External audit update - additional audit risk

Noted Finance 1 paper

AI summaryAudit Committee notes external auditor's report flagging a new high risk that the Housing Revenue Account land value may be materially understated, with management tasked to find any further unrecorded land.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the external auditor's update
MoneyNot stated
What happens nextManagement review of HRA landExercise to find items of HRA land not on the asset register
Who it affectsHRA land valuation and balance sheetCouncil's fixed asset register and financial statements

What was decided

The committee noted the external auditor's report on an additional significant audit risk.

Why

The external auditor identified a new significant risk after their work on asset disposals showed the Council had sold items of Housing Revenue Account land that were not recorded in the fixed asset register, meaning the HRA land value in the balance sheet may be materially understated. Report P3, P4

The auditor classed the inherent risk of material misstatement on HRA land completeness as high. Report P6

What happens next

Management is to complete an exercise to identify any other items of HRA land that are not recorded in the Council's asset management records, which the auditor will then test. Report P5, P4

Options considered

  • Chosen: Note the external auditor's update on the additional significant risk. Committee resolved to note the report.

Implications

  • Financial: HRA land value in the balance sheet may be materially understated, which could affect the accounts once the management review is complete. Report P4
  • Risk: The auditor has classed the inherent risk of material misstatement on HRA land completeness as high. Report P6

Who and where

  • The Council's Housing Revenue Account land holdings and fixed asset register Report P4, P5
  • Readers of the Council's financial statements Report P4

Timeline

  • 25 June 2025: External auditor presented the original audit plan to the Audit Committee, listing significant risks. Report P3
  • November 2025: Auditor reports an additional significant risk on completeness of HRA land to the Audit Committee. Report P2, P3

Plain English for the jargon

  • HRA: Housing Revenue Account: the council account that records income and spending on council housing.
  • Significant risk: A risk identified by the external auditor that needs special audit attention because it could lead to a material misstatement in the accounts.
  • Material misstatement: An error in the accounts large enough to influence a reader's view of the financial statements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item266

Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Audit Committee, 2 pages

Hinckley and Bosworth Borough Council Audit Committee Update – additional audit risk

November 2025

Azets > Move forward with confidence 1 Change to significant risks identified We presented our audit plan to the Audit Committee meeting on 25 June 2025. This plan included information on the significant risks we had identified for the Council as a result of our planning procedures. Since we communicated this to you, we have identified an additional significant risk relating to the completeness of HRA land.

Identified risk Planned audit procedures Completeness of HRA land Procedures performed to mitigate risks of material misstatement in this area will include: As previously communicated to the Audit Committee, we have performed testing on • Documenting our understanding of the process used by management for recording capital movements as part of our approach to rebuilding assurance on the Council’s new purchases of HRA land; balance sheet. • Reviewing the exercise undertaken by management to identify additional items of HRA land that are not currently included within the balance sheet; Our work on asset disposals identified an inconsistency between the value of assets • Testing a sample of HRA land from other source records and ensuring items have sold, and the amount of sale proceeds received. been included in the exercise completed by management; • Where HRA land has been revalued ahead of inclusion in the balance sheet we will Further investigation highlighted that the Council has sold items of HRA land which review the basis on which the valuations are carried out and challenge the key were not recorded in the Council’s fixed asset register and consequently were not assumptions applied. included in the value of assets in the balance sheet. There is a risk that the HRA land value may be materially understated.

Management is to complete an exercise to understand whether there are any other items of HRA land that are not recorded within the Council’s asset management records.

Inherent risk of material misstatement: HRA land (Completeness): High risk

Azets > Move forward with confidence 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External audit update: additional audit riskReport 2 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 20 attended
DC
Councillor DS CopeChair, present
RW
Councillor R Webber-JonesVice-Chair, present
CA
Councillor CM AllenCommittee Member, apologies
RF
Councillor REH FlemmingCommittee Member, present
SG
Councillor SM GibbensCommittee Member, present
EH
Councillor E HollickCommittee Member, present
CL
Councillor C LambertCommittee Member, present
AP
Councillor A PendleburyCommittee Member, apologies
MS
Councillor MJ SurteesCommittee Member, apologies, sent representative
BS
Councillor BE SuttonCommittee Member, present
PW
Councillor P WilliamsCommittee Member, present
RA
Councillor RG AllenCommittee Member, present as substitute

All 20 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. External audit update - additional audit riskThis decision
  2. External Audit Plan 2025/26 SummaryApproved
  3. External Audit draft Audit Completion Report year ended 31 March 2025 and Letter of RepresentationNoted
  4. External Auditor's Annual Report - Year ended 31 March 2025Noted
  5. External Audit Plan 2024/25Noted
  6. External Auditors Annual report - year ended 31 March 2024Noted

More from Hinckley and Bosworth Audit Committee

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 16 September be confirmed as a correct record. Decided Open
11 Nov 2026 Car Parks 2026/27 - Internal Audit Final ReportRESOLVED – the internal audit final report for car parks be approved. Approved Open
11 Nov 2026 Internal Audit progress reportRESOLVED – (i) The internal audit progress report be noted; (ii) Further discussion take place between the chairs of ... Noted Open
11 Nov 2026 Progress Report on the National Fraud Initiative (NFI) and any other Fraud issuesRESOLVED – the report be noted and the national report be circulated to members when available. Noted Open
11 Nov 2026 Corporate Risk Register reviewRESOLVED – the risk register be noted. Noted Open