Executive, Wednesday 10 July 2019 at 6.30pm

Request for Supplementary Budget for Health & Safety Improvements at Jubilee building

Approved Executive 1 paper

Executive approved this item on Wednesday 10 July 2019. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

RESOLVED – a supplementary budget of £29,023.00 to allow for health and safety improvements at the Jubilee Building be approved.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Executive, 4 pages

Purpose of report

1.1To agree a supplementary budget to support health and safety improvements at the Jubilee Building.

Recommendation

2.1Executive agrees a supplementary budget of £29,023.00 to allow for health and safety improvements at the Jubilee Building.

3. BACKGROUND TO THE REPORT

3.1Two recent visits to the Jubilee Building by the Health and Safety Executive highlighted a number of health and safety improvements which were required in order to ensure compliance with Health and Safety Regulations.

3.2Following these visits an officer task group was set up to respond to the issues raised and to identify necessary works. The works are detailed in appendix 1. Immediate priority works have been completed and subsequently the Health and Safety Executive have confirmed that appropriate action to remedy these matters has been completed. In the course of a full review of the Jubilee depot a number of other key safety improvements have been identified to ensure future compliance with health and safety regulations and to ensure the safe operation of the depot and its staff.

3.3The costs of the works are £69,000.00. A supplementary budget of £29,023.00 is required to support these works.

4. EXEMPTIONS IN ACCORDANCE WITH THE ACCESS TO INFORMATION PROCEDURE RULES

4.1Report to be taken in open session.

06/16 5. FINANCIAL IMPLICATIONS (AW)

5.1The additional cost of the supplementary will be met from the waste management reserve, which will reduce reserves, but ensure there is no in year affect on the general fund.

5.2There is currently a £30,000 capital budget and a £10,000 revenue budget in place Therefore, if the £10,000 revenue budget is utilised, the supplementary required is £29,023.

5.3Also, in the capital programme there is £30,000 in 2020/21 and £30,000 in 2021/22 for health and safety improvements at the Jubilee Building. Therefore it may be possible to offset the increased costs over the different financial years if further work is not needed.

6. LEGAL IMPLICATIONS (FA)

6.1The Health and Safety at Work Act 1974, associated Acts and statutory instruments provide a number of legal obligations for employers to undertake, failure of which can result in prosecution.

7. CORPORATE PLAN IMPLICATIONS

7.1Contributes to Corporate objectives on People and Place.

Consultation

8.1Unison is actively involved in the health and safety improvements at the Jubilee.

Risk implications

9.1Management of significant (Net Red) Risks Risk Description Mitigating actions Owner Failure to provide safe working H&S review of site Caroline environment completed, action plan Roffey developed, and new Jubilee H&S working practices embedded.

10. KNOWING YOUR COMMUNITY – EQUALITY AND RURAL IMPLICATIONS

10.1The site is a waste transfer station and as such we must comply with the environmental permitting regulations and not cause and nuisance to our neighbours or environmental damage.

11. CORPORATE IMPLICATIONS

11.1By submitting this report, the report author has taken the following into account:

- Community Safety implications - Environmental implications - ICT implications - Asset Management implications

06/16 - Procurement implications - Human Resources implications - Planning implications - Data Protection implications - Voluntary Sector

Background papers: None

Contact Officer: Sharon Stacey ext 5636 Executive Member: Councillor B Crooks

06/16 APPENDIX 1

Yard Reconfiguration follow HSE visit and subsequent risk assessments 2019 - Jubilee Building, Hinckley

Value of remaining works Pedestrian Safety £13,900.00 Vehicle safety £15,300.00 Infrastructure £9,823.00 Total of remaining works £39,023.00

06/16

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Request for Supplementary Budget for Health & Safety Improvements at Jubilee buildingSupplementary 4 pages DownloadRead as text

At this meeting

Whole meeting
60MinutesOn the agenda
62Request for Supplementary Budget for Health & Safety Improvements at Jubilee buildingThis decision
63Matter from which the public may be excludedDecided 64Leicestershire ICT Partnership Shared ServicePrivate

On this subject at Hinckley and Bosworth

Search all
  1. Request for Supplementary Budget for Health & Safety Improvements at Jubilee buildingThis decision
  2. Temporary Accommodation - Supplementary budget requestApproved
  3. Supplementary income request - Homelessness demands and temporary accommodationApproved
  4. Supplementary income request - Homelessness demands and temporary accommodationNoted
  5. Additional supplementary budget request for social service adaptation worksNoted
  6. Markets - supplementary budget requestApproved

More from Hinckley and Bosworth Executive

All decisions
MeetingDecisionOutcome
23 Sep 2026 Future Ready Council StrategyRESOLVED – The Executive: (i) Endorsed the 2026–2028, attached as Appendix A. (ii) Supported the development of a del... Decided Open
23 Sep 2026 Housing Services - Landlord Property Safety and ComplianceRESOLVED – The Executive: (i) approved the Landlord Property Safety and Compliance Policy 2026. (ii) Noted the streng... Approved Open
23 Sep 2026 Cyber Security StrategyRESOLVED - (i) Members approved the strategy. (ii) The positive work undertaken by the ICT Service to date was noted. Approved Open
29 Jul 2026 Tenant satisfaction measures and tenant engagement updateRESOLVED – The Executive: (i) Noted the tenant engagement activity undertaken during 2025/26; (ii) Acknowledged the i... Noted Open
29 Jul 2026 Fraud StrategyRESOLVED – The Executive: (i) Considered and approved the Fraud Management Strategy & Action Plan; (ii) Noted that of... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies