Internal
Progress Report Year ending 31 March 2020
Hinckley and Bosworth Borough Council 30 October 2019
© 2019 Grant Thornton UK LLP | Progress Report | 30 October 2019 Internal
Introduction & headlines Purpose Changes to the audit plan (continued) This report provides an update on progress against the 2019/20 internal audit plan. Due to the urgent deadlines and the potential financial implications for the Council, we have prioritised these pieces of work by delaying the start of some of our Q2 audits. The paper also includes a summary of emerging national issues and developments that Both of these pieces of work are currently in progress. may be relevant to you as a council. We pose a series of challenge questions in respect of these emerging issues, which the committee may wish to consider. Please In addition, we have agreed with management to change the timing of three reviews: note these challenge questions do not require a response for audit purposes. • Key financial systems - we have deferred to quarter 4 because of the impact on the finance team of the delayed external audit occurring in the Autumn. Final reports issued • Capital projects delivery – awaiting approval of the asset management plan and audit to be undertaken following this. We have finalised two audit reports since the last Audit Committee meeting. • Investment property management - commercialisation strategy is in its infancy Audit Completed Overall assurance rating so delay to quarter 4 requested.
Health and Safety Partial assurance with improvements required Crematorium N/a – advisory report Work in progress As shown in the table overleaf, we have a number of set up meeting in place and anticipate making some accelerated progress with the audit plan over the coming weeks. Work completed We have completed 12 days of our annual internal audit plan and 16 days of We have also completed our review of the Housing Revenue Account business plan. additional work as at 17 October 2019. This way has been delayed due to difficulties in obtaining sufficient evidence to complete our testing. However, the draft report has been discussed and is currently with management. Resourcing the internal audit plan Changes to the audit plan We confirm that we have sufficient internal audit team members available to deliver Management asked us to undertake two other pieces of work, which were not included the remainder of the audit plan on time. We will flex the plan where needed for in the 19/20 internal audit plan: emerging priorities and to accommodate timescales requested by management. • Leisure management contract review – the Council is challenging the utility costs of a leisure centre contract and has asked us to undertake an independent review • 2018/19 housing subsidy grant claim – we have agreed to undertake this work instead of your external auditor
© 2019 Grant Thornton UK LLP | Progress Report | 30 October March 2019 2 Internal
Recommendation Tracking Th graph below summarises the status of internal audit recommendations issued in 2018/19. 47 recommendations have been issued.
© 2019 Grant Thornton UK LLP | Progress Report | 30 October March 2019 3 Internal
Progress against 2019/20 internal audit plan Internal Audit area Planned Indicative Scope APB Fieldwork Fieldwork Debrief Draft Management Final Days days timing meeting agreed started completed held report response report used held received
Key financial systems 14 Q4 -
Capital projects delivery 11 Q4 -
Risk management 7 Q2 -
Investment property 12 Q4 - management
Housing options – 10 Q3 0.5 homelessness
Housing repairs 9 Q3 0.5
Planning enforcement 12 Q3 0.5
Waste management 12 Q3 0.5
Building control 11 Q4 0.5
Revenues and benefits 12 Q2 4 partnership
Sub-total 110 6.5
Recommendation 3 Ongoing 0.5 follow up
Contract management 4 Ongoing 1
Annual risk assessment 3 Complete 3 and planning
Attendance at audit 2 Ongoing 0.5 committee and meetings
Contingency 8 N/a 0.5
Total 130 12
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 13 pages | DownloadRead as text |
Follow Audit Committee at Hinckley and Bosworth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Nov 2026 | Minutes of previous meetingRESOLVED – the minutes of the meeting held on 16 September be confirmed as a correct record. | Decided | Open |
| 11 Nov 2026 | Car Parks 2026/27 - Internal Audit Final ReportRESOLVED – the internal audit final report for car parks be approved. | Approved | Open |
| 11 Nov 2026 | Internal Audit progress reportRESOLVED – (i) The internal audit progress report be noted; (ii) Further discussion take place between the chairs of ... | Noted | Open |
| 11 Nov 2026 | Progress Report on the National Fraud Initiative (NFI) and any other Fraud issuesRESOLVED – the report be noted and the national report be circulated to members when available. | Noted | Open |
| 11 Nov 2026 | Corporate Risk Register reviewRESOLVED – the risk register be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.