunel University, a major developed site, is considered acceptable.
The proposed generator has been located to minimise its impacts and would not be detrimental to the character or appearance of the area. In addition nearby trees would be retained which will assist with integrating this structure into this Green Belt setting.
Subject to an appropriate conditions the proposal would not be detrimental to the amenity of nearby occupiers.
Accordingly, the proposal is considered to comply with relevant planning policy and approval is recommended. 2. RECOMMENDATION APPROVAL subject to the following:
1 T8 Time Limit - full planning application 3 years The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990.
2 OM1 Development in accordance with Approved Plans
Central & South Planning Committee - 8th June 2010 PART 1 - MEMBERS, PUBLIC & PRESS The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the external appearance of the development is satisfactory and complies with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
3 NONSC Fuel Tank Height The fuel storage tank hereby approved shall be no greater than 2.2m in height from existing ground level.
REASON To ensure that the external appearance of the development is satisfactory and minimise impacts on the openess of the site in compliance with Policies OL1 and BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007) and Planning Policy Guidance 2 - Green Belts.
4 M1 Details/Samples to be Submitted No development shall take place until details and/or samples of all materials, colours and finishes to be used on all external surfaces have been submitted to and approved in writing by the Local Planning Authority.
REASON To ensure that the development presents a satisfactory appearance in accordance with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Data Centre Building (Antonin Artaud), Brunel University, Kingston Lane, Hillingdon: 532/APP/2010/509Report | 14 pages | DownloadRead as text |
Follow Central & South Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 May 2021 | To sign and receive the minutes of the previous meeting dated 7 April 2021That the minutes of the meeting dated 7 April 2021 be approved as an accurate record subject to an amendment to indic... | Approved | Open |
| 4 May 2021 | 2 De Salis Road, Hillingdon - 38071/APP/2020/36391) That the application be refused; and 2) That delegated authority be granted to the Head of Planning to explore the... | Refused | Open |
| 4 May 2021 | 43 Sweetcroft Lane, Hillingdon - 17412/APP/2021/5991) That the application be refused; and 2) That delegated authority be granted to the Head of Planning, in consultati... | Refused | Open |
| 4 May 2021 | Heinz Wolff Building, Brunel University - 532/APP/2021/330That the application be approved. That the application be approved. | Approved | Open |
| 4 May 2021 | Harmondsworth Landfill Site, Harmondsworth Lane - 43155/APP/2020/4267That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.