Resolved
RESOLVED – the report be noted.
Finance & Performance Scrutiny noted this item on Monday 21 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – the report be noted.
1.1To provide the Finance and Performance Scrutiny with the 2nd quarter 2016/17 outturn position for: o Performance Indicators including available benchmarking o Service Improvement Plans o Corporate risks o Service area risks.
2.1That members: o Note the 2nd quarter 2016/17 position for items listed at 1.1 above o Recommend any actions that should be taken to improve performance on indicators failing to meet target o Recommend any actions that should be taken to address Service Improvement Plans that are showing signs of slippage o Review risks that pose the most significant threat to the Council’s objectives and priorities (red risks).
3. BACKGROUND TO THE REPORT
3.1Hinckley and Bosworth Borough Council provide a wide range of services that are delivered to the community and set strategic aims that help focus on priorities in order to deliver the vision: “A Borough to be proud of”.
3.2This is achieved by managing performance in the following ways: o On a daily basis within each section o On a monthly basis within each service area o On a quarterly basis through the council's decision-making process o On an annual basis through the production of the council's “Corporate Plan".
06/16 3.3 The council’s performance is monitored through Service Improvement Plans and includes performance indicators which are measurable. These are set by the council to show how well local priorities and objectives are being met.
3.4Inherent in the corporate aims and outcomes are “risks” that create uncertainty. The council recognises it has a duty to manage these risks in a structured way to help ensure delivery of priorities and to provide value for money services. The council has a Risk Management Strategy which sets out the framework for the monitoring and management of risks.
3.5Performance and risk management is embedded into all the council’s business activities in a structured and consistent manner. All Service Improvement Plans which include Performance Indicators and Risks are held and managed on the council’s performance management system: TEN.
Overall summary for the period April to September 2016/17
3.6Performance Indicators – 2nd quarter 2016/17. There are fifty eight performance indicators that are measured and monitored at quarterly intervals.
Of these, four indicators are showing some slippage to target:
Indicator 2016/17 2016/17 Comments target 2nd qtr actual LCUS1b – 15% 25.26% Still above target - whilst calls have marginally Customer reduced for this quarter compared to 2015/16 the services: Lost average time for the length of call is increasing (on calls average 30 seconds per call) . This is due to the more complex nature of the queries. Currently recruiting to .50 FTE to cover a secondment and currently training a new recruit 1.0 FTE (takes 6 months training) who has replaced an experienced member of staff who left in the summer. This represents a reduction in 10.50% of the team and therefore has had an impact. Following recruitment and further training this should be addressed.
LCUS3 - 80% 74.20% Still above target: Currently training a new recruit 1.0 Customer FTE (takes 6 months training) who has replaced an services: person experienced member of staff who left in the summer. sees customer This represents a reduction in 10.50% of the team within 10 mins and therefore has had an impact. Following recruitment and further training this should be addressed. Good customer satisfaction levels continue to support that customers are happy to wait for the excellent service provided.
LI009 – Finance: 25% 28% Deviation to target mainly due to slight increase Debt over 90 in debts from our commercial units. days old as a % of aged debt We are working with the Estates team to reduce this debt.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Performance & risk management update, 2nd quarter summary for 2016/17Report | 11 pages | DownloadRead as text |
Follow Finance & Performance Scrutiny at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Aug 2026 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 6 July 2026 be confirmed as a correct record. | Decided | Open |
| 6 Jul 2026 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 11 May 2026 be confirmed as a correct record. | Decided | Open |
| 6 Jul 2026 | Hinckley and Bosworth UK Shared Prosperity Fund UpdateRESOLVED – the report be noted. | Noted | Open |
| 6 Jul 2026 | Performance and Risk Management Framework end of year summary for 2025/26RESOLVED – Members review the risks that posed the most threat to the council’s objectives and priorities and note th... | Decided | Open |
| 6 Jul 2026 | Business Rates and Pooling update Quarter 4 - 2025/26RESOLVED – the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.