Executive, Wednesday 20 November 2013 at 6.30pm

Hinckley Squash Club

Approved Executive 1 paper

Executive approved this item on Wednesday 20 November 2013. Below is the council's own wording, with the papers it was decided on.

Item269

Resolved

RESOLVED – financial assistance of up to £49,000 in grant funding to help facilitate the delivery of a four court new squash facility in Hinckley be approved subject to a management agreement regarding public use.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Executive, 3 pages

Wards affected

Purpose of report

1.1To report on the current position regarding Hinckley Squash Club who are required to relocate from the Bus Station site for the Crescent regeneration scheme and seek Member support to financial assistance to support the delivery of a four court state of the art new facility at Tungsten Park.

Recommendation

2.1That Members note the positive progress made in securing the opportunity for a new site and premises for Hinckley Squash Club.

2.2That Members approve financial assistance of up to £49,000 in grant funding to help facilitate the delivery of a four court new squash facility in Hinckley.

3. BACKGROUND TO THE REPORT

3.1Following the grant of planning consent for the Crescent regeneration scheme on the Hinckley Bus Station site in 2011 and grant of a Compulsory Purchase Order by the Secretary of State in 2012, negotiations have taken place with a number of the owners and occupiers. This has helped to secure a satisfactory outcome in respect of relocation or compensation for moving off site to enable the Crescent scheme to be developed. Informal notices have already been served and the General Vesting Order seeking possession of the site is programmed to be served in January 2014. This will enable works on the Bus Station site to commence in March 2014 and be complete and open to the public in 2015.

3.2In parallel with this, the Council is undertaking a major procurement exercise on the provision of a new Leisure Centre on Argents Mead. A report on the outcomes of this process and a decision to take forward the implementation of a new Leisure Centre is programmed for January 2014. None of the shortlisted schemes currently accommodate new squash courts.

New Squash Court Facility

3.2In view of the above, discussions have been underway with Hinckley Squash Club and England Squash and Racket Association to seek to secure an enhanced replacement facility on Tungsten Park, Coventry Road which could be made available for community use. The scale of the new facility (which will cost in the order of £1M) not only replaces the three court facility currently on the Bus Station site, but will provide a fourth court which will allow the centre to be used for regional competitions. The total cost of providing a fourth court is estimated at £75,000. England Squash and Racket Association have agreed to contribute to the cost. The Council is being requested to provide the remaining contribution of £49,000. Management Agreement

3.3If Members are minded to agree to providing a financial grant to enable delivery of a four court facility, it is proposed that this will be subject to a management agreement to secure community use of the facility. This would be similar to other agreements that England Squash and Racket Association have secured for Council’s on similar arrangements elsewhere in the country and include free use of the facility by the council to host events and to work in partnership with the council and school sports activity network to develop sustainable school club links. A key benefit of this approach is that it will continue to provide squash facilities available to the public following the closure of the existing Leisure Centre. It will also allow a more proactive approach for encouraging community use of the new facility on Tungsten Park.

3.4Members are recommended to support the request for financial assistance.

4. FINANCIAL IMPLICATIONS [SK]

4.1If Members support this request for grant funding then a supplementary budget of £49,000 would need to be approved by the Executive in line with financial regulations.

4.2Since the building of a squash court is capital by nature, this contribution would be reflected in the council’s capital programme as “Revenue Expenditure Funded from Capital Under Statute”. This reflects that a capital contribution is being made for an asset that will not be held on the council’s Balance Sheet.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hinckley Squash ClubReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Hinckley Squash ClubThis decision
  2. Hinckley Squash & Rackets ClubApproved
  3. Hinckley Squash & Rackets ClubAgreed

More from Hinckley and Bosworth Executive

All decisions
MeetingDecisionOutcome
23 Sep 2026 Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... Decided Open
23 Sep 2026 Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... Approved Open
23 Sep 2026 Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. Approved Open
29 Jul 2026 Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... Noted Open
29 Jul 2026 Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies