Oxeney Cottage Thorney Mill Road, West Drayton - 40485/APP/2019/1922
ApprovedPlanning1 paper
Central & South Planning Committee approved this item on Tuesday 3 September 2019. Below is the council's own wording, with the papers it was decided on.
That the application be approved. That the application be approved and the Head of Planning and Enforcement be delegated authority to formulate wording for conditions in relation to parking allocation, construction logistics plan and acoustic fencing.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Report to Central & South Planning Committee, 18 pages
Report of the Head of Planning, Transportation and Regeneration
Address OXENEY COTTAGE THORNEY MILL ROAD WEST DRAYTON
Development: Erection of a detached, two storey building to create 4 x 1-bed self contained flats with associated parking and installation of new crossover to front involving demolition of existing buildings LBH Ref Nos: 40485/APP/2019/1922
Date Plans Received: 07/06/2019 Date(s) of Amendment(s): 07/06/2019 Date Application Valid: 12/06/2019 1. SUMMARY The application seeks planning permission for the erection of a detached, two storey building to create 4 x 1-bed self contained flats with associated parking and installation of new crossover to front involving demolition of existing buildings.
The proposal, although it does represent a disproportionate change to the size of the original building on site, is not considered to have materially altered the built-up appearance of the site or the openness of the Green Belt and on balance, it is considered to be acceptable on Green Belt grounds. Also, the proposal would not be detrimental to the residential amenities of adjoining residential occupiers. The scheme would provide suitable residential accommodation to its occupiers and adequate off-street parking is provided.
The application is recommended for approval. 2. RECOMMENDATION APPROVAL subject to the following:
1 RES3 Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
REASON To comply with Section 91 of the Town and Country Planning Act 1990 2 RES4 Accordance with Approved Plans The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers SC/OXNEY/2019/LANDSCAPE and AC/OXNEY//2017/COMBINED2 and shall thereafter be retained/maintained for as long as the development remains in existence.
REASON To ensure the development complies with the provisions of the Hillingdon Local Plan: Part Two Saved UDP Policies (November 2012) and the London Plan (2016).
Central & South Planning Committee - PART 1 - MEMBERS, PUBLIC & PRESS 3 RES7 Materials (Submission) The works on the superstructure shall not commence until details of all materials and external surfaces have been submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be constructed in accordance with the approved details and be retained as such.
Details should include information relating to make, product/type, colour and photographs/images.
REASON To ensure that the development presents a satisfactory appearance in accordance with Policy BE13 Hillingdon Local Plan: Part Two Saved UDP Policies (November 2012) 4 RES9 Landscaping (car parking & refuse/cycle storage) That the works on the superstructure shall not commence until a landscape scheme has been submitted to and approved in writing by the Local Planning Authority. The scheme shall include: -
1. Details of Soft Landscaping 1.a Planting plans (at not less than a scale of 1:100), 1.b Written specification of planting and cultivation works to be undertaken, 1.c Schedule of plants giving species, plant sizes, and proposed numbers/densities where appropriate
2. Details of Hard Landscaping 2.a Refuse Storage 2.b Cycle Storage 2.c Means of enclosure/boundary treatments 2.d Car Parking Layouts (including demonstration that 5% of all parking spaces are served by electrical charging points) 2.e Hard Surfacing Materials
3. Details of Landscape Maintenance 3.a Landscape Maintenance Schedule for a minimum period of 5 years. 3.b Proposals for the replacement of any tree, shrub, or area of surfing/seeding within the landscaping scheme which dies or in the opinion of the Local Planning Authority becomes seriously damaged or diseased.
4. Schedule for Implementation
Thereafter the development shall be carried out and maintained in full accordance with the approved details.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.