Resolved
That the contents of the report be noted.
Property, Highways and Transport Select Committee noted this item on Thursday 8 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the contents of the report be noted.
RESTORATION PROJECT AT CRANFORD PARK: AN UPDATE Committee name Property, Highways and Transport Select Committee
Officer reporting Michael Naughton, Place Directorate
Papers with report None
Ward N/A
HEADLINES This Report provides an update on the Restoration Project at Cranford Park.
RECOMMENDATIONS That the Committee note the contents of the report.
SUPPORTING INFORMATION 1.Introduction
This project consists of the restoration of the historic buildings, structures and landscapes of Cranford Park, the building of a new café. the provision of additional visitor facilities including a playground and interpretation, the introduction of volunteering and events programmes managed by on-site staff and the upgrading of the park for educational, recreational and community purposes.
It has been largely externally funded, the largest funder being the National Heritage Lottery Fund/National Communities Lottery Fund. The first round Bid to the Lottery was successful in December 2017 and the second, very detailed, Bid in July 2020. Construction works took place on site from April 2022 to July 2023. The project budget, for capital works and activity plan, was £4,492,906.00.
2. Update on the New Build and Restoration Works
Practical completion took place on 24th July 2023. By this time the repairs had been carried out to the cellars and stables, each with heating, lighting and security systems, the new café and associated hard landscaping had been completed, the Information Centre upgraded, the playground built, the car park extended, the driveway put in, the courtyard upgraded, the passing place near the entrance constructed, the cable bridge put in place over the River Crane and St. Dunstan’s Subway upgraded. Over recent months, minor snagging has taken place.
However it was considered hat the Cellars were too damp to instal the main staircase and three
Classification: Part 1 - Public Property, Highways and Transport Select Committee – Thursday 8 February 2024 fire doors, which are all largely of timber. Investigation works are underway into improving waterproofing and dealing with condensation problems.
3. Update on Interpretation
The entrance signs have been installed, the new notice boards are in place and the new maps and interpretation have replaced the previous ones, which were by now very out of date.
The projector has been installed in the cellar, and this now shows a 10 minute film about the history of Cranford Park and Cranford House. A motion activated audio play of an old groom talking to a stable lad (set in 1828), has been installed in the stables, together with horse harness, hay and a dressing up box for visiting school children.
The ten posts for the audio trail have been installed around the park and the app (audio and visual) is ready to download.
Some minor signage is still outstanding, as are the plaques acknowledging the funders. This will be completed shortly.
4. Update on Electricity Installation
The park requires a 500 kva electrical transformer to provide enough power for the café kitchen, electric charging points and the other energy requirements of the offices on the site.
It was agreed with Southern and Scottish Electricity (SSE) that the transformer could only be located on the eastern side of the River Crane, the cables crossing the river via a cable bridge.
Whilst the bridge has been put in place (its design requiring a Permit from the Environment Agency) and the Intake cupboard has been made ready in the Information Centre, SSE could not source the Transformer until May 2023, charging the consequent uplift in price to the Council.
However, before they would instal it, SSE required a Deed of Grant to be drawn up between Transport for London and LB Hillingdon, for a right of way over the few metres of driveway in TfL’s ownership. This legal document was not straightforward, but completion has now taken place.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cranford Park Heritage Asset ProjectReport | 159 KB | DownloadRead as text |
Follow Property, Highways and Transport Select Committee at Hillingdon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2024 | To receive the minutes of the previous meetingThat the minutes from the meeting on 6 March 2024 be confirmed as an accurate record. | Decided | Open |
| 9 Apr 2024 | Review Into The Council's Road Safety Initiatives And Activities Around The Borough's SchoolsThat delegated authority be given to Democratic Services to finalise the recommendations with the Chair and Labour Le... | Decided | Open |
| 9 Apr 2024 | Cabinet Forward PlanThat the update and the Forward Plan be noted. | Noted | Open |
| 9 Apr 2024 | Work ProgrammeThat the work programme be noted. | Noted | Open |
| 6 Mar 2024 | To receive the minutes of the previous meetingThat the minutes from the meeting on 8 February 2024 be agreed as an accurate record. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.