Resolved
RESOLVED - That the application be approved.
Major Applications Planning Committee approved this item on Tuesday 20 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the application be approved.
Report of the Head of Planning, Sport and Green Spaces
Address 1 THE SQUARE FURZEGROUND WAY STOCKLEY PARK
Development: Erection of a side extension and roof extension including recladding of existing building, provision of new decked car parking including hard and soft landscaping and ancillary works. LBH Ref Nos: 37506/APP/2017/4534
Drawing Nos: Noise Impact Assessment [Scotch Partners, November 2017] 20.201 P1 20.202 P1 20.203 P1 20.204 P1 20.251 P1 20.252 P1 20.271 P1 20.272 P1 20.273 P1 20.274 P1 30.601 P1 30.602 P1 30.603 P1 30.604 P1 Energy Statement [Scotch Partners, December 2017] Transport Assessment [Canerpo Associates, December 2017] Air Quality Assessment [Wardell Armstrong, December 2017] 10.251 P1 10.202 P1 10.203 P1 10.252 P1 10.271 P1 10.272 P1 10.273 P1 10.274 P1 Aroboricultural Impact Assessment [Broad Oak Tree Consultants, December 2017] Design and Access Statement [December 2017] Planning Statement [Smith Jenkins, December 2017] 10.201 P1 TM303LS01 TM303L01 Tree Removal Plan 00.101 P1 Covering Letter [Smith Jenkins, 15 December 2017]
Date Plans Received: 15/12/2017 Date(s) of Amendment(s): Date Application Valid: 19/12/2017
Major Applications Planning Committee - 20th February 2018 PART 1 - MEMBERS, PUBLIC & PRESS 1. SUMMARY This application relates to an existing office building within Stockley Park. The application proposes a comprehensive refurbishment, recladding and a single storey and side extensions to provide 2,360 sqm GIA of office floorspace. Also proposed is a decked car park and associated hard and soft landscaping.
The proposal is considered to provide a high quality design that is appropriate and reflects the character of Stockley Park. The application is deemed to accord with the relevant policies and guidance contained within the Hillingdon Local Plan (November 2012) and the London Plan (March 2016) and subject to the attachment of appropriate conditions is recommended for approval. 2. RECOMMENDATION 1.That delegated powers be given to the Head of Planning and Enforcement to grant planning permission subject to:
A) Entering into an agreement with the applicant under Section 106 of the Town and Country Planning Act 1990 (as amended) and/or S278 of the Highways Act 1980 (as amended) and/or other appropriate legislation to secure:
Non-monetary contributions:
i) A full and formal Travel Plan with associated £20,000.00 bond to include a Sustainable Transport Measures is required to be submitted and agreed in writing by the LPA before occupation of the development. Thereafter, the Travel Plan is required to be reviewed annually to monitor and if required, update and/or amend the document to the satisfaction of the LPA, in order that its aims and objectives are achieved.
ii) Construction Training: either a contribution equal to the formula (£2,500.00 for every £1m build cost + Coordinator Costs £9,600.00 or an in kind scheme) or an in- kind training scheme equal to the financial contribution delivered during the construction period of the development with the preference being for an in-kind scheme to be delivered.
Monetary contributions:
iii) Highways Contribution £90,000 to local highway improvements
iv) Project Management & Monitoring Fee: a contribution equal to 5% of the total cash contributions secured from the scheme to enable the management and monitoring of the resulting agreement, is sought.
B)That Officers be authorised to negotiate and agree the detailed terms of the proposed agreement and conditions of approval.
C)If the Legal Agreements have not been finalised by 20 March 2018 (or such other time frame as may be agreed by the Head of Planning and Enforcement), delegated authority be given to the Head of Planning and Enforcement to refuse planning permission for the following reason:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1 The Square, Furzerground Way: 37506/APP/2017/4534Report | 147 KB | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.