Bishopshalt School Royal Lane Hillingdon 4277/APP/2012/2721
ApprovedPlanning1 paper
Central & South Planning Committee approved this item on Thursday 31 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved – That the Head of Planning, Environment, Sport and Green Spaces be given delegated authority to approve the application subject to referral to the Secretary of State. If the application is approved the conditions and informatives set out in the officer’s report be attached.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning & Enforcement Services
Address BISHOPSHALT SCHOOL ROYAL LANE HILLINGDON
Development: Replacement of the existing felt roof to the canteen and associated repair to timber skylights and windows (application for listed building consent).
LBH Ref Nos: 4277/APP/2012/2721
Drawing Nos: K12_0377 153 Rev. A K12_0377 154 Rev. A K12_0377 001 K12_0377 155 Rev. A K12_0377 100 Rev. A Design and Access Statement (K12/0377/0004 SCN/G4) Paraglaze Rooflights & Upstands Brochure K12_0377 150 (Existing roof plan) K12_0377 151 (Existing section) K12_0377 152 (Existing section) Specification Document Project: 10968
Date Plans Received: 02/11/2012 Date(s) of Amendment(s): 03/01/2013 Date Application Valid: 02/11/2012 05/11/2012
1. CONSIDERATIONS
1.1Site and Locality Bishopshalt School is located on the east side of Royal Lane and comprises a variety of buildings. The main school building is an attractive Grade II Listed Victorian building, which has been extended over the years in a variety of styles.
The school buildings are surrounded by extensive grounds, beyond which are residential properties to the east and west, Harlington Road Depot to the south, and Coney Green, an area of public open space and playing fields to the north. The school site falls within the Hillingdon Village Conservation Area and the Green Belt.
The application site comprises the flat roof over the canteen, located to the northern wing of the school. The existing canteen roof structure is covered with 30mm asphalt that is currently failing and requires refurbishment.
1.2Proposed Scheme The development proposals comprise the replacement of the existing 30mm asphalt roof with an elastomeric membrane roofing system in dark grey to match existing.
As part of the waterproofing works, all roof-mounted plant and equipment is to be removed and set aside for re-positioning on completion. No new plant is proposed as part of the application. The metal walkway and supports will be removed to allow waterproofing and will be re-fixed or replaced as necessary following the works.
Central & South Planning Committee - 31st January 2013 PART 1 - MEMBERS, PUBLIC & PRESS Downpipes will be removed to facilitate the re-roofing work and set aside for re-fixing on completion. Redundant vent pipes and other redundant penetrations to the roof will be removed and the holes in the deck made good.
The existing timber frame skylights are to be refurbished.
1.3Relevant Planning History Comment on Planning History
2. Advertisement and Site Notice
2.1Advertisement Expiry Date:- Not applicable
2.2Site Notice Expiry Date:- Not applicable
3. Comments on Public Consultations EXTERNAL
The application was advertised as a development affecting the Hillingdon Village Conservation Area.
ENGLISH HERITAGE
You are authorised to detemine the application for listed building consent as you see fit. In doing so, English Heritage would stress that it is not expressing any views on the merits of the proposals, which are subject to this application.
INTERNAL
URBAN DESIGN AND CONSERVATION OFFICER
PROPOSAL: Replacement of the existing felt roof to the canteen and associated repair timber skylights and windows (application for listed building consent).
BACKGROUND: The school, once a private house, dates from 1858 and is Tudor in style, comprising 5 bays with a later 3-bay extension to the south. The building is grade II listed and is within the Hillingdon Village Conservation Area. The proposed changes are to the adjoining section of the school, not included in the listing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.