Hinckley and Bosworth Borough Council
Finance & Performance Scrutiny, Monday 10 November 2025 at 6.30pm

Frontline service review - planning

Noted Finance 1 paper

AI summaryHinckley and Bosworth Finance and Performance Scrutiny committee noted the planning service update: 81% major application processing, 84% minor, both above targets, with the five year housing land supply at 3.89 years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPlanning service performance update received by scrutiny committee
MoneyNot stated
What happens nextAppeals report due 18 December 2025Separate planning appeals report scheduled for Scrutiny Commission
Who it affectsResidents, applicants and local businessesAcross the borough, including the Earl Shilton and Barwell growth areas

What was decided

The committee noted the planning service performance report and acknowledged positive performance, recruitment improvements and forthcoming planning appeals challenges. Report 2.1, 2.2

Why

Performance is now 81% for major applications against a 60% target and 84% for minor applications against a 70% target, removing the council from risk of government designation for processing speed. Report 5.2, 5.5

Recruitment has stabilised since 2022/23, with permanent posts filled across teams and a £251,621 reduction in agency staff spending in 2024/25 compared with 2023/24. Report 4.19, 4.21, P37

A new national housing target has raised the council's requirement to 663 dwellings per year from 432, reducing the five year housing land supply to 3.89 years and triggering a new Local Plan consultation. Report 4.17, 5.14

What happens next

A separate report on planning appeals is being presented to Scrutiny Commission on 18 December 2025. Report 5.10

The second stage Regulation 18 Local Plan consultation runs from 17 October 2025 to 28 November 2025, with Regulation 19 consultation planned for Spring 2026 and submission by December 2026. Report 4.17, P80

The Earl Shilton Sustainable Urban Extension Section 106 agreement is expected to be signed by the end of December 2025. Report 4.3

The money

  • £251,621 Reduction in agency and consultant spending in 2024/25 compared with 2023/24 Report 4.21, P37
  • £1,100,477 Total planning application income in 2024/25 Report 8.1, P68
  • £82,523 Planning application income shortfall in 2024/25 against a budget of £1,183,000 Report 8.1, P68
  • £88,953 Pre-application advice income in 2024/25 against a target of £58,530 Report P68
  • £497,985 Agency staff spending in development control in 2024/25, an overspend of £63,055 Report P68
  • £2,600,011 UK Shared Prosperity Fund 2022 to 2025 allocation fully spent on 33 projects Report 4.10
  • £850,583 UK Shared Prosperity Fund 2025 to 2026 allocation delivered through 22 projects Report 4.12
  • £400k Rural England Prosperity Fund 2023 to 2025 capital funding fully spent Report 4.11

Implications

  • Financial: Planning application income fell £82,523 short of the £1,183,000 budget in 2024/25, though agency staff costs reduced by £251,621 year on year. Report 8.1, P68
  • Legal: Major application appeal performance sits at 10.0%, the government threshold, with 9 of 11 major appeals allowed between October 2022 and September 2024; the council has not been designated but remains at risk. Report 5.6, 5.7, 5.9, P50
  • Risk: Five year housing land supply has fallen to 3.89 years due to the increased housing target of 663 dwellings per year, creating a risk of speculative development and appeals. Report 5.14, P78
  • Staffing: Permanent recruitment has improved but the council still uses 0.5FTE agency cover in Development Management and 1FTE external consultant cover. Report P34, 4.21
  • Other: A new second stage Regulation 18 Local Plan consultation runs from 17 October to 28 November 2025, with submission to government targeted for December 2026. Report 4.17, P80

Who and where

  • Residents across the borough, including those in the Earl Shilton and Barwell Sustainable Urban Extension areas Report 4.3, 5.14
  • Planning applicants and developers, with 1400 applications received in 2024/25 Report 4.2, 8.1
  • Neighbourhood Plan areas, including Market Bosworth, Thornton, Bagworth and Stanton under Bardon Report 4.18
  • Local businesses supported through the Economic Development and Regeneration Team and UKSPF projects Report 4.5, 4.10

Timeline

  • June 2024: Planning Committee resolved to grant permission for up to 1,500 dwellings in the Earl Shilton SUE Report 4.3
  • 31 July to 27 September 2024: First stage Regulation 18 Local Plan consultation Report 4.15
  • December 2024: New NPPF and standard housing method published, raising housing target from 432 to 663 dwellings per year Report 4.16, 4.17
  • 17 October 2025 to 28 November 2025: Second stage Regulation 18 Local Plan consultation Report 4.17, P80
  • End of December 2025: Earl Shilton SUE Section 106 agreement expected to be signed Report 4.3
  • Spring 2026: Regulation 19 Local Plan consultation planned Report 4.17, P80
  • 18 December 2025: Separate planning appeals report scheduled for Scrutiny Commission Report 5.10
  • December 2026: Local Plan submission to MHCLG targeted Report 4.17, P80

Plain English for the jargon

  • SUE: Sustainable Urban Extension, a major planned housing development
  • NPPF: National Planning Policy Framework
  • MHCLG: Ministry of Housing, Communities and Local Government
  • UKSPF: UK Shared Prosperity Fund
  • REPF: Rural England Prosperity Fund
  • HDT: Housing Delivery Test, an annual measurement of housing delivery against targets
  • PPA: Planning Performance Agreement, an agreement for very large and complex applications
  • NDP: Neighbourhood Development Plan
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item229

Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Finance & Performance Scrutiny, 12 pages

Purpose of report

1.1To update members on the performance of the planning service.

Recommendation

2.1That the report be noted.

2.2That Members acknowledge the positive planning performance and notable achievements, the improvement in retention and recruitment across the service and the current and forthcoming challenges with regards to planning appeals.

3. Background to the report

3.1The Planning Service forms part of the Community Services Directorate. It includes the work areas development management, planning enforcement, regeneration/economic development, conservation/heritage and planning policy. This report sets out the key activities carried out by the service, how it is performing against defined indicators and the budget position.

4. Service overview

4.1The service is structured to work as three teams reporting to the Assistant Director Planning and Regeneration and Director of Community Services (Interim).

06/16 Development Management

4.2Development Management continues to receive a good mix of application types. In 2024/25 the service received 1400 (down from 1473 in 2023/24) applications of all types. This included 52 (up from 36 in 2023/24) applications for major developments, including 34 (up from 20 in 2023/24) applications for major residential development.

4.3In June 2024, Planning Committee resolved to grant permission for up to 1,500 dwellings across two planning applications that form the majority of the Earl Shilton Sustainable Urban Extension (SUE). The S106 agreement is ongoing and expecting to be signed by the end of December 2025. The ongoing application for the Barwell Sustainable Urban Extension (SUE) for 2.500 dwellings is expected to be reported back to Planning Committee for a further resolution within this current financial year.

4.4Planning enforcement continues its proactive approach to enforcement. Complaints about the service have continued to reduce with a more focused timely response on making a decision as to whether to take enforcement action.

Regeneration and Economic Development

4.5The Council’s Economic Development and Regeneration Team supports regeneration and economic regeneration in the borough.

4.6The Hinckley Public Realm Masterplan includes proposals for a Wayfinding Strategy and we are working on the implementation of the strategy, with installation of wayfinding items (signage) using funds available through the UK Shared Prosperity Fund (UKSPF), Hinckley Area Committee and Section 106 monies. A Hinckley Town Centre Masterplan, to identify key sites within the town centre and determine their feasibility for regeneration has been completed, through consultants, including a refresh of the Town Centre Vision. The Vision has received Member endorsement, and the Masterplan will form part of the Local Plan evidence base at its next stage of consultation in Spring 2026.

4.7The Economic Development and Regeneration Team promotes economic well-being for all local businesses and residents across the whole of the borough by delivering against the aims and objectives of the Council’s Economic Regeneration Strategy 2021-2025. Work has commenced on the work towards a new Economic Regeneration Strategy 2026-2030 with a business intelligence survey undertaken early 2025. Delivery is through working in partnership with local businesses, education establishments and forums to encourage networking, joint initiatives and to explore funding and training opportunities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Frontline service review: planningReport 12 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 14 attended
MS
Councillor MJ SurteesChair, apologies
PW
Councillor P WilliamsVice-Chair, in the Chair, present
DC
Councillor DS CopeCommittee Member, absent
DG
Councillor DT GlenvilleCommittee Member, apologies
LM
Councillor LJ MullaneyCommittee Member, absent
HS
Councillor H SmithCommittee Member, apologies
PS
Councillor P Stead-DavisCommittee Member, present
BS
Councillor BE SuttonCommittee Member, present
AW
Councillor A WeightmanCommittee Member, apologies
IB
Ilyas BhamOfficer, in attendance
CB
Chris BrownOfficer, in attendance
RO
Rebecca OwenOfficer, in attendance

All 14 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. Frontline service review - planningThis decision
  2. Frontline service review - Hinckley Leisure CentreAgreed
  3. Frontline service review: Street Scene ServicesDecided
  4. Frontline Service Review - Environmental ServicesNoted
  5. Frontline service review - Street Scene ServicesNoted
  6. Review of Key Frontline Services: Health & Safety EnforcementNoted

More from Hinckley and Bosworth Finance & Performance Scrutiny

All decisions
MeetingDecisionOutcome
24 Aug 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 6 July 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 11 May 2026 be confirmed as a correct record. Decided Open
6 Jul 2026 Hinckley and Bosworth UK Shared Prosperity Fund UpdateRESOLVED – the report be noted. Noted Open
6 Jul 2026 Performance and Risk Management Framework end of year summary for 2025/26RESOLVED – Members review the risks that posed the most threat to the council’s objectives and priorities and note th... Decided Open
6 Jul 2026 Business Rates and Pooling update Quarter 4 - 2025/26RESOLVED – the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies