Unit F, Prologis Distribution Park, Stockley Park 68137/APP/2011/2564
ApprovedPlanning1 paper
Central & South Planning Committee approved this item on Tuesday 14 February 2012. Below is the council's own wording, with the papers it was decided on.
Resolved – That the application be approved subject to the conditions and informatives set out in the officer’s report and addendum sheet circulated at the meeting, with condition 8 deleted and condition 16 amended to delete reference to a Hotel .
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning & Enforcement Services
Address UNIT F, PROLOGIS DISTRIBUTION PARK STOCKLEY ROAD WEST DRAYTON
Development: Alterations to existing elevations, boundary treatment and landscaping, installation of external plant and associated screening, alterations to access and car parking arrangements, including installation of gate house and gates in connection with use as a Class B8 data centre.
LBH Ref Nos: 68137/APP/2011/2564
Drawing Nos: 30400-PL-101 30400-PL-102 30400-PL-103 30400-PL-104 30400-PL-110A 30400-PL-111 30400-PL-112 30400-PL-113A 30400-PL-114A A05906 A05952 Acoustic Report Letter from Energy Provider Transport Statement Design and Access Statement 30400-PL-100
Date Plans Received: 19/10/2011 Date(s) of Amendment(s): Date Application Valid: 21/10/2011 1. SUMMARY This application relates to Unit F at Prologis Park, Stockley Road. The proposal relates to works which are required to facilitate the use of the building as a Data Centre.
Advice from the Council's Legal Advisor is that Appeal Decisions (considered relevant to this current scenario) show that this type of use can be considered a storage (Class B8) use, and as such no permission is required for the use itself, however alterations to the loading and parking areas, as well as security fencing are required and would need planning permission.
While there is not an objection raised to this proposal (which involves significant reductions in the size of the loading area, and a reduction in car parking spaces), the recommendation for approval is on the basis that the building (Unit F) be used as a Data Centre (which has unique characteristics which mean less deliveries are necessary and less staff/visitor parking is required). A condition is recommended to ensure this.
2. RECOMMENDATION APPROVAL subject to the following:
Central & South Planning Committee - 14th February 2012 PART 1 - MEMBERS, PUBLIC & PRESS 1 T8 Time Limit - full planning application 3 years The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990.
2 OM1 Development in accordance with Approved Plans The development shall not be carried out otherwise than in strict accordance with the plans hereby approved unless consent to any variation is first obtained in writing from the Local Planning Authority.
REASON To ensure that the external appearance of the development is satisfactory and complies with Policy BE13 and BE15 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
3 M1 Details/Samples to be Submitted No development shall take place until details and/or samples of all materials, colours and finishes to be used on all external surfaces have been submitted to and approved in writing by the Local Planning Authority.
REASON To ensure that the development presents a satisfactory appearance in accordance with Policy BE13 of the Hillingdon Unitary Development Plan Saved Policies (September 2007).
4 OM19 Construction Management Plan Prior to development commencing, the applicant shall submit a demolition and construction management plan to the Local Planning Authority for its approval. The plan shall detail:
(i) The hours during which development works will occur (please refer to informative I15 for maximum permitted working hours). (ii) A programme to demonstrate that the most valuable or potentially contaminating materials and fittings can be removed safely and intact for later re-use or processing. (iii) Traffic management and access arrangements (vehicular and pedestrian) and parking provisions for contractors during the development process (including measures to reduce the numbers of construction vehicles accessing the site during peak hours). (iv) The storage of demolition/construction materials on site.
The approved details shall be implemented and maintained throughout the duration of the demolition and construction process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.