Resolved – That the Head of Planning be given delegated authority to approve the application following clarification of the description of the development. If the application was approved the conditions and informatives set out in the officer’s report and addendum sheet circulated at the meeting and condition 6 being amended and an additional informative added, be attached. Amend Condition 6 to read Prior to the commencement of development a traffic management plan shall be submitted to and approved in writing by the Local Planning Authority. This shall provide details in relation to access (vehicular and pedestrian) and the parking provision for school and contracting staff, the delivery of materials, measures to protect children, and the storage of materials on site during construction, details of vehicle booking systems, the use of re-timed or consolidated construction vehicle trips, protection of vulnerable road users and use of operators committed to best practice as demonstrated by membership of TfL's Freight Operator Recognition Scheme (FORS) or similar. REASON To ensure that the construction does not have an unacceptable impact on residential amenity and in the interests of highway and pedestrian safety in accordance with policies AM2 and AM7 of the Hillingdon Local Plan: ... view the full minutes text for item 70.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report of the Head of Planning & Enforcement Services
Address PINKWELL PRIMARY SCHOOL PINKWELL LANE HAYES
Development: Expansion of school to include standalone classroom block and extended nursery, dining room, staff room, reception, library and classrooms with associated car parking and landscaping.
LBH Ref Nos: 11242/APP/2012/3116
Drawing Nos: Statement of Community Involvement, dated November 2012 Design & Access Statement, dated December 2012 Planning Statement, dated December 2012 External below Ground Drainage Technical Note, produced by WSP Baseline Air Quality Assessment, dated August 2011 8222-A-105 Rev. J 8222-A-268 Rev. D PNK-011 8222-E-002 Rev. A 8222-A-242 Rev. D 8222-A-243 Rev. D 8222-A-244 Rev. D PNK-012 PNK-013 8222-A-101 Rev. F 8222-A-245 Rev. G 8222-A-108 Rev. E 8222-A-246 Rev. E 8222-A-247 Rev. F 8222-A-248 Rev. E 8222-A-241 Rev. D 8222-A-251 Rev. D 8222-A-252 Rev. D 8222-A-253 Rev. D 8222-A-254 Rev. E 8222-A-255 Rev. E 8222-A-258 Rev. D 8222-A-261 Rev. D 8222-A-262 Rev. E 8222-A-263 Rev. E 380.001 Rev. A 8222-A-101 Rev. F 8222-A-102 Rev. D 0278-D-02 Rev. C 0278-D-03 Rev. B 0278-D-04 Rev. A 040 Rev. A 041 Rev. A 042 Rev. A 043 Rev. A Transport Assessment Report No. 8222-E-002 Rev. A, dated November 2012 Validation and Calibration of Traffic Models Report No. 2915/022/T24
Central & South Planning Committee - 5th March 2013 PART 1 - MEMBERS, PUBLIC & PRESS Flood Risk Assessment 2915/015/RP25, dated August 2011 Thames Water Asset Location Search Energy Statement, dated February 2013 8222-A-107 Rev. G 8222-A-240 Rev. F 8222-A-265 Rev. F 8222-A-271 Rev. D
Date Plans Received: 13/12/2012 Date(s) of Amendment(s): 07/02/2013 Date Application Valid: 18/12/2012 15/02/2013 05/02/2013 18/12/2012 1. SUMMARY This application seeks full planning permission for the expansion of the existing school to provide for an additional form of entry with construction of a new standalone 2 storey classroom block to the rear of the main existing school buildings, a new 2 storey extension to an existing 2 storey block, an infill extension to provide a library facility, the creation of a 2nd nursery space with the re-location of the existing specialist resource provision to the new classroom block, and the general internal refurbishment of the school building involving a minor extension to the school entrance/reception area. The scheme would also involve the removal of a set of 3 mobile classroom blocks from the school site.
The Education Act 1996 states that Local Authorities have a duty to educate children within their administrative area. The Hillingdon Primary Capital Schools Programme is part of the Council's legal requirement to meet the educational needs of the borough. In recent years the borough has seen a rise in birth rates up to 2008 and the trend has continued through 2009 and 2010. This growth in the birth rate, combined with net in- migration and new large scale housing developments in the borough has meant that there is now a significant need for additional primary school classrooms across the borough.
Accordingly, the Council wishes to expand Pinkwell Primary to provide additional places for the children of the borough. The new school will provide additional capacity for 252 pupils including 60 nursery school pupils over two sessions.
The proposal fully complies with the aims of the National Planning Policy Framework (NPPF), London Plan Policy 3.18 and R10, which seek to encourage the provision of new and/or enhanced educational facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.