The Council's Budget: General Fund Revenue Budget and Capital Programme 2011/12

Approved Executive 4 papers

CABINET approved this item on Thursday 17 February 2011. Below is the council's own wording, with the papers it was decided on.

Item257

Resolved

That Cabinet approves for recommendation to Council: The General Fund revenue budget proposals for 2011/12 summarised at Appendix 1, including the detailed budget changes contained at Appendices 2 to 7; The proposed fees and charges included at Appendix 8; The capital programme set out at Appendix 9; The Treasury Management Strategy Statement, Annual Investment Strategy and Minimum Revenue Provision Statement for 2011/12 to 2013/14 as detailed in Appendix 11; That Cabinet notes the Corporate Director of Finance & Business Services’ comments regarding his responsibilities under the Local Government Act 2003. That Cabinet recommends to Council (as set out in Schedule C of the Constitution - Budget and Policy Framework Procedure Rules) that it resolves that Cabinet may utilise the general reserves or balances during the MTFF financial years 2011/12 to 2014/15 in respect of those functions which have been reserved to the Cabinet in Article 7 of the Constitution. Reasons for decision Cabinet considered its budget proposals and budget strategy for 2011/12 and beyond for approval by full Council. The revenue budget proposals had been developed to deliver a zero increase in Council Tax for 2011/12. They sought to do this whilst maintaining sound balances and reserves. The budget strategy had been delivered through a rigorous focus on identifying savings and efficiencies across the Council. This had been done through the Business Improvement Delivery Programme and monitored in conjunction with the Leader of the Council throughout the budget process. Cabinet outlined the challenge that it had in proposing a balanced budget for 2011/12 due to the national economic position and a noticeable reduction in Government funding. The need for significant savings of over £26m, more than double the £10.3m required the previous year, had been developed smartly based on more efficient delivery methods and implementing the new Council operating model, rather than service reductions. In proposing changes to the way local music services were provided, Cabinet noted that the Leader of the Council had chaired a meeting earlier that evening to listen to the views of young people, parents and others involved in the Music Service. Cabinet accepted to look again at the music service following the passing of the budget by setting up a working group led by Councillor Judy Kelly. The working group would report back in May with thorough proposals to maintain Hillingdon’s excellence in this area, whilst providing a more sustainable and efficient music service. Despite the savings required, Cabinet outlined a number of priority growth areas to support the delivery of Cabinet’s objectives for the Administration. These included the enhancement of the Careline and Telecareline service , further investment in Highways Maintenance and staffing for new Youth Centres and the extension of library opening hours. Each of the service Policy Overview Committees referred their comments on the draft budget to the Corporate Services and Partnerships Policy Overview Committee on 9 February 2011. Cabinet considered the Committee’s comments. Cabinet then recommended their budget proposals to full Council on 24 February 2011 in order to formally set the General Fund revenue budget, capital programme and Council Tax for the 2010/11 financial year. Alternative options considered and rejected Cabinet could have amended its growth proposals, added or removed new capital schemes or varied fees and charges, however this could have had a consequential impact on the revenue budget requirement and Council Tax. Officers to action: Christopher Neale and Paul Whaymand , Finance and Business Services Urgency Provisions This report had been circulated less than 5 working days before the Cabinet meeting and was agreed by the Chairman to be considered as urgent.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to CABINET

MTFF 2011/12 - 2014/15 Revenue Budget - Corporate Summary Appendix 1

Corporate Summary 2010/11 2011/12 2012/13 2013/14 2014/15 £(000s) £(000s) £(000s) £(000s) £(000s) Resources Increase in Council Tax Base (Band D properties) 1,417 1,166 750 400 400 Increase in Council Tax (%) 0.00% 0.00% 0.00% 2.50% 2.50% Collection Fund Deficit / (Surplus) -769 1,438 0 0 0 Council Tax Base (Band D properties) 97,952 99,118 99,868 100,268 100,668 Council Tax Band D (£) £1,112.93 £1,112.93 £1,112.93 £1,140.75 £1,169.27 Council Tax Revenues 109,783 108,870 111,150 114,380 117,710 Government Formula Grant 84,411 85,876 77,778 75,078 72,378 Area Based Grant 17,644 0 0 0 0 Council Tax freeze grant 0 2,765 2,765 2,765 2,765 Specific Education Grants 9,704 0 0 0 0 Early Intervention Grant 10,857 11,527 11,527 11,527 Learning Disability and Health Reform Grant 5,781 5,781 5,918 5,918 5,918 Preventing homelessness 100 580 580 580 580 Housing & Council Tax Benefit Subsidy Admin Grant 2,418 2,418 2,297 2,297 2,297 NHS S256 Agreement 2,728 2,610 2,610 2,610 Home Office Grant 300 300 300 300 Lead Local Flood Authority Grant 127 185 185 185 Grant Income 120,058 111,432 103,960 101,260 98,560 Total Resources 229,841 220,302 215,110 215,640 216,270 Budget Requirement

Roll Forward Budget 224,892 229,841 229,841 229,841 229,841

Inflation (non-schools) 600 1,980 3,400 7,400 12,400 Corporate Items 2,280 4,548 8,191 10,149 12,542 Service Pressures 8,197 7,369 7,337 7,314 7,314 Contingency 3,440 1,026 6,166 11,051 15,976 Priority Growth Items 712 1,776 2,826 3,941 5,076 Savings -10,280 -26,238 -42,651 -54,056 -66,879 Total Budget Requirement - all resources 229,841 220,302 215,110 215,640 216,270 Less non-formula grant -35,647 -25,556 -26,182 -26,182 -26,182 Budget Requirement 194,194 194,746 188,928 189,458 190,088

Budget Gap / (Surplus) 0 0 0 0 0 Summary 10/02/11 MTFF 2011/12 - 2014/15 Corporate Items Appendix 2 Description Net Variation from 2010/11 Budget 2011/12 2012/13 2013/14 2014/15 £(000s) £(000s) £(000s) £(000s) Corporate Items Increases LAA Reward Grant - falling out 3,040 3,040 3,040 3,040 Capital Programme financing costs -400 900 2,000 3,100 Additional Capital Programme financing provision (PCP) 1,000 2,000 2,000 2,000 National Insurance Contributions Increase 420 420 420 420 Contributions (from) / to Balances -293 550 1,100 1,793 Increase in Council Tax Older Persons Discount 0 500 1,100 1,700 LABGI / Housing & Planning Delivery Grant fall out 500 500 500 500 LAA Reward Grant share to Safer Hillingdon Partnership 76 76 -216 -216 Concessionary Fares Levy 735 735 735 735 Sub-total 5,078 8,721 10,679 13,072

Decreases LAA Reward Grant Share to Primary Care Trust -335 -335 -335 -335 LAA Reward Grant Share to BAA & Uxbridge College -130 -130 -130 -130 LAA Reward Grant Share to Groundwork Trust -65 -65 -65 -65

Sub-total -530 -530 -530 -530

Net Corporate Items 4,548 8,191 10,149 12,542

Corporate 10/02/11 MTFF 2011/12 - 2014/15 Service Pressures Appendix 3

Description Net Variation from 2010/11 Budget Group 2011/12 2012/13 2013/14 2014/15 £(000s) £(000s) £(000s) £(000s)

Social Care Pressures (Adults) ASCH&H 1,250 1,250 1,250 1,250 SEN Transport demographic pressures F&BS 350 350 350 350 Waste Disposal Levy PECS 1,300 1,300 1,300 1,300 Increase in Transitional Children due to Demographic Changes ASCH&H 2,546 2,546 2,546 2,546 Homelessness Budget - Reduction in DWP Funding ASCH&H 800 800 800 800 Local Land Charges Income F&BS 720 720 720 720 Golf Courses Income PECS 303 271 248 248 Corporate Landlord PECS 100 100 100 100 Total Service Pressures 7,369 7,337 7,314 7,314

Service pressures 3 of 124 10/02/11 MTFF 2011/12 - 2014/15 Development and Risk Contingency Appendix 4

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendicies 1-10: Budget tables and fees and chargesReport 346 KB DownloadRead as text
PDF
Treasury Management StrategyAppendix 11 192 KB Download
PDF
Policy Overview Committee commentsAppendix 12 76 KB Download
PDF
The Council's Budget: General Fund Revenue Budget and Capital Programme 2011/12Report 246 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
RP
Councillor Raymond PuddifootChair, present
DS
Councillor David SimmondsVice-Chair, present
JB
Councillor Jonathan BiancoCommittee Member, present
KB
Councillor Keith BurrowsCommittee Member, present
PC
Councillor Philip Corthorne MIPDCommittee Member, present
HH
Councillor Henry HigginsCommittee Member, present
DM
Councillor Douglas MillsCommittee Member, present
SS
Councillor Scott Seaman-DigbyCommittee Member, present
JN
Jay NandhraOfficer, expected

On this subject at Hillingdon

Search all
  1. The Council's Budget: General Fund Revenue Budget and Capital Programme 2011/12This decision
  2. General Fund Revenue Budget, Housing Revenue Account and Capital Programme 2026 / 2027Approved
  3. General Fund Revenue Budget, Housing Revenue Account and Capital Programme 2025 / 2026Agreed
  4. General Fund Revenue Budget, Housing Revenue Account and Capital Programme 2024 / 2025Approved
  5. General Fund Revenue Budget, Housing Revenue Account and Capital Programme 2023 / 2024Approved
  6. General Fund Revenue Budget, Housing Revenue Account and Capital Programme 2022 / 2023Approved

More from Hillingdon CABINET

All decisions
MeetingDecisionOutcome
19 Nov 2026 Corporate Peer Review & Action PlanThat Cabinet: 1) Welcomes the findings of the LGA Corporate Peer Challenge undertaken June 2026 and notes the strengt... Approved Open
19 Nov 2026 Strategic Review of Library Services and Future Delivery ModelThat Cabinet: 1) Approves the launch of the Strategic Review of Library Services and Future Delivery Model, the devel... Approved Open
19 Nov 2026 Hayes Town Centre Regeneration FrameworkThat Cabinet agrees to adopt the as the Council’s strategic vision and delivery framework for improvements to Hayes T... Agreed Open
19 Nov 2026 Old Vinyl Factory, Hayes: Conservation Area AppraisalThat Cabinet: 1) Duly considers the public consultation responses to the draft Appraisal for The Old Vinyl Factory Co... Approved Open
19 Nov 2026 Carers Strategy UpdateThat Cabinet: 1) Note the report and agree that officers bring forward an annual progress report to Cabinet on suppor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies