Resolved
RESOLVED - That the application be approved.
Major Applications Planning Committee approved this item on Tuesday 20 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the application be approved.
Report of the Head of Planning, Sport and Green Spaces
Address ACOL CRESCENT EARLY LEARNING CENTRE ACOL CRESCENT RUISLIP Development: Demolition of all existing buildings and replacement with new part two, part three-storey building accommodating 33 (14 x 1 bedroom and 19 x 2 bedroom) social housing flats with associated access, parking and landscaping LBH Ref Nos: 67607/APP/2017/4627
Drawing Nos: APL015 (Fully Wheelchair Adoptable Flats) APL016 (Fully Wheelchair Adoptable Flats) APL017 (Fully Wheelchair Adoptable Flats) APL001 Rev.C (Site Location Plan) Tree survey and Arboricultural Impact Assessment, prepared by Simon Pryce Arboriculture dated 17/01/17 APL007 Rev.B (Front Elevation) APL010 Rev.B (Sections A-A & B-B) APL011 Rev.B (Section Through Site) APL012 Rev.C (Visuals) APL013 Rev.A (Site Elevations as Existing) APL002 Rev.A (Topographical Survey) 16/100 Rev.A (Tree Survey and Tree Protection Plan) Planning Daylight, Sunlight & Overshadowing Report, prepared by BLDA Consultancy dated 08/12/17 Acoustic Design Statement, prepared by Energist UK dated 22/11/17 Archaeological Desk Based Assessment, prepared by CgMs dated November 2017 Extended Phase 1 Habitat Survey and Bat Building Inspection, prepared by SES dated 07/11/16 Transport Statement, prepared by PFA dated 20/12/17 Planning Statement, prepared by Pegasus Group dated December 2017 Energy Strategy Rev.B, prepared by Energist London dated 15/12/17 Flood Risk Assessment & Drainage Statement Rev.B, prepared by Infrastruct CS Ltd dated 29/01/17 Air Quality Assessment, prepared by Aether dated 12/01/18 Design & Access Statement Rev.A, prepared by Hunters dated 07/02/18 APL009 Rev.C (Side Elevations) APL008 Rev.D (Rear Elevation) APL006 Rev.E (Second Floor Plan and Roof Plan) APL005 Rev.D (Ground Floor Plan and First Floor Plan) APL004 Rev.E (Landscape Plan) APL003 Rev.G (Site Plan)
Date Plans Received: 21/12/2017 Date(s) of Amendment(s): 19/01/2018 Date Application Valid: 22/12/2017 07/02/2018 21/12/2017 1. SUMMARY This application seeks full planning permission for the redevelopment of the former South
Major Applications Planning Committee - 20th February 2018 PART 1 - MEMBERS, PUBLIC & PRESS Ruislip Early Years Centre in Acol Crescent, South Ruislip, to provide a new part two, part three-storey building accommodating 33 social housing flats with associated access, parking and landscaping.
Planning permission (ref: 65847/APP/2014/427) was previously granted for the redevelopment of the site to provide 28 social and supported housing units in 2014. That application expired on 06/06/17. Following expiry of that consent prior approval (ref: 67607/APP/2017/2529) for demolition of the existing buildings on the site was sought. It was determined that prior approval for demolition was not required on 21/11/17. At the time of writing demolition works are underway.
There has been no significant change in policy since 2014 which deem residential use of the site no longer acceptable and, accordingly, no objection is raised to the principle of the development.
The scheme would achieve an appropriate appearance within the street scene, provide an appropriate landscape setting, appropriate living conditions for future occupiers and have no unacceptable impacts on the amenity of nearby residential occupiers. Furthermore, notwithstanding objections on the matter from local residents, it is not considered that it would lead to such a significant increase in traffic or parking demand that refusal could be justified.
The proposal is considered to comply with relevant local, London Plan and national planning policies and guidance and, accordingly, subject to conditions and planning obligations, approval is recommended. 2. RECOMMENDATION That delegated powers be given to the Head of Planning and Enforcement to grant planning permission, subject to the following:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ACOL Crescent Early Learning Centre: 67607/APP/2017/4627Report | 211 KB | DownloadRead as text |
Follow Major Applications Planning Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Oct 2023 | To sign and receive the minutes of the previous meetingThat the item be deferred to the meeting of the Hillingdon Planning Committee on 01 November 2023. | Deferred | Open |
| 11 Oct 2023 | West Drayton Leisure Centre - 75127/APP/2023/1646That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 11 Oct 2023 | The Barn Hotel, Ruislip - 7969/APP/2023/1833That the application be approved as per officers’ recommendation. That the application be approved as per officers’ r... | Approved | Open |
| 14 Sep 2023 | To sign and receive the minutes of the previous meetingThat the minutes of the meeting dated 26 July 2023 be agreed as an accurate record. | Agreed | Open |
| 14 Sep 2023 | Pets at Home, Elystan Business Centre, Springfield Road.That the application be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.