Packet Boat House, Packet Boat Lane, Cowley 20545/APP/2012/2848

Agreed Planning 1 paper

Central & South Planning Committee agreed this item on Tuesday 23 April 2013. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

Resolved A. That the Council enters into an agreement with the applicant under Section 106of the Town and Country Planning Act 1990 (as amended): i. Affordable Housing if the applicant does not substantially commence development within 18 months from the grant of planning permission then a review mechanism will be implemented to ensure that if on-site affordable housing or a contribution towards off site affordable housing is viable it is secured. ii. An Education contribution in the sum of £57,639 iii. A Health Facilities contribution in the sum of £14,560.22 iv. A Communities Facilities contribution in the sum of £15,000 v. A Libraries contribution in the sum of £1,545.60 vi. A Construction Training scheme delivered during the construction phase of the development or a financial contribution equal to £2,500 for every £1 million build cost in the sum of £30,866.72). vii. A Project Management and Monitoring fee equal to 5% of the total cash contributions. viii. Parking allocation plan. B) That in respect of the application for planning permission, the applicant meets the Council’s reasonable costs in preparation of the Section 106 and 278 Agreements and any abortive work as a result of the agreement not being completed. C) That officers be authorised to negotiate and agree the detailed terms of the proposed agreement and conditions of approval. D) If the Legal Agreement/s have not been finalised before the 07-05-13, delegated authority be given to the Head of Planning, Sport and Green Spaces to refuse planning permission for the following reason: ’The applicant has failed to provide contributions towards the improvement of services and facilities as a consequence of demands created by the proposed development (in respect of education, health facilities, community facilities, public realm, library improvements and construction training). The proposal therefore conflicts with Policy AM2, AM7 and R17 of the adopted Local Plan and the Council’s Planning Obligations SPG.’ E) That subject to the above, the application be deferred for determination by the Head of Planning, Sport and Green Spaces under delegated powers, subject to the completion of the legal agreement under Section 106 of the Town and Country Planning Act 1990 and other appropriate powers with the applicant. F) That if the application is approved, the conditions and informatives in the officer’s report be imposed, the changes in the addendum circulated at the meeting and subject to any changes negotiated by the Head of Planning, Sport and Green Spaces prior to issuing the decision.
Word for word from the decision Hillingdon published for this meeting. Source: modgov.hillingdon.gov.uk

Follow this further

Built from Hillingdon's papers

What the report saysPro

Report to Central & South Planning Committee

Report of the Head of Planning, Sport and Green Spaces

Address PACKET BOAT HOUSE PACKET BOAT LANE COWLEY UXBRIDGE

Development: Alterations, additions and conversion of existing building to create 41 flats with associated car parking, refuse and recycling facilities, amenity space and landscaping.

LBH Ref Nos: 20545/APP/2012/2848

Drawing Nos: 1576-A-LC 1576-A-312 1576-A-311 1576-A-310 1576-A-309 1576-A-308 Rev D 1576-A-306 Rev I 1576-A-303 Rev I 1576-A-302 Rev I 1576-A-301 Rev H 1576-A-300 Rev H 1576-A-307 REV E 1576-A-305 REV G 1576-A-304 REV G 1576-A-06 1576-A-05 1576-A-04 1576-A-03 1576-A-02 1576-A-01 REV A Design & Access Statement Energy Statement Acoustics Report Phase II Environmental Report Flood Risk Assessment DWG05

Date Plans Received: 15/11/2012 Date(s) of Amendment(s): 14/02/2013 Date Application Valid: 05/02/2013 16/11/2012 10/04/2013 DEFERRED ON 13th March 2013 FOR SITE VISIT .

The application was heard at the 13th March 2013 Central & South Planning Committee. Members deferred the application in order to enable them to conduct a site visit, which took place on April 16th. Members also raised the following concerns:

i) Clarification over the commercial space forming part of the earlier appeal scheme The appeal scheme provided commercial floorspace on part of the ground, first and second floors. The whole eastern section of the floor plate of the ground and first floors facing the access road between Packet Boat House and the adjacent unit of the Tomo Indrtsial Estate as well a smaller section of the second floor were all set aside for commercial use. The current scheme proposed an entirely residential use.

Central & South Planning Committee - 23rd April 2013 PART 1 - MEMBERS, PUBLIC & PRESS The Hillingdon Design & Accessibility Statement 'Residential Extensions' (HDAS) states that 'Where a two or more storey building abuts a property or its garden, adequate distance should be maintained to overcome possible overdomination'. It should be noted that there is a significant difference in levels between Packet Boat House and the adjoining industrial unit. The application site is approximately 1.8m higher than the adjacent unit. With the industrial unit being 2 stories in height from ground level, the 1.8m ground level with the application site means that in the adjoining industrial building is only, at worst, 1.5 stories in height when measured from the ground level of Packet Boat House. Given this, the proposed scheme would not contravene the 15m standard set out within HDAS.

It is also noted that of the 4 units within the ground floor on the eastern elevation, 2 units have dual aspect and would benefit from outlook and light arising from the side elevations. The two units which are not dual aspect are south facing which would maximise the amount of light entering the units and as mentioned above their relationship with the neighbouring building does not contravene the Council's adopted guidance. Overall, it is considered that the scheme complies with the HDAS and the accommodation within these units would be of an acceptable standard with regard to daylight and outlook.

In relation to noise the Council's Environmental Protection Unit have reviewed the scheme in detail and consider that all of the units within the scheme, including those facing the access road, would benefit from an appropriate environment in terms of noise subject to appropriate glazing specifications, which are secured by condition.

Officers have assessed the proposals with the aid of Specialist Officers who have unanimously agree that, subject to appropriate conditions, the proposals conform with all residential policies and standards including the levels of daylight and sunlight entering each unit, outlook and noise.

ii) Clarification over access arrangements

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Packet Boat House, Packet Boat Lane, Cowley 20545/APP/2012/2848Report 4.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JH
Councillor John HensleyChair, present
WB
Councillor Wayne BridgesCommittee Member, present
JD
Councillor Janet DuncanCommittee Member, present
NF
Councillor Neil FyfeCommittee Member, present
DG
Councillor Dominic GilhamCommittee Member, present
BS
Councillor Brian SteadCommittee Member, present
BE
Councillor Beulah EastCommittee Member, present as substitute
DP
Councillor David PayneCommittee Member, present as substitute
MK
Councillor Mo KhursheedCommittee Member, apologies, sent representative
JC
Councillor Judith CooperVice-Chair, apologies, sent representative
NW
Nadia WilliamsSecretary, in attendance

On this subject at Hillingdon

Search all
  1. Packet Boat House, Packet Boat Lane, Cowley 20545/APP/2012/2848This decision
  2. Paddington Packet Boat Public House - 1058/APP/2021/3423Approved
  3. Packet Boat Marina - 53216/APP/2020/3138Approved
  4. Little Britain Lake, Packet Boat Lane, Cowley - 52368/APP/2017/1844Refused
  5. Packet Boat Marina, Packet Boat Lane, Cowley - 53216/APP/2018/4179Approved
  6. Paddington Packet Boat Public House, Cowley - 1058/APP/2018/4486Decided

More from Hillingdon Central & South Planning Committee

All decisions
MeetingDecisionOutcome
4 May 2021 To sign and receive the minutes of the previous meeting dated 7 April 2021That the minutes of the meeting dated 7 April 2021 be approved as an accurate record subject to an amendment to indic... Approved Open
4 May 2021 2 De Salis Road, Hillingdon - 38071/APP/2020/36391) That the application be refused; and 2) That delegated authority be granted to the Head of Planning to explore the... Refused Open
4 May 2021 43 Sweetcroft Lane, Hillingdon - 17412/APP/2021/5991) That the application be refused; and 2) That delegated authority be granted to the Head of Planning, in consultati... Refused Open
4 May 2021 Heinz Wolff Building, Brunel University - 532/APP/2021/330That the application be approved. That the application be approved. Approved Open
4 May 2021 Harmondsworth Landfill Site, Harmondsworth Lane - 43155/APP/2020/4267That the application be approved. 1) That delegated authority be granted to the Head of Planning to reword Point 2 on... Approved Open