Resolved – That delegated powers be given to the Head of Planning, Trading Standards and Environmental Protection to grant planning permission subject to the following: a) The prior receipt of a satisfactory unilateral undertaking under Section 106 of the Town and Country Planning Act 1990 (as amended) or other appropriate legislation to secure: i) A contribution towards Construction Training equal to £2,500 for every £1 million build cost or an in-kind scheme submitted to and approved by the Council. ii) A contribution towards Hospitality Training equal to £400 for every one in 3 jobs arising from the development or an in-kind scheme submitted to and approved by the Council. iii) An Air Quality contribution in the sum of £25,000 towards air quality initiatives in the area. iv) A Travel Plan to be prepared and adhered to including a £20,000 surety to ensure compliance with the travel plan for a period of ten years. v) A Project Management and Monitoring Sum equal to 5% of the total cash contributions secured from the scheme. vi) The pro-rata phasing of the financial contributions based on number of bedrooms in each phase of the proposed development. That if the application was to be approved the conditions set out in the officer’s report and on the addendum sheet circulated at the meeting be imposed.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning & Enforcement Services
Address COMPOUND D HOTEL SITE, TERMINAL 5 HEATHROW AIRPORT HOUNSLOW
Development: APPLICATION FOR A NEW PLANNING PERMISSION TO REPLACE AN EXTANT PLANNING PERMISSION COMPRISING: EXTENSION TO NORTHERN END OF THE TERMINAL 5 HOTEL (75 EXTRA BEDROOMS) AND ERECTION OF A 239-BEDROOM AIRLINE CREW HOTEL INCLUDING 77 PARKING SPACES (REFERENCE 47853/APP/2008/1333).
LBH Ref Nos: 47853/APP/2011/1642
Drawing Nos: 007(A)-100 Rev P1 007(A)-200 Rev P1 007(A)-201 Rev P1 007(A)-318 Rev P1 007(A)-400 Rev P4 007(A)-401 Rev P2 007(A)-402 Rev P2 007(A)-403 Rev P2 007(A)-501 Rev P1 007(A)-001 Rev P1 007(A)-002 Rev P1 007(A)-003 Rev P1 007(B)-400 Rev P1 007(B)-401 Rev P1 007(B)-501 Rev P1 007(B)-301 Rev P1 007(B)-311 Rev P2 007(B)-312 Rev P2 007(B)-313 Rev P2 007(B)-314 Rev P2 007(B)-315 Rev P2 007(B)-316 Rev P1 007(A)-311 Rev P6 007(A)-312 Rev P6 007(A)-313 Rev P6 007(A)-314 Rev P6 007(A)-315 Rev P6 007(A)-316 Rev P6 007(A)-317 Rev P6 001 Aerial view from the North 002 Aerial view from the South East Aerial view from the West Transport Assessment Design and Access Statement Service and Delivery Management Plan Travel Plan and Employee Travel Policy Accessibility Statement Updated Energy Statement Updated Transport Assessment
Central & South Planning Committee - 27th March 2012 PART 1 - MEMBERS, PUBLIC & PRESS Date Plans Received: 27/06/2011 Date(s) of Amendment(s): Date Application Valid: 22/07/2011
1. SUMMARY Planning permission is sought to renew an unimplemented full planning permission for the erection of a 75 bedroom extension to the Terminal 5 Sofitel Hotel adjacent to the main multi storey car park at Terminal 5 and for the construction of a 239 bedroom hotel on the adjoining site to the west which also benefits from an original extant permission for a Terminal 5 multi-deck car park.
The site for the new 239 bedroom hotel has recently been the subject of a planning permission for a new, larger 453 bedroom hotel following completion of a S106 agreement (Ref: 47853/APP/2008/3326). Accordingly, the applicant has advised that it is not intended to implement the 239 bedroom hotel proposal but only the 75 bedroom extension to the Sofitel Hotel. Whilst this report relates to the entire renewal proposals, Members should note that the 239 bedroom hotel element is unlikely to be implemented. This is because the applicant has permission to build a larger hotel on the site of the 239 bedroom hotel scheme.
The 75 bedroom extension to the existing hotel is at the northern end of the Sofitel Terminal 5 Hotel and is designed to match it. The site for the new 239 bedroom hotel is prominent and in close proximity to the entrance to the main Terminal 5 campus where it is currently screened by temporary fencing. The previous permission for this hotel was granted in 2008 with a 3 year time limit for implementation which has since been delayed by the economic downturn and lack of development finance. A unique curved design is proposed for its front facade with complementary materials to the adjacent hotel and it is considered preferable, in visual terms, to the extant Terminal 5 multi-deck car park.
The applicant wishes to have flexibility to implement the 75 bedroom extension separately from the new 239 bedroom hotel especially as it is intended to implement the more recent permission for the larger hotel. No objection is seen to this approach as both the extension and new hotel are on physically separate sites and do not need to be constructed concurrently.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.