Resolved – That no objections be raised subject to the considerations set out in the officers report and considerations 4, 5, 6, 11 and 14 being deleted and an informative added as follows:- Additional Informative If after 3 years it is apparent that there is a need to retain the building for a longer period, the Council requests that it be contacted so that the ongoing future arrangements can be discussed.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning & Enforcement Services
Address FORMER CONTRACTOR'S COMPOUND, SOUTH OF SWINDON ROAD HEATHROW AIRPORT
Development: Creation of 180 space, temporary staff car park (Consultation under Schedule 2, Part 18 of the Town and Country Planning (General Permitted Development) Order 1995).
LBH Ref Nos: 67622/APP/2011/405
Drawing Nos: Design and Access Statement Environmental and Geotechnical Desk Study 14645-00-GA-200-000002 VERSION 2.0 14645-00-GA-200-000003 VERSION 2.0 14645-00-GA-200-000004 VERSION 2.0 14645-XX-SE-200-000001 VERSION 2.0 14645-XX-SE-200-000002 VERSION 2.0 Existing Pedestrian Route Layout Option A Option B Heathrow's Letter dated 18/02/2011 14000-00-GA-911-000001 VERSION 3.0
Date Plans Received: 18/02/2011 Date(s) of Amendment(s): Date Application Valid: 18/02/2011 1. SUMMARY BAA has submitted this proposal for consultation under Schedule 2, Part 18 of the Town and Country Planning (General Permitted Development) Order 1995. Heathrow Airport Limited (HAL) are proposing the construction of an interim staff car park serving Terminal 4. The development includes all enabling and preparatory works, and all works necessary to deliver an operational facility. The car park will provide up to a maximum of 180 spaces. The facility will be used exclusively for staff car parking.
The interim car park will be located on Swindon Road close to the existing T4 Departures and Multi-storey Car Park 4 (MSCP4) exit ramp and will consist of a car park/road base at grade together with a single deck proprietary modular car park structure.
The site currently contains existing temporary accommodation and is required to be cleared to facilitate the main build works. There are 3 no (2no single storey and 1no two- storey portakabins on the site) used by airline and airport staff. The development includes the relocation of these teams to permanent facilities and the removal of the temporary structures.
The proposed development is considered to be visually acceptable in this busy airport location and would integrate well with the new terminal building. The level of car parking provision would fall well within the airport's staff parking space cap (based on the 2009/2010 annual parking survey) and it is not considered that the proposal would have any adverse impacts on the surrounding road network. The proposal complies with relevant London Plan and UDP policies and, accordingly, it is recommended that no objections be raised.
Central & South Planning Committee - 29th March 2011 PART 1 - MEMBERS, PUBLIC & PRESS 2. RECOMMENDATION No objection to the application, subject to the following considerations:
1 M1 Details/Samples to be Submitted No development shall take place until details and/or samples of all materials, colours and finishes to be used on all external surfaces have been submitted to and approved in writing by the Local Planning Authority.
REASON To ensure that the development presents a satisfactory appearance in accordance with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
2 T4 Temporary Building - Removal and Reinstatement The building hereby permitted shall be removed and the land restored to its former condition on or before 3 years from the date of this notice.
REASON 1. In order to comply with the terms of the application. 2. The structure, by reason of design and materials is not considered suitable for permanent retention in compliance with Policy OE1 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
3 OM1 Development in accordance with Approved Plans The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the external appearance of the development is satisfactory and complies with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.