RESOLVED – (i) The tender sum of £5,070,819.24 for a 50 week programme be noted; (ii) The revised budget of £6,915,000 for delivery of the scheme (£1,943,190 supplementary) be approved; (iii) The updated business case and proposed in-house management model or via a council wholly owned company (depending on the VAT response obtained from HMRC) be approved.
Word for word from the decision Hinckley and Bosworth published for this meeting.Source: moderngov.hinckley-bosworth.gov.uk
1.1This report reviews the progress of the Hinckley Crematorium project following the tender period for selection of a Main Contractor to carry out the construction phase of the project.
Recommendation
2.1That members: note the tender sum of £5,070,819.24 for a 50 week programme approve a revised budget of £6,915,000 for delivery of the scheme (£1,943,190 supplementary). approve the updated business case and proposed in-house management model or via a council wholly owned company depending on the VAT response obtained from Her Majesty's Revenue and Customs (HMRC).
3. Background to the report
3.1HBBC accessed the Procure Partnerships East Midlands Framework to select potential contractors. Our projects estimated value sat within the £4m - £12m procurement category which contained eight contractors, all of which were informed of the tender opportunity and asked if they would be interested in tendering
3.2Six contractors responded positively to the invitation to tender from the Procure Partnerships East Midlands Framework, of which four were selected to receive the tender documentation electronically.
06/16 3.3 Bids were sought from the four contractors based on the amended JCT Design and Build (2016) Building Contract. The tender documentation was issued to the four contractors via the Hinckley and Bosworth Borough Council’s Delta site on 15th January 2020, with a return date of 26th February 2020. The return date was later extended to 1st April 2020 following extension requests from the tendering contractors.
3.4On the 13th February one of the bidders notified the project team that following discussions with the Regional Framework Team, due to the timescales involved and level of sub-consultant and sub-contractor design elements along with the costs associated to these, that they would decline the opportunity to tender for this project.
3.5Three contractors successfully returned their tender to the Delta site on the 1st April.
Bidder A - £4,916,205.00 *based upon a 40 weeks programme Bidder B - £5,829,059.00 *based upon a 40 weeks programme Bidder C - £5,898,749.44 based upon a 40 weeks programme
*Both Bidders A and B have stated that they think a 40-week programme is unachievable and have based their tenders on a 50-week programme.
3.6Bidder A included several clarifications and proposals in their tender submission. These have been reviewed and formal responses were issued to them on 1st May 2020. Bidder A was asked to submit their response together with an adjusted tender price by 11th May 2020.
3.7Bidder B included several proposals in their tender submission, including Value Engineering options which equate to £545,000 in savings, however many of these options would require planning approval and even if these were deliverable, it was still significantly higher than the lowest tender.
3.8The revised tender figures, to account for the adjustments made following the clarification process, are below:
Bidder A £5,070,819.24 50 weeks Bidder B £5,838,909.00 50 weeks
3.9Our finance team have conducted financial background checks on each of the tendering contractors and have confirmed all contractor reports to be acceptable. Performance Bonds or Parent Company Guarantees will also be in place to help manage any future risks.
3.10Members should note that there are outstanding risks where costs need to be added to mitigate such and professional fees etc. The table below gives detail of the likely project costs in total of £6,639,400.
06/16 Bidder A Revised tender £ 5,070,819.24 submission following receipt of tender clarifications and proposals
Local authority housing fund - round 4RESOLVED – (i) Participation in the local authority housing fund round 4, including the acquisition of six residentia...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.