Resolved
RESOLVED – ( i ) the undertaking of a tenancy and property audit be approved; (ii) a supplementary budget request of up to £50,000 be approved, to be financed from HRA balances.
Executive approved this item on Wednesday 20 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – ( i ) the undertaking of a tenancy and property audit be approved; (ii) a supplementary budget request of up to £50,000 be approved, to be financed from HRA balances.
1.1To propose undertaking a full tenancy and property audit of our tenants/tenancies.
1.2To use the results of the tenancy and property audit to inform information held on tenants, to assist in tenancy management, to gain a view on the internal condition of properties and to undertake a rent review of Council rents.
2.1That Executive approve the undertaking a tenancy and property audit.
2.2That Executive approve a supplementary budget request of up to £50,000, to be financed from HRA balances to finance the costs associated with executing and undertaking a tenancy/property audit.
3. BACKGROUND TO THE REPORT
3.1In order to ensure robust and effective management of our housing stock and tenants, accurate information is needed on both our properties and tenancies.
3.2With regard to tenants, currently information held is incomplete, particularly where tenants have been in resident for a number of years. Increasingly services to tenants are reactive, due to the fact that individual needs and issues are not known until they manifest themselves into problems. By gaining a baseline position on our tenants a better understanding of the future and current need will be gained in order to inform service configuration.
3.3Understanding the internal condition of properties will enable tenancy conditions to be enforced if there are issues with damage caused by tenants. This will have a beneficial impact on the long term condition of properties.
3.4Gaining information on property type/facilities will also enable the property attributes to be updated and will inform a rent review of properties. Carrying out a rent review will provide the opportunity to base rents on current, up-to-date data.
3.5The outputs of these exercise would show adherence to the “collect once, use numerous times” (COUNT) which is deemed best practice from a data quality point of view.
4. METHOD OF UNDERTAKING PROPERTY/TENANCY AUDIT
4.1The audit work required to collect the data can be carried out internally, with the employment of temporary surveyors or through the engagement of a consultant. The preferred method would be the engagement of a consultant which would ensure an objective, independent oversight, quality control and would overcome internal
-1- capacity issues preventing current officers carrying out the review. An estimate of the cost of the work is up to £50,000.
4.2An internal governance structure would be set up to over see the project, led by the Head of Finance and supported by the Chief Officer (Housing, Community Safety and Partnerships). This project will also involve input from other departments using this information (e.g. revenues and benefits and housing repairs) to ensure it meets the requirements of other users.
4.3It is proposed that the cost of this work is funded from HRA balances and as such, a supplementary budget request to a maximum of £50,000 is requested from Executive to fund this expenditure.
5. FINANCIAL IMPLICATIONS (KB)
5.1It is proposed that the cost of this work is funded from HRA balances and as such, a supplementary budget request to a maximum of £50,000 is requested from Executive to fund this expenditure. The HRA balance is currently as at 1st April 2013 was £1.891million
5.2Any outputs from the review which result in changes to rent levels would need to be input into the HRA 30 year Business Plan to ensure the ongoing viability of balances and reserves.
6. LEGAL IMPLICATIONS (AB)
6.1Any information held about tenants must be processed in compliance with the Data Protection Principles set out in the Data Protection Act 1998. Care must be taken that the information collected is done so fairly and lawfully and that it is adequate, relevant and not excessive in relation to the purpose it is collected for. In addition the information should not be held for longer than is necessary.
7. CORPORATE PLAN IMPLICATIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tenancy/property auditReport | 3 pages | DownloadRead as text |
Follow Executive at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... | Decided | Open |
| 23 Sep 2026 | Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... | Approved | Open |
| 23 Sep 2026 | Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. | Approved | Open |
| 29 Jul 2026 | Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... | Noted | Open |
| 29 Jul 2026 | Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.