Resolved
That the Committee noted the report.
Property, Highways and Transport Select Committee noted this item on Thursday 8 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee noted the report.
Civic Centre Works - Project Update Committee name Property, Highways and Transport Select Committee
Officer reporting Michael Naughton
Papers with report None
Ward All
HEADLINES Civic Centre Works Update regarding completed work, current work, proposed works and issues / decisions that need to be confirmed to take the project forward.
RECOMMENDATIONS That the Committee note the contents of the report.
SUPPORTING INFORMATION ENABLING WORKS
Civic Centre 2 East and 1 North quadrants – The stripping out of asbestos and ceilings have been completed and the areas handed over to Capital Programme Works Service.
Various complicated office moves in 2 South, 4 East and 3 North have been completed to facilitate the asbestos removal and ceiling strip out of each quadrant, in readiness for handing over to the Capital Programme Works Service for subsequent fitting-out. All were completed on schedule by the Facilities team.
Middlesex Suite The external scaffolding and temporary roof have now been erected. The roof repair and recovering contract has commenced and the replacement Crittall windows are due to be installed. The roof structure is to be reinforced for installation of the air source heat pumps and replacement PV panels.
The new replica Crittall windows are on order following receipt of Listed Building Consent The asbestos removal within the CAB Office and ex-Apetito kitchens commenced in November 2023.
DE-CARBONISATION
The installation of heat pumps, installation of heating system controls, installation of PV Panels,
Classification: Part 1 - Public Property, Highways and Transport Select Committee – 8 February 2024 building fabric insulation, loft insulation, secondary glazing and lighting is ongoing. These works funded by Salix (Government Grant) must be claimed by 31/03/2024.
The first 10 heat pumps (by Therma Nova) manufactured in Denmark were delivered on 9th January 2024; 14 more are to be delivered on 19th February 2024 and the final delivery 11th March 2024 at Civic Centre. All works for Decarbonisation should complete by October 2024. Basement car park and LED lighting improvements are also being progressed.
INTERNAL FIT-OUT TO CIVIC OFFICES AND MIDDLESEX SUITE
Construction Programme currently runs from October 2023 to July 2024. The appointed contractor Greyline commenced in October, with capital release approved for works to 2 East, 1 North, Middlesex Suite and Corporate Reception. Due to a new location for the Housing Needs Reception and other factors, an updated contract programme is being sequenced.
Civic Centre 2 East Office Areas – Structural works to create the new spaces and meeting rooms are complete and there is continued design of mechanical and electrical, fire, and data requirements. 1 North – The new staff breakout area has been stripped out, and new water, drainage and electrical works are progressing for the fit-out of the kitchen and vending machines. 1 North – The CCTV room now has 60-minute fire and acoustic rated walls installed to provide a safe and secure environment for the Borough’s CCTV command centre. Ceilings are being replaced, to be followed by installation of blue lighting to reduce glare. 1 North - Housing Reception – This area will now be co-locating with CAB Office on Level 1 of the Middlesex Suite.
Further quadrants of the Civic Centre are being prepared for decanting and asbestos strip out. A Capital Release paper is ready for approval to enable the Main Contractor to commence fit-out in these next quadrants. This will be subject to external clients reviewing the Civic Centre for rental opportunities.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Civic Centre Works: Project UpdateReport | 192 KB | DownloadRead as text |
Follow Property, Highways and Transport Select Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2024 | To receive the minutes of the previous meetingThat the minutes from the meeting on 6 March 2024 be confirmed as an accurate record. | Decided | Open |
| 9 Apr 2024 | Review Into The Council's Road Safety Initiatives And Activities Around The Borough's SchoolsThat delegated authority be given to Democratic Services to finalise the recommendations with the Chair and Labour Le... | Decided | Open |
| 9 Apr 2024 | Cabinet Forward PlanThat the update and the Forward Plan be noted. | Noted | Open |
| 9 Apr 2024 | Work ProgrammeThat the work programme be noted. | Noted | Open |
| 6 Mar 2024 | To receive the minutes of the previous meetingThat the minutes from the meeting on 8 February 2024 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.