Central & South Planning Committee approved this item on Wednesday 8 January 2020. Below is the council's own wording, with the papers it was decided on.
That the application be approved, subject to delegated authority to the Head of Planning, Transportation and Regeneration for an additional condition. That the application be approved, subject to: 1. An amendment to Condition 1 to change the wording from “5 years” to “10 years”; and, 2. Delegated authority to the Head of Planning to ensure that there is ramped access to all fire exits.
Word for word from the decision Hillingdon published for this meeting.Source: modgov.hillingdon.gov.uk
Development: Erection of a temporary single storey prefabricated system building, together with a link to the AMU building, with a total floor area of 743 sq.m, to provide for a 20 bed space decant and winter overspill ward, including 4 parking spaces; demolition of Building 17 and the creation of 30 replacement staff car parking spaces; reconfiguration of the parking area to the east of the Womens' Services Building resulting in a net provision of 11 replacement visitor parking spaces LBH Ref Nos: 4058/APP/2019/3286
Date Plans Received: 08/10/2019 Date(s) of Amendment(s): 12/12/2019 Date Application Valid: 08/10/2019 11/12/2019 08/10/2019 09/10/2019 1. SUMMARY This application seeks planning permission for the construction of a single storey flat roofed prefabricated system building, to accommodate a 750 sq m, 20 bed ward. The ward accommodation will address demand for additional ward accommodation during the winter months, whilst during the summer months, it will be used as a decant ward to accommodate the refurbishment and maintenance of other wards. The Trust will lease the building initially for 5 years with an option to purchase for a longer term.
The proposed building will be located centrally within the hospital site and will result in the loss of 45 spaces on an existing car park, which will be reprovided in three main locations within the hospital site.
An existing S106 Agreement covering the hospital site states that no planning application that involves additional internal floorspace of greater than 250 sqm being created shall be submitted prior to the Council's written approval of an over-arching masterplan
Central & South Planning Committee - 8th January 2020 PART 1 - MEMBERS, PUBLIC & PRESS demonstrating how the Hospital as a whole will be redeveloped in a phased, coherent, sustainable strategic and comprehensive manner (the Strategic Master Plan).
The Trust advises that some preliminary work on the Strategic Masterplan has been started. However this work has not been completed at the time of the application and the Trust is under pressure to have the overspill and decant ward available for use this winter. The Trust has therefore requested that the requirements of the S106 agreement do not apply to the proposed ward. The nature of the building is that it is a pre fabricated structure not intended to be a permanent feature of the site, so placing it in this location does not prejudice the outcome of a future masterplan. If future large scale buildings ie larger than 250 sq meters, are proposed on the site, then the Trust accepts that the obligations of the S106 Agreement will still apply.
In light of the above, a deed of variation to the 2013 legal agreement (the Principal Agreement) is recommended, which would allow the current scheme to proceed in this instance, but would preserve the restrictions set out in the 2013 Agreement in all other respects.
The scheme would not have an adverse impact upon neighbouring residential properties from an amenity perspective or impact adversely on surrounding streets in terms of visual amenity, traffic congestion or pressure upon on-site car parking.
Officers consider that the benefits, on grounds of clinical and locational need, when weighed against the drawbacks of the proposed development are significant and therefore, this would outweigh the ad hoc development of the hospital site and loss of soft landscaping arising from the proposed development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.