Hinckley and Bosworth Borough Council
Audit Committee, Wednesday 27 May 2026 at 6.30pm

Internal Audit Partnership Governance 2025/26

Noted Finance 1 paper

AI summaryHinckley and Bosworth Audit Committee noted an internal audit report giving Moderate Assurance on partnership governance, with two medium priority findings on outdated partnership agreements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInternal audit report on partnership governance
MoneyNot stated
What happens next30 September 2026Deadline to update both partnership agreements
Who it affectsThree shared service partnershipsICT, Revenues and Benefits, Building Control

What was decided

The committee noted the Internal Audit Final Report on Partnership Governance 2025/26, prepared by Forvis Mazars LLP. Report P1

The committee accepted the Moderate Assurance opinion, which requires some improvements to the governance, risk management and control framework. Report P7, P43

Why

The audit reviewed governance of three key shared service partnerships: Leicestershire ICT Partnership (LICTP), Leicestershire Revenues and Benefits Partnership (LRBP), and Leicestershire Building Control Partnership (LBCP). Report P4, P10, P34

Auditors found no High Priority issues but identified two Medium Priority findings, both relating to partnership agreements that are outdated or unsigned. Report P7, P8

What happens next

The Director (Resources, Audit and Monitoring Officer) will lead work to finalise and sign a new LICTP partnership agreement and SLA by 30 September 2026, ahead of the new unitary authority formed under local government reorganisation. Report P15, P18, P19

A comprehensive review and update of the LRBP agreement will also be completed by 30 September 2026, covering the 2026/27 and 2027/28 period. Report P22, P25, P26

Options considered

  • Chosen: Continue operating under existing arrangements pending new agreements. Partners have agreed to work in good faith on the same basis as existing agreements while a new model is negotiated. Report P18

Implications

  • Legal: Absence of a signed enforceable LICTP agreement since the original 2013 agreement and 2015 Deed of Variation expired in March 2021 creates risk of unclear governance, accountability, and potential legal exposure. Report P15, P16
  • Legal: The LRBP agreement dates from April 2011 and references outdated legislation including the Data Protection Act 1998 and Accounts and Audit Regulations 2003. Report P22
  • Risk: Reliance on automatic renewal of the LRBP agreement without formal reassessment is flagged as a key root cause. Report P8, P22

Who and where

  • Leicestershire ICT Partnership (LICTP) members, HBBC and Melton Borough Council Report P10, P15
  • Leicestershire Revenues and Benefits Partnership (LRBP) members, including Harborough District Council and North West Leicestershire District Council Report P10, P22
  • Leicestershire Building Control Partnership (LBCP), led by Blaby District Council Report P10
  • Council Tax and Business Rates service users in participating authorities Report P10, P25

Timeline

  • 3 October 2025: Preliminary debrief meeting held with audit sponsor Report P11, P39
  • January 2026: Last update to LRBP cost contribution split agreed by Joint Committee Report P25
  • 26 January 2026: Draft report issued Report P1
  • 6 May 2026: Amended draft report issued Report P1
  • 12 May 2026: Final report issued Report P1
  • 27 May 2026: Audit Committee meeting
  • 30 September 2026: Target date for updated LICTP and LRBP partnership agreements Report P19, P26

Plain English for the jargon

  • LICTP: Leicestershire ICT Partnership, a shared ICT service led by HBBC for Melton Borough Council.
  • LRBP: Leicestershire Revenues and Benefits Partnership, a shared service led by HBBC covering Council Tax, Business Rates, Housing Benefit and related services.
  • LBCP: Leicestershire Building Control Partnership, led by Blaby District Council, delivering Building Regulations and Building Safety Act functions.
  • LGR: Local Government Reorganisation, the programme under which a new unitary authority is being formed.
  • DoV: Deed of Variation, a legal document amending an existing partnership agreement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

RESOLVED – the report be noted.
Word for word from the decision Hinckley and Bosworth published for this meeting. Source: moderngov.hinckley-bosworth.gov.uk

Follow this further

Built from Hinckley and Bosworth's papers

What the report saysPro

Report to Audit Committee

Hinckley and Bosworth Borough Council: Internal Audit Final Report Partnership Governance (25/26) Engagement Sponsor: Julie Kenny (Director (Resources, Audit & Monitoring Officer)) Engagement Contacts: Sally O’Hanlon (Head of Partnership), John Palmer (Strategic Head of ICT) and Chris Brown (Assistant Director Planning and Regeneration) May 2026 Reporting Timetable Amended Draft Report Issued: 06/05/2026 Debrief Meeting: 03/10/2025 Comments Received: 05/05/2026 Draft Report Issued: 26/01/2026 Final Report Issued: 12/05/2026 Contents

Your One Page Summary ....................................................................................................................................................................3 01 Introduction and Background ..........................................................................................................................................................4 02 Detailed Action Plan ........................................................................................................................................................................6 A1 Engagement Information ...............................................................................................................................................................10 Contacts .............................................................................................................................................................................................14

Disclaimer This report (“Report”) was prepared by Forvis Mazars LLP at the request of Hinckley & Bosworth Borough Council (HBBC) and terms for the preparation and scope of the Report have been agreed with them. The matters raised in this Report are only those which came to our attention during our internal audit work. Whilst every care has been taken to ensure that the information provided in this Report is as accurate as possible, Internal Audit have only been able to base findings on the information and documentation provided and consequently no complete guarantee can be given that this Report is necessarily a comprehensive statement of all the weaknesses that exist, or of all the improvements that may be required. The Report was prepared solely for the use and benefit of HBBC and to the fullest extent permitted by law Forvis Mazars LLP accepts no responsibility and disclaims all liability to any third party who purports to use or rely for any reason whatsoever on the Report, its contents, conclusions, any extract, reinterpretation, amendment and/or modification. Accordingly, any reliance placed on the Report, its contents, conclusions, any extract, reinterpretation, amendment, and/or modification by any third party is entirely at their own risk. Please refer to the Statement of Responsibility in Appendix A1 of this report for further information about responsibilities, limitations, and confidentiality.

Hinckley & Bosworth Borough Council – Partnership Governance (25/26) Internal Audit Final Report CONFIDENTIAL Page 2 Your One Page Summary Engagement Objective: To assess the adequacy and effectiveness of controls in place to maintain effective partnership relationships and outcomes of the ICT (LICTP), Revenues and Benefits (LRBP) partnerships and Leicestershire Building Control Partnership (LBCP).

Engagement rationale Why the engagement is in Your 2025/26 Plan Your Strategic Risk Your Strategic / Tactical Objective To assess the adequacy and effectiveness of Partnerships may not align with the Council’s Ensuring partnerships contribute to service controls in place to maintain effective partnership broader organisational goals, priorities, or transformation, efficiency, and customer relationships and outcomes of the ICT and statutory responsibilities. satisfaction. Revenues and Benefits partnerships.

Summary of our opinion

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Partnership Governance 2025/26Report 481 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
DC
Councillor DS CopeChair, present
DR
Councillor Dr R Webber-JonesVice-Chair, present
CA
Councillor CM AllenCommittee Member, present
RF
Councillor REH FlemmingCommittee Member, present
SG
Councillor SM GibbensCommittee Member, present
EH
Councillor E HollickCommittee Member, present
CL
Councillor C LambertCommittee Member, apologies
AP
Councillor A PendleburyCommittee Member, present
MS
Councillor MJ SurteesCommittee Member, present
BS
Councillor BE SuttonCommittee Member, present
PW
Councillor P WilliamsCommittee Member, present
CB
Charles BlackOfficer, in attendance

All 19 on the meeting page

On this subject at Hinckley and Bosworth

Search all
  1. Internal Audit Partnership Governance 2025/26This decision
  2. Car Parks 2026/27 - Internal Audit Final ReportApproved
  3. Internal Audit progress reportNoted
  4. Enforcement Action - Planning 2025/2026 - Internal Audit Final ReportApproved
  5. Internal Audit Progress report - September 2026Approved
  6. Internal Audit Annual Report 2025/2026Approved

More from Hinckley and Bosworth Audit Committee

All decisions
MeetingDecisionOutcome
11 Nov 2026 Minutes of previous meetingRESOLVED – the minutes of the meeting held on 16 September be confirmed as a correct record. Decided Open
11 Nov 2026 Car Parks 2026/27 - Internal Audit Final ReportRESOLVED – the internal audit final report for car parks be approved. Approved Open
11 Nov 2026 Internal Audit progress reportRESOLVED – (i) The internal audit progress report be noted; (ii) Further discussion take place between the chairs of ... Noted Open
11 Nov 2026 Progress Report on the National Fraud Initiative (NFI) and any other Fraud issuesRESOLVED – the report be noted and the national report be circulated to members when available. Noted Open
11 Nov 2026 Corporate Risk Register reviewRESOLVED – the risk register be noted. Noted Open