Resolved

RESOLVED – ( i ) the increase in the project budget for the Project to £300,000 be approved; (ii) the increase of £62,880 be funded from additional FA grant funding of £49,823 and earmarked reserves of £13,057.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Council, 3 pages

Purpose of report

In accordance with financial procedure rules, to seek member approval for additional expenditure which can be funded from additional grant funding and existing reserves.

Recommendation

That Council agree:

1. To the increase in the project budget for Richmond Park Project to £300,000. 2. The increase of £62,880 is funded from additional FA grant funding of £49,823 and Earmarked Reserves of £13,057.

3. BACKGROUND TO THE REPORT

3.1Work to improve the drainage of Richmond Park was initially identified in the Green Space Strategy, as a result of problems with water lying on the football pitches after periods of heavy rainfall. The building of the Hinckley Club for Young People has encouraged a bid to be put forward to the FA Football Foundation to apply for match funding to allow for a higher specification drainage scheme to ensure the quality of the football pitches at the site compliment the new state of the art facility for young people.

3.2There is now a need for further funding (as specified in the financial implications) to ensure the project can be carried out as per the specification agreed by the FA in the grant application and also in line with Environment Agency conditions.

4. FINANCIAL IMPLICATIONS [PE]

4.1The current approved project budget is £237,120 of which £100,000 was to be funded from the Football Association and £137,120 from HBBC. Tendering costs have come in well above the budget therefore the estimated project cost is now £300,000. The Football Association funding has increased to £149,823. This therefore means an additional £13,057 is required from HBBC to take HBBC’s funding element to £150,177. The additional £13,057could be met from Special Expenses Reserves. 5. LEGAL IMPLICATIONS (AB)

A funding agreement with the Football Foundation has been agreed in respect of the increased grant funded part of the project. Otherwise no legal implications are raised by this report.

6. CORPORATE PLAN IMPLICATIONS

This document contributes to Strategic Objectives 1, Cleaner and greener neighbourhoods, and 3, Safer and healthier borough of the Corporate Plan.

Consultation

None specific for this report.

Risk implications

It is the Council’s policy to proactively identify and manage significant risks which may prevent delivery of business objectives.

It is not possible to eliminate or manage all risks all of the time and risks will remain which have not been identified. However, it is the officer’s opinion based on the information available, that the significant risks associated with this decision / project have been identified, assessed and that controls are in place to manage them effectively.

The following significant risks associated with this report / decisions were identified from this assessment:

Management of significant (Net Red) Risks Risk Description Mitigating actions Owner Non approval of budget. Budget deficit to be found Michael from other budgets. Brymer . Not fulfilling agreement with FA. Budget deficit will have to Michael Lack of available budget will be found from other Brymer mean agreed specification for budgets to ensure agreed works will be unachievable. specification can be achieved and FA funding secured.

9. KNOWING YOUR COMMUNITY – EQUALITY AND RURAL IMPLICATIONS

The recommendations contained within the report present no implications with regard to equalities or rural areas. The development will be of benefit to all groups within the community and all areas of the Borough

10. CORPORATE IMPLICATIONS

By submitting this report, the report author has taken the following into account: - Community Safety - Environmental implications - ICT implications - Asset Management implications - Human Resources implications - Planning Implications - Voluntary Sector

Background papers: None

Contact Officer: Paul Scragg

Executive Member: Cllr B Crooks

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Richmond ParkReport 3 pages DownloadRead as text

More from Hinckley and Bosworth Council

All decisions
MeetingDecisionOutcome
27 Oct 2026 Minutes of the previous meetingRESOLVED – the minutes of the meeting held on 29 September be approved. Approved Open
27 Oct 2026 Review of the council's constitutionRESOLVED – the changes to the constitution be approved. Approved Open
27 Oct 2026 Community Governance Review - Witherley - final recommendationsRESOLVED – (i) The current parish of Witherley and Witherley Parish Council be abolished; (ii) Fenny Drayton parish a... Decided Open
29 Sep 2026 Minutes of the previous meetingsRESOLVED – the minutes of the meetings held on 23 July and 4 August 2026 be confirmed as a correct record. Decided Open
29 Sep 2026 Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies