Resolved
Resolved – That the application be approved as set out in the officer’s report, with amendments highlighted above and amendments in the Addendum sheet circulated at the meeting.
Central & South Planning Committee approved this item on Thursday 1 September 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the application be approved as set out in the officer’s report, with amendments highlighted above and amendments in the Addendum sheet circulated at the meeting.
Report of the Head of Planning & Enforcement Services
Address BRUNEL UNIVERSITY - TOWER C KINGSTON LANE HILLINGDON
Development: Creation of an area of concrete hardstanding.
LBH Ref Nos: 532/APP/2010/2391
Drawing Nos: BUTC-PP-00-DET-302-A - Ground Floor Detail BUTC-PP-00-PLN-301-A Site Block Plan BUTC-PP-00-SIT-300-A Site Location Plan
Date Plans Received: 12/10/2010 Date(s) of Amendment(s): 13/07/2011 Date Application Valid: 12/10/2010 1. SUMMARY The application seeks to install a new area of concrete hardstanding adjacent to the southern elevation of Tower C, a locally listed building within Brunel University utilised by the Universities Engineering Department.
Tower C is scheduled within the Council's Local List, however similar alterations have taken place in the past and the Council's Conservation Officer raises no objection to the installation of the proposed hardstanding adjacent to the building.
It is not considered that the proposal would have any significant impact on the openness of the Green Belt within this Major Developed Site and adequate soft landscaping would be retained in the vicinity of the application site.
The proposal is also considered acceptable in terms of highways safety.
Accordingly, the application is recommended for approval subject to conditions. 2. RECOMMENDATION APPROVAL subject to the following:
1 T8 Time Limit - full planning application 3 years The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990.
2 OM1 Development in accordance with Approved Plans The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the external appearance of the development is satisfactory and complies with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
Central & South Planning Committee - 1st September 2011 PART 1 - MEMBERS, PUBLIC & PRESS INFORMATIVES
1 I52 Compulsory Informative (1) The decision to GRANT planning permission has been taken having regard to all relevant planning legislation, regulations, guidance, circulars and Council policies, including The Human Rights Act (1998) (HRA 1998) which makes it unlawful for the Council to act incompatibly with Convention rights, specifically Article 6 (right to a fair hearing); Article 8 (right to respect for private and family life); Article 1 of the First Protocol (protection of property) and Article 14 (prohibition of discrimination).
2 I53 Compulsory Informative (2) The decision to GRANT planning permission has been taken having regard to the policies and proposals in the Hillingdon Unitary Development Plan Saved Policies (September 2007) set out below, including Supplementary Planning Guidance, and to all relevant material considerations, including the London Plan (February 2008) and national guidance. OL1 Green Belt - acceptable open land uses and restrictions on new development OL2 Green Belt -landscaping improvements OL5 Development proposals adjacent to the Green Belt BE13 New development must harmonise with the existing street scene. BE19 New development must improve or complement the character of the area. BE20 Daylight and sunlight considerations. BE21 Siting, bulk and proximity of new buildings/extensions. BE24 Requires new development to ensure adequate levels of privacy to neighbours. BE38 Retention of topographical and landscape features and provision of new planting and landscaping in development proposals. BE8 Planning applications for alteration or extension of listed buildings
3. CONSIDERATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Brunel University (Tower C) Kingston Lane, Hillingdon 532/APP/2010/2391Report | 8 pages | DownloadRead as text |
Follow Central & South Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 May 2021 | To sign and receive the minutes of the previous meeting dated 7 April 2021That the minutes of the meeting dated 7 April 2021 be approved as an accurate record subject to an amendment to indic... | Approved | Open |
| 4 May 2021 | 2 De Salis Road, Hillingdon - 38071/APP/2020/36391) That the application be refused; and 2) That delegated authority be granted to the Head of Planning to explore the... | Refused | Open |
| 4 May 2021 | 43 Sweetcroft Lane, Hillingdon - 17412/APP/2021/5991) That the application be refused; and 2) That delegated authority be granted to the Head of Planning, in consultati... | Refused | Open |
| 4 May 2021 | Heinz Wolff Building, Brunel University - 532/APP/2021/330That the application be approved. That the application be approved. | Approved | Open |
| 4 May 2021 | Harmondsworth Landfill Site, Harmondsworth Lane - 43155/APP/2020/4267That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.