What was decided
Hillingdon Planning Committee approved the application and the Section 106 legal agreement as recommended [D]. Approval is subject to the planning conditions and the Section 106 heads of terms [1.7] [9.3]. Report 1.7, 9.3
The approved mezzanine provides 1,332 sq. m. of additional floor space inside Unit 2, taking the total floor area to 2,774 sq. m. [3.1] The existing lawful retail use class does not change [3.1]. Report 3.1
The new permission supersedes condition 12 on permission 43510/APP/2012/3176, which restricted sales including clothing and footwear [7.12] [7.15]. The mezzanine may only be used with Unit 2 for the specified retail goods, an ancillary cafe and ancillary storage. It cannot be used for another purpose or subdivided [P214]. Report 7.12, 7.15, P214
Why
The council's retail consultant found that no sequentially preferable, available or suitable site within the defined catchment could meet the retailer's operational requirements [7.7]. The retail impact assessment showed low trade diversion and no credible risk of significant adverse effects on town centre vitality, viability or planned investment [7.11]. Report 7.7, 7.11
The proposal would bring a unit vacant since Summer 2024 back into retail use and create 50 to 60 local jobs, as well as construction jobs [2.1] [7.1]. Because the work stays inside the existing building envelope, officers identified no external alteration, design impact or adverse effect on residential amenity [7.18] [7.19]. Report 2.1, 7.1, 7.18, 7.19
The proposal was found consistent with the National Planning Policy Framework, The London Plan and Hillingdon Local Plan [9.2]. The retail, urban design, landscape and highways officers raised no objection [1.4] [P46] [P58] [P59]. No public comments or representations were received during consultation [6.2]. Report 9.2, 1.4, P46, P58, P59, 6.2
What happens next
Secure and comply with the Section 106 legal agreement. It requires £40,396 for air quality mitigation, construction employment training, an end user employment scheme and a project management and monitoring fee equalling 5% of total financial contributions [7.67] [P166] [P168]. Report 7.67, P166, P168
Before development starts, submit a construction management plan for council approval in consultation with Transport for London. It must cover construction phases and hours, contractor access and parking, air quality and dust [P204] [P205] [P206]. A staff travel plan condition also applies [P59]. Report P204, P205, P206, P59
Begin development before the expiration of three years from the date of permission and work in accordance with the approved plans [P190] [P191] [P193] [P195]. The development must also meet the BREEAM excellent water standard and the restricted use condition [P210] [P211] [P213] [P214]. Report P190, P191, P193, P195, P210, P211, P213, P214
The money
- £40,396 Air quality mitigation contribution secured through the Section 106 agreement Report 7.33, P166
- 5% Project management and monitoring fee, equalling 5% of total financial contributions under the agreement Report P168
Options considered
- Chosen: Approve the application subject to conditions and a Section 106 legal agreement. Officers considered the proposal acceptable and recommended approval subject to the conditions and legal agreement [1.7] [9.2] [9.3]. Report 1.7, 9.2, 9.3
- Rejected: Refuse the application for failing the Sequential Test. The proposal passed because no sequentially preferable, available or suitable site met the retailer's operational requirements [7.7]. Report 7.7
- Rejected: Refuse the application for significant adverse retail impact. The assessment found low trade diversion and no credible risk of significant adverse effects on town centre vitality, viability or planned investment [7.11]. Report 7.11
- Chosen: Require £40,396 air quality mitigation contribution. Transport emissions are not air quality neutral or positive and will affect nearby focus areas [7.27] [7.31] [7.33]. Report 7.27, 7.31, 7.33
- Chosen: Secure construction employment training and an end user employment scheme. Economic Development requested both schemes under the Section 106 agreement [P50] [P51] [P166] [P168]. Report P50, P51, P166, P168
- Chosen: Require construction management and staff travel plan conditions. The highways and air quality officers made their support conditional on these controls [P58] [P59] [P60] [P61]. Report P58, P59, P60, P61
- Chosen: Require the BREEAM excellent water standard and related measures. The condition is intended to reduce mains water consumption [7.52] [P210] [P211]. Report 7.52, P210, P211
- Chosen: Restrict the mezzanine to the assessed retail use. The permission must follow the terms assessed for the application and retain council control over the use [P214] [P215]. Report P214, P215
Implications
- Financial: The Section 106 heads of terms include £40,396 for air quality mitigation and a project management and monitoring fee equalling 5% of total financial contributions [7.33] [P166] [P168]. The report says the mezzanine is not liable for CIL, subject to a post determination review [8.7] [8.8]. Report 7.33, P166, P168, 8.7, 8.8
- Legal: Approval is subject to the recommended conditions and the Section 106 heads of terms [P189] [7.67] [9.3]. The mezzanine must remain linked to Unit 2 and cannot be subdivided [P214]. Report P189, 7.67, 9.3, P214
- Legal: The new permission supersedes condition 12 on permission 43510/APP/2012/3176, which restricted sales including clothing and footwear [7.12] [7.15]. The related refurbishment application 43510/APP/2024/3337 was to be decided under delegated authority at the same time, and the mezzanine condition links it to the assessed retail use [3.2] [7.15]. Report 7.12, 7.15, 3.2
- Staffing: The scheme would create 50 to 60 local jobs, alongside construction jobs [7.1]. The Section 106 terms include construction employment training and an end user employment scheme [P166] [P168]. Report 7.1, P166, P168
- Equalities: The scheme provides level access, disabled parking outside the unit and a 21 person mid rise lift [7.40]. Officers found no adverse equality impacts [8.2]. Report 7.40, 8.2
- Climate: The development is not air quality neutral for transport emissions, so £40,396 mitigation is required [7.31] [7.33]. It also uses LED lighting, an R32 heat pump and heat recovery ventilation [7.55]. Report 7.31, 7.33, 7.55
- Risk: No ground works or footprint increase are proposed, so the report finds no increased contamination or flooding risk [1.4] [7.51] [7.66]. Highways officers found no notable detrimental effect on congestion or road safety [7.25]. Report 1.4, 7.51, 7.66, 7.25
- Other: The retail impact assessment found low trade diversion and no credible risk of significant adverse effects on town centres or planned investment [7.11]. The proposal would improve retail choice and reuse a vacant unit [7.1]. Report 7.11, 7.1
Who and where
- Residents seeking retail choice Report 7.1
- Local workers Report 7.1
- People with disabilities Report 7.40, 8.2
- Town centre businesses and shoppers Report 7.11
- Nearby residents Report 7.19
- Retail park users and visitors Report 7.23, 7.24
- Construction workers and contractors Report P166, P206
- Future Unit 2 operator Report P214
Timeline
- 07.05.2014: Permission 43510/APP/2012/3176 was granted with condition 12 restricting sales of specified goods [7.12]. Report 7.12
- Summer of 2024: The previous occupant closed, leaving Unit 2 vacant [2.1]. Report 2.1
- 29.04.25: Consultation letters were sent to 49 neighbouring properties [6.1]. Report 6.1
- 21.05.25: The application was advertised by site notice and press notice [6.1]. Report 6.1
- 04.06.25: The public consultation period expired [6.1]. Report 6.1
- 5th November 2025: Hillingdon Planning Committee considered and approved the application [P14] [D]. Report P14
- Before the expiration of three years from the date of this permission: Development must have begun [P190] [P191]. Report P190, P191
Plain English for the jargon
- Mezzanine: An additional floor inside the existing building envelope, above the ground floor [3.1].
- Section 106 agreement: The legal agreement securing air quality mitigation, employment schemes and the monitoring fee for this approval [7.67] [P166] [P168].
- Use Class E(a): The lawful retail class used for selling goods other than hot food to visiting members of the public [7.23].
- Sequential Test: The check of town centre and edge of centre sites before accepting an out of centre retail scheme [7.2] [7.7].
- Retail Impact Assessment: The assessment of effects on investment, town centre vitality and viability, consumer choice and trade [7.10].
- BREEAM excellent water standard: At least the excellent standard for the 'Wat 01' water category, with water saving and recycling measures [P210] [P211].
- Community Infrastructure Levy: A levy the report says does not apply to this mezzanine floor, subject to review after the decision [8.7] [8.8].
- Critical Drainage Area: An area where developments must reduce surface water runoff entering sewers [P224].