CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hinckley and Bosworth Borough Council
Scrutiny Commission, Thursday 2 July 2020 at 6.30pm

Hinckley Crematorium Project Update

Noted Scrutiny 1 paper

Scrutiny Commission noted this item on Thursday 2 July 2020. Below is the council's own wording, with the papers it was decided on.

Item395

Resolved

RESOLVED – the report be noted and RECOMMENDED to Council.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Scrutiny Commission, 7 pages

Purpose of report

1.1This report reviews the progress of the Hinckley Crematorium project following the tender period for selection of a main contractor to carry out the construction phase of the project.

Recommendation

2.1That members:  note the tender sum of £5,070,819.24 for a 50 week programme  approve a revised budget of £6,915,000 for delivery of the scheme (£1,943,190 supplementary).  approve the updated business case and proposed in-house management model

3. Background to the report

3.1HBBC accessed the Procure Partnerships East Midlands Framework to select potential contractors. Our projects estimated value sat within the £4m - £12m procurement category which contained eight contractors, all of which were informed of the tender opportunity and asked if they would be interested in tendering

3.2Six contractors responded positively to the invitation to tender from the Procure Partnerships East Midlands Framework, of which four were selected to receive the tender documentation electronically.

3.3Bids were sought from the four contractors based on the amended JCT Design and Build (2016) Building Contract. The tender documentation was issued to the four contractors via the Hinckley and Bosworth Borough Council’s Delta site on 15th January 2020, with a return date of 26th February 2020. The return date was later

06/16 extended to 1st April 2020 following extension requests from the tendering contractors.

3.4On the 13th February one of the bidders notified the project team that following discussions with the Regional Framework Team, due to the timescales involved and level of sub-consultant and sub-contractor design elements along with the costs associated to these, that they would decline the opportunity to tender for this project.

3.5Three contractors successfully returned their tender to the Delta site on the 1st April.

Bidder A - £4,916,205.00 *based upon a 40 weeks programme Bidder B - £5,829,059.00 *based upon a 40 weeks programme Bidder C - £5,898,749.44 based upon a 40 weeks programme

*Both Bidders A and B have stated that they think a 40-week programme is unachievable and have based their tenders on a 50-week programme.

3.6Bidder A included several clarifications and proposals in their tender submission. These have been reviewed and formal responses were issued to them on 1st May 2020. Bidder A was asked to submit their response together with an adjusted tender price by 11th May 2020.

3.7Bidder B included several proposals in their tender submission, including Value Engineering options which equate to £545,000 in savings, however many of these options would require planning approval and even if these were deliverable, it was still significantly higher than the lowest tender.

3.8The revised tender figures, to account for the adjustments made following the clarification process, are below:

Bidder A £5,070,819.24 50 weeks Bidder B £5,838,909.00 50 weeks

3.9Our finance team have conducted financial background checks on each of the tendering contractors and have confirmed all contractor reports to be acceptable. Performance Bonds or Parent Company Guarantees will also be in place to help manage any future risks.

3.10Members should note that there are outstanding risks where costs need to be added to mitigate such and professional fees etc. The table below gives detail of the likely project costs in total of £6,639,400.

Bidder A Revised tender £ 5,070,819.24 submission following receipt of tender clarifications and proposals

LCC Section 278 works, £150,000.00 LCC Fees, Design costs provisional estimate

Potential Ransom over £200,000.00 Access LCC provisional estimate

06/16 Utility Connections for 200,000.00 supply provisional estimate Landscaping costs by £200,000.00 £ 750,000.00 Green Spaces - say Provisional estimate HBBC Fees - internal and £200,000.00 consultant assuming 18 months to completion

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hinckley Crematorium Project UpdateReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hinckley and Bosworth

Search all
  1. Hinckley Crematorium Project UpdateThis decision
  2. Hinckley Crematorium Project UpdateNoted

More from Hinckley and Bosworth Scrutiny Commission

All decisions
MeetingDecisionOutcome
22 Oct 2026 Scrutiny Commission Work ProgrammeRESOLVED – (i) The additional review item into the adoption of public open space associated with housing developments... Approved Open
22 Oct 2026 Review of the council's constitutionRESOLVED - Council be recommended to approve the constitutional amendments as set out within the report. Approved Open
22 Oct 2026 Budget planRESOLVED - members noted the Budget Plan for 2027/2028. Noted Open
22 Oct 2026 Homelessness and rough sleeping strategy / local plan to end homelessness 2026-2029RESOLVED – The Scrutiny Commission: (i) Noted the progress made in developing the Homelessness and Rough Sleeping Str... Noted Open
22 Oct 2026 Rough Sleeping programme allocation 2026/27RESOLVED – The Scrutiny Commission recommended to Council that it approves acceptance of the £100,524 allocation, est... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies