CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hinckley and Bosworth Borough Council
Audit Committee, Thursday 13 October 2016 at 6.30pm

Internal Audit progress report

Noted Finance 1 paper

Audit Committee noted this item on Thursday 13 October 2016. Below is the council's own wording, with the papers it was decided on.

Item212

Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Audit Committee, 11 pages

www.pwc.co.uk

Internal Audit Progress Report

Hinckley and Bosworth Borough Council

October 2016 Progress Report

Contents Introduction 2

Activity and progress 4

Appendix 1: Detailed progress tracker 5 Appendix 2: Overdue recommendations 7 Appendix 3. Recent Publications 8

Distribution List

For information Audit Committee

 Contents Progress Report

Introduction Purpose of this report We are committed to keeping the Audit Committee up to date with Internal Audit progress and activity throughout the year. This summary has been prepared to update you on our activity since the last meeting of the Audit Committee and to bring to your attention matters that are relevant to your responsibilities as members of the Authority’s Audit Committee.

2016/17 Internal Audit Plan Progress The draft 2016/17 Internal Audit Plan was presented and approved by the Audit Committee at its meeting on the 27 July 2016. The Internal Audit Plan sets out the risks that were identified as part of the planning process, together with the targeted work to be performed in order to address the identified risks. We will report back to you on any changes to the assessment of audit risks and on the work undertaken in response to the risks identified.

We have concluded our Internal Audit fieldwork in the following areas:

 Corporate Governance

We have started our Internal Audit fieldwork and are pleased to report work is ongoing in the following areas:

 Finance;  Compliance;  Estates and Assets;  Community Safety;  Partnerships;  Environmental Health; and  Revenues and Benefits Partnership.

A detailed assessment of our performance against the Internal Audit Plan, tracking assignments undertaken and planned activity is shown in Appendix One. At the time of writing this report we have completed 22 of the planned audit days. This represents 17% of the annual internal audit plan and is broadly in line with our planned timescales.

Changes to the 2016/17 Internal Audit Plan Our original plan indicated that there would be two reviews into Housing Benefits and Fraud prevention and detection in the Revenues and Benefits Partnership. Following a scoping meeting with the Head of the Revenue and Benefits Partnership in August 2016 we have determined it more appropriate to undertake one substantial review focused on key areas of risk currently facing the Revenues and Benefits Partnership rather than reviewing basic operating controls in two areas. In agreement with management we will use the 14 days included in the Internal Audit Plan to undertake just one specifically tailored review. This work is due to commence in quarter three.

Our original plan indicated that there would be a review around Environmental Health during quarter 3. Following a scoping meeting with the Environmental Health Chief Officer in August 2016 we have determined it more appropriate to undertake a review into the processes and controls around the Garden Waste Recycling charges which fall under the remit of the Street Scene services rather than Environmental Health. The work is still scheduled to take place during quarter 3.

Our original plan indicated that some days of the internal audit plan would be used to support the Council with the advancement of the Hinckley and Bosworth Development Company. Following a scoping meeting with the Estates and Asset Manager in August 2016 it was confirmed that the Council have decided they will not be

Page | 2 Progress Report

progressing with the Development Company and as such further support is not required. We will review at a future date if the allocated audit days can be used to support future Council projects.

Page | 3 Progress Report

Activity and progress Final reports Since our previous Internal Audit Progress Report, we have issued a final report for the following review performed in accordance with the 2016/17 Internal Audit Plan:

Ref Name of audit Conclusion Date final Number of recommendations made report issued Critical High Medium Low

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit progress reportReport 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Internal Audit progress reportThis decision
  2. Car Parks 2026/27 - Internal Audit Final ReportApproved
  3. Internal Audit progress reportNoted
  4. Enforcement Action - Planning 2025/2026 - Internal Audit Final ReportApproved
  5. Internal Audit Progress report - September 2026Approved
  6. Internal Audit Annual Report 2025/2026Approved

More from Hinckley and Bosworth Audit Committee

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 16 September be confirmed as a correct record. Decided Open
11 Nov 2026 Car Parks 2026/27 - Internal Audit Final ReportRESOLVED – the internal audit final report for car parks be approved. Approved Open
11 Nov 2026 Internal Audit progress reportRESOLVED – (i) The internal audit progress report be noted; (ii) Further discussion take place between the chairs of ... Noted Open
11 Nov 2026 Progress Report on the National Fraud Initiative (NFI) and any other Fraud issuesRESOLVED – the report be noted and the national report be circulated to members when available. Noted Open
11 Nov 2026 Corporate Risk Register reviewRESOLVED – the risk register be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies