RESOLVED – ( i ) the 2012/13 allocation of the ‘earmarked’ service improvement expenditure as set out in the report be approved; (ii) the permanent transfer of £150,000 for service improvement expenditure from the Housing Revenue Account General Fund budget to the HRA Capital Budget be approved; (iii) the future allocation from 2013/14 of the £150,000 for service improvement expenditure be delegated to the Chief Officer, Business, Contract and Street Scene Services and the Executive Member for Housing in accordance with agreed Tenant Priorities; (iv) the movement of £120,000 from the existing Major Voids Enhancements Housing Revenue Account Capital Budget to the Kitchen Upgrades Housing Revenue Account Capital Budget be approved; (v) the movement of £11,000 from the existing Windows: Single to Double Glazing Capital Budget to a newly created Sheltered Accommodation Improvements Capital Budget be approved; (vi) the movement of £10,000 from the Environment Works Housing Revenue Account Revenue Budget to a newly created Neighbourhood Improvement Fund Housing revenue Account Revenue Budget be approved; (vii) A supplementary estimate of £96,628 for the stock condition surveys and stock profile surveys from the Housing Revenue Account balances be approved. (Councillor Richards was absent for the vote on this item).
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
To seek approval for the re-alignment of Housing Revenue Account (HRA) Budgets for various council house improvement schemes and funding of housing surveys from the Housing Revenue Account balances.
Recommendation
That Council approve:
1) The 2012/13 allocation of the ‘earmarked’ service improvement expenditure as follows:
i. £75,000 for electrical testing and upgrades ii. £50,000 for Boiler Replacements iii. £25,000 for new Kitchens
2) The permanent transfer of £150,000 for service improvement expenditure from Housing Revenue Account General Fund budget to the HRA Capital Budget.
3) The future allocation (from 2013/14) of the £150,000 capital service improvement expenditure is delegated to the Chief Officer – Business, Contract and Street Scene Services and Executive Member for Housing in accordance with agreed Tenant Priorities.
4) The movement of £120,000 from the existing Major Voids Enhancements Housing Revenue Account Capital Budget to the Kitchen Upgrades Housing Revenue Account Capital Budget
5) The movement of £11,000 from the existing Windows: Single to Double Glazing Capital Budget to a newly created Sheltered Accommodation Improvements Capital Budget
6) The movement of £10,000 from the Environment Works Housing Revenue Account Revenue Budget to a newly created Neighbourhood Improvement Fund Housing Revenue Account Revenue Budget.
7) A supplementary estimate of £96,628 for the stock condition surveys and stock profile surveys from the Housing Revenue Account balances.
3. BACKGROUND TO THE REPORT
Service Improvement Expenditure
3.1The Responsive Repairs Business Case agreed by Council on 7 December 2010 identified that an additional £150,000 could be spent on Council House repairs and improvements whilst still achieving substantial savings on the previous contract arrangement. For this year, whilst a consultation to determine our Tenants future requirements is being finalised, the following improvement areas have been identified:
A. Electrical testing and upgrades – An Electrical Periodic Inspection (PIR) was carried out at each Council property on a 15 year cycle, this inspection highlights any non compliance in accordance with current regulation. The regulation has recently been revised. One of the main changes is that, in most properties, a new consumer unit now has to be installed, thereby substantially increasing the cost of remedial works. It is also a new requirement that the cycle of testing be reduced from a 15 year to a 10 year cycle. This funding will assist in meeting the new requirements for this year whilst additional funding is identified for future years.
B. Boiler Replacements – The boiler servicing the Castle Court Complex, which was installed in 1977 is due to be replaced. A new energy efficient ‘green’ heating system incorporating condensing boilers, solar thermal, improved controls and photovoltaic cells will be installed as a replacement.
C. Additional kitchen refurbishment projects – Kitchens are replaced in order of priority from the Kitchen Refurbishment Waiting List. At present budget levels, any new requests to this Waiting List are schedule to be carried out in the financial year 2019/20. The additional funds will assist with reducing waiting time.
The above schemes will assist in improving the overall fabric of the housing stock and ensure compliance with our decent homes aspirations as a responsible Landlord. Future year allocations will be determined based on decent homes requirements and tenant views.
Movement of Existing Budgets
3.2Over the last three years, the Council has increased the number of new kitchens units that it has installed whilst a property is empty. This change has been introduced for several reasons:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.