What was decided
The committee approved the application as recommended, with a minor typographical amendment to condition 4.
The approved scheme creates natural grass football pitches using imported soils, with rainwater harvesting, extensive planting and habitat creation. Approximately 60,163m3 of soil will be imported to regrade the site. The plans allow either smaller pitches or one large adult pitch, with each layout used as needed [P24]. Report 1.1, P22, P23, P24
Implementation is subject to conditions covering imported soil, drainage, construction, landscaping, pitch use, ecology and biodiversity. Report P187, P199, P206, P215, P218, P243, P251
Why
The scheme would put underused grassland into community sports use, especially for youth, and support active lifestyles. One consultation response said it would benefit the whole community. Report 1.2, 6.1, 9.1
Outdoor sports and the related engineering work were treated as appropriate in the Green Belt. The public benefit was judged to outweigh the minimal impact on openness, while planting would screen the changes. Football pitches had previously been permitted at the same location, although they were not built. Report 1.6, 4.1, 7.10, 7.11, 7.12, 9.2
The Environment Agency's soil objection was lifted after further information confirmed clean imported soils. Sport England did not object, and the Highway Authority found no measurable congestion, parking or safety concerns. Neighbour impacts were considered acceptable because of the pitch layout, restricted use and construction controls. Report 1.4, 1.5, 1.6, 7.23, 7.24, 7.25, 7.26, 7.27, P50, P62, P63, P68, P199, P215
What happens next
Development must begin before the expiration of three years from the date of permission. Report P173, P174, P175
Before commencement, submit and gain approval for a materials report setting out each soil source, precise volume and chemical test results. If contamination is found, report it immediately in writing and submit any investigation, remediation and verification for approval. Report P218, P219, P220, P221, P224, P225
Submit the drainage scheme before commencement, apart from demolition, ground and enabling work, and the construction logistics plan before development. Submit the landscape scheme, biodiversity gain plan and ecological impact assessment before development, with the ecological assessment informed by the bird, bat and badger surveys identified in the preliminary assessment. Submit pitch operating hours for approval before first use. Report P187, P188, P199, P200, P206, P207, P216, P243, P244, P246, P251
Options considered
- Chosen: Approval with officer conditions and a minor typographical amendment to condition 4. The proposal was considered acceptable, and no material consideration pointed to a different decision. Report 9.3
Implications
- Legal: Planning permission was granted, but commencement and operation remain subject to the recommended conditions and the condition 4 amendment. Report 9.3
- Risk: Imported soil must be tested and linked to approved sources before use. Newly found contamination triggers investigation, remediation and verification. Report P218, P219, P220, P221, P224, P225
- Climate: The scheme includes rainwater harvesting. Conditions require sustainable drainage and tree retention, which the report links to water control, biodiversity and carbon capture. Report 7.39, 7.45, P187, P191, P230
- Climate: The habitat plan is intended to deliver predicted biodiversity gains of 16.81% (2.07 Units) with a 118.34% (0.12 Units) hedgerow net gain. Report 7.49, 7.50, P251
- Risk: The maximum forecast is 320 additional weekend trips, outside peak hours. The Highway Authority found no measurable worsening of congestion, parking stress or road safety. Report 7.33, P62, P63, P68
- Other: Conditions protect neighbours through pitch use limits, a restriction on external lighting, and controls for construction noise, dust, vibration, traffic and water. Report 7.26, P199, P215, P227
- Equalities: The council found no adverse equality impact. An Equality Act 2010 informative reminds operators to identify and remove barriers for disabled users. Report 8.2, P56, P57, P58
- Financial: The proposal is not liable for the Council's Community Infrastructure Levy.
Who and where
- Young people and the wider local community Report 1.2
- Youth football users Report 7.30
- Patrons and drivers attending matches Report 7.31, 7.33, P62
- Neighbouring residents and occupiers Report 7.23, 7.27
- People with disabilities and other users with protected characteristics Report 7.41, 8.2, P56, P57, P58
- Birds, bats, badgers and other protected species Report 7.46, 7.47, P246
- Local drivers, pedestrians and road users Report P63, P68, P199
- Environment Agency, as consultee on imported soils Report 1.5, P44, P218
Timeline
- 13/08/24: A Transport Assessment, T001, Rev 2, was submitted as supporting evidence. Report 7.28
- January 2025: Sports England provided its comments. Report P49, P50
- 02/01/25: A site notice was placed at the site. Report 6.1
- 07-03-25: 46 neighbouring properties were consulted by letter. Report 6.1
- During the 21-day consultation periods: One letter of support was received. Report 6.1
- 5th November 2025: The committee approved the application, subject to a minor typographical amendment to condition 4. Report P13
- Before first use: Pitch operating hours must be submitted to and approved by the Local Planning Authority. Report P215, P216
- Before the expiration of three years from the date of permission: Development must begin. Report P173, P174
Plain English for the jargon
- Green Belt: Protected land where inappropriate development is refused unless very special circumstances exist [7.8].
- Sustainable Drainage System, SuDS: Drainage features embedded in landscaping where practicable, with runoff and exceedance information [P191] [P192] [P193].
- Biodiversity Net Gain, BNG: A requirement for a plan demonstrating compliance with the 10% biodiversity net gain requirement [P251] [P252].
- Community Infrastructure Levy, CIL: A levy adopted by the Council, although this proposal is not CIL liable [8.3].
- Construction Management Plan, CMP: The submitted plan for construction vehicle movements, considered broadly fit for purpose [P65] [P66].
- Ecological Impact Assessment, EcIA: A detailed assessment informed by bird, bat and badger surveys before development starts [P243] [P244] [P246].
- Flood Zone: A flood risk classification under which outdoor sports are treated as water compatible [7.44].
- National Planning Policy Framework, NPPF: The national policy framework used to assess sports provision, Green Belt development and flood risk [7.2] [7.9] [7.37] [7.44].