Performance and Risk Management Framework end of year summary for 2018/19

Agreed Finance 1 paper

Finance & Performance Scrutiny agreed this item on Monday 24 June 2019. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

It was agreed that a historical report of performance indicators dropped or targets that had been amended would be included the next time this matter was reported · Targets were generally not reduced or even maintained if they had been achieved · The number of missed bins would be reported as a percentage in future · Due to difficulties in recruiting a Building Control Manager, the authority had entered into a shared service with Blaby and Harborough district councils · Nine of the 20 service improvement plan targets had not met their target date and most would be rolled over to 2019/20 · The Risk Management Strategy was due for review during 2019/20. A member requested that, as it was difficult to avoid acronyms in such reports, a glossary be provided. It was agreed that this would be considered. Councillor Webber-Jones entered the meeting at this juncture. It was moved by Councillor Sheppard-Bools, seconded by Councillor Gibbens and RESOLVED – the 2018/19 end of year position in relation to performance indicators, service improvement plans, corporate risks and service area risks be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Finance & Performance Scrutiny, 13 pages

Purpose of report

1.1To provide Finance & Performance Scrutiny with the end of year 2018/19 outturn position for: o Performance Indicators including benchmarking where available o Service Improvement Plans o Corporate risks o Service area risks

Recommendation

2.1That members: o Note the 2018/19 end of year position for items listed at 1.1 above o Recommend any actions that should be taken to improve performance on Indicators that are not on target o Recommend any actions that should be taken to address Service Improvement Plans showing signs of slippage against target date(s) o Review risks that pose the most significant threat to the Council’s objectives and priorities (red risks)

3. BACKGROUND TO THE REPORT

3.1Hinckley and Bosworth Borough Council provide a wide range of services that are delivered to the community and set strategic aims that help focus on priorities in order to deliver the council’s vision for Hinckley & Bosworth to be: “A Place of Opportunity” This is achieved by managing performance in the following ways: o On a daily basis within each section o On a monthly basis within each service area o On a quarterly basis through the council's decision-making process o On an annual basis through the production of the council's “Corporate Plan"

3.2The Council’s performance is monitored through Service Improvement Plans and includes performance indicators which are measurable. These are set by the Council to show how well local priorities and objectives are being met.

06/16 3.3 Inherent in the corporate aims and outcomes are “risks” that create uncertainty. The Council recognises it has a duty to manage these risks in a structured way to help ensure delivery of priorities and to provide value for money services. The Council has a Risk Management Strategy which sets out the framework for the monitoring and management of risks.

3.4Performance and risk management is embedded into all the Council’s business activities in a structured and consistent manner. All Service Improvement Plans which include Performance Indicators and Risks are held and managed on the Council’s performance management system: TEN

Overall summary for the period April 2018 to March 2019

3.5Performance indicators – Sixty indicators covering all service areas have been monitored for performance:  Thirty three indicators are monitored monthly  Twenty three indicators are monitored quarterly  Four indicators are monitored annually

3.5.1 Overall status of performance indicators

3.5.2 There are no outstanding indicator returns

3.5.3 Twenty indicators did not meet target Indicator Target Actual Comments Working Days Lost 8 9.28 Despite not meeting target we have seen a positive due to Sickness decreasing trend this year compared to 2017/18 which Absence was 10.40 days. Long term absence has particularly been a challenge during 2018/19, in contrast short term absence has reduced by 35%; this is due to the hard work of managers who are consistently implementing the council’s sickness policy. Long term absence cases are closely managed by the HR Team and scrutinised each month by the Strategic Leadership Team and will continue to do so during 2019/20. % Ethnic minority 6% 4.5% 19/425 employees in the Employee count has increased overall while ethnic workforce minority group count remains the same Housing Repairs – 92% 88.6% This is our first year of benchmarking against this figure. completed at first We have identified performance by contractor and are visit working closely with them to bring these figures up

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Performance and Risk Management Framework end of year summary for 2018/19Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Performance and Risk Management Framework end of year summary for 2018/19This decision
  2. Performance and Risk Management Framework end of year summary for 2025/26Noted
  3. Performance & Risk Management Framework 2nd quarter summary for 2024/25Noted
  4. Performance & Risk Management Framework 1st quarter summary 2024/25Noted
  5. Performance and Risk Management Framework Quarter 2 summary 2023/24Noted
  6. Performance and Risk Management Framework end of year summary for 2020/21Agreed

More from Hinckley and Bosworth Finance & Performance Scrutiny

All decisions
MeetingDecisionOutcome
24 Aug 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 6 July 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 11 May 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Hinckley and Bosworth UK Shared Prosperity Fund UpdateRESOLVED – the report be noted. Noted Open
6 Jul 2026 Performance and Risk Management Framework end of year summary for 2025/26RESOLVED – Members review the risks that posed the most threat to the council’s objectives and priorities and note th... Decided Open
6 Jul 2026 Business Rates and Pooling update Quarter 4 - 2025/26RESOLVED – the report be noted. Noted Open